← Back
Single or multiple dwelling with stores or offices
84-01 101 AVENUE
QUEENS · BIN 4188282
💬 Discuss this project
1931Year Built
2Stories
S9Building Class
R6BZoning
3,200 sfGross Floor Area
4Units
Rent Stabilized1 Open Violation ▸FDNY Report ↗
Single or multiple dwelling with stores or offices · Owner of record: 84-01 101 AVE NY LLC · 1,942 sf lot · 1.65 FAR built · Flood zone X
Locations of Work
ArchitectureMechanicalPlumbing
Roof1p · 1 filing · 13 docs
Floor 26p · 2 filings · 20 docs
Floor 19p · 4 filings · 20 docs
Cellar4p · 2 filings · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
A TAHER CONTRACTING607/08/2026
HPD303/22/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
12/09/2021$1.0M—— → —$319/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
BANGASH ASSOCIATES INC.1410/24/2024
W.D.ROSS, R.A., P.C206/11/2024
ASHRAF CORP103/22/2023
ARQUITECTURA VARELA107/21/2021
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
SHEIKH EXPEDITING2803/21/2026
DUNBAR CONSULTANTSINC603/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
A TAHER CONTRACTING CO INGeneral Contractor1907/08/2026
LAPRIP INVESTORS INCGeneral Contractor303/21/2026
JOHNNY'S P&H CONTRAC INCPlumbing307/08/2026
G.N. CONSTRUCTION INCGeneral Contractor203/21/2026
GREAT AMERICAN CONSTR SERGeneral Contractor107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
BANGASH ASSOCIATES INC84881310/24/2024
JAY KAVI CORPORATION8500210/24/2024
BUILD-TECH CONSTRUCTION612206/11/2024
W.D.ROSS, R.A., P.C3758206/11/2024
Building Lifecycle
All (94)Filed (18)Permit Issued (17)Signed Off (8)Violation (24)Inspection (10)Objection (6)Special Inspection (11)
04/06/2026
Violation issued (FDNY_NOV, closed)
03/18/2026
Violation issued (HPD, open)
A
08/05/2025
Violation issued (FDNY_NOV, closed)
05/12/2025
Signed off — Alteration
Proposed parapet repair on existing 1-story, 2-car garage. No change in occupancy, egress, use, or bulk. Filed to address violations V 050721IMEGNCY16165; V 050321IMEGNCY16156
Q00571031-I1
11/22/2024
Signed off — Alteration
APPLICATION FILE TO INSTALL KITCHEN HOOD FOR COOKING EQUIPMENT AND PIZZA OVEN AT PARTIAL 1ST FLOOR. NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
Q01036301-I1
11/22/2024
Signed off — Alteration
APPLICATION FILE TO INTERIOR RENOVATION CELLAR THRU 2ND FLOOR AS TILES, CEILING, SHEETROCK, INSTALL SPLIT A/C UNIT (ELECTRICAL) ON THE ROOF TOP. NO CHANGE IN USE OR EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
Q00850921-I1
11/12/2024
Signed off — Alteration
INSTALLATION OF PLYWOOD FENCE AS PER PLAN. NO CHANGE IN USE,OCCUPANCY, OR EGRESS UNDER THIS APPLICATION.
Q00546985-I1
10/24/2024
Filed — Alteration
APPLICATION FILE TO INTERIOR RENOVATION CELLAR THRU 2ND FLOOR AS TILES, CEILING, SHEETROCK, INSTALL SPLIT A/C UNIT (ELECTRICAL) ON THE ROOF TOP. NO CHANGE IN USE OR EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
Q00850921-P2
09/23/2024
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
09/18/2024
Special inspection requirement — Structural Steel - Details
FAZAL BANGASH
09/18/2024
Special inspection requirement — Final
FAZAL BANGASH
09/18/2024
Special inspection requirement — Structural Stability – Alterations of existing buildings
FAZAL BANGASH
09/18/2024
Special inspection requirement — Masonry
FAZAL BANGASH
08/16/2024
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
07/31/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
FAZAL BANGASH
07/30/2024
Filed — Alteration
APPLICATION FILE TO INSTALL KITCHEN HOOD FOR COOKING EQUIPMENT AND PIZZA OVEN AT PARTIAL 1ST FLOOR. NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
Q01036301-P4
07/29/2024
Objection raised — Other
07/29/2024
Objection resolved — Addressed
07/25/2024
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
07/18/2024
Filed — Alteration
APPLICATION FILE TO INSTALL KITCHEN HOOD FOR COOKING EQUIPMENT AND PIZZA OVEN AT PARTIAL 1ST FLOOR. NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
Q01036301-P2
07/15/2024
Inspection — Fail-Final PL - Up to 3 Requested Floors
Fail
View inspection ↗
07/05/2024
Filed — Alteration
APPLICATION FILE TO INSTALL KITCHEN HOOD FOR COOKING EQUIPMENT AND PIZZA OVEN AT PARTIAL 1ST FLOOR. NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
Q01036301-P1
07/05/2024
Inspection — Certified Gas-Gas-Piping-Roughing
Certified
View inspection ↗
07/05/2024
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
07/04/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
FAZAL BANGASH
06/12/2024
Objection raised — Other
06/12/2024
Objection resolved — Addressed
06/12/2024
Objection raised — Other
06/12/2024
Objection resolved — Addressed
06/11/2024
Filed — Alteration
Proposed parapet repair on existing 1-story, 2-car garage. No change in occupancy, egress, use, or bulk. Filed to address violations V 050721IMEGNCY16165; V 050321IMEGNCY16156
Q00571031-P2
05/13/2024
Permit issued — Mechanical Systems
Q01036301-I1-MS
05/10/2024
Permit issued — Plumbing
Q01036301-S1-PL
05/06/2024
Signed off — Alteration
APPLICATION FILE TO EXTERIOR FACADE REPAIR AS FACE BRICK REPLACE, DOORS AND WINDOWS REPLACE AT WEST AND FRONT ELEVATION AS PER PLAN.
Q00890859-I1
05/05/2024
Filed — Alteration
APPLICATION FILE TO INSTALL KITCHEN HOOD FOR COOKING EQUIPMENT AND PIZZA OVEN AT PARTIAL 1ST FLOOR. NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
Q01036301-I1
05/05/2024
Signed off — Alteration
PROPOSED INSTALLATION OF PIPE SCAFFOLD FOR REMEDIAL REPAIRS AS PER PLANS. PIPE SCAFFOLD SHALL COMPLY WITH CHAPTER#33 OF 2014 THE NY BUILDING CODE. NO CHANGE IN USE OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
Q00847709-I1
05/05/2024
Filed — Alteration
APPLICATION FILE TO INSTALL KITCHEN HOOD FOR COOKING EQUIPMENT AND PIZZA OVEN AT PARTIAL 1ST FLOOR. NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
Q01036301-S1
05/02/2024
Signed off — Alteration
APPLICATION FILE TO REMOVE & CAP EXIST. BOILER AND INSTALL TANKLESS 02 COMBINATION UNITS AT 2ND FLOOR SEPARATELY TWO APARTMENTS AS PER PLAN. NO CHANGE IN USE EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
Q00853449-I1
05/02/2024
Signed off — Alteration
APPLICATION FILE TO REMOVE & CAP EXIST. BOILER AND INSTALL TANKLESS 02 COMBINATION UNITS AT 2ND FLOOR SEPARATELY TWO APARTMENTS AS PER PLAN. NO CHANGE IN USE EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
Q00853449-S1
04/20/2024
Filed — Alteration
APPLICATION FILE TO REMOVE & CAP EXIST. BOILER AND INSTALL TANKLESS 02 COMBINATION UNITS AT 2ND FLOOR SEPARATELY TWO APARTMENTS AS PER PLAN. NO CHANGE IN USE EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
Q00853449-P2
04/17/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
FAZAL BANGASH
04/12/2024
Filed — Alteration
APPLICATION FILE TO REMOVE & CAP EXIST. BOILER AND INSTALL TANKLESS 02 COMBINATION UNITS AT 2ND FLOOR SEPARATELY TWO APARTMENTS AS PER PLAN. NO CHANGE IN USE EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
Q00853449-P1
04/09/2024
Inspection — Pass-Final Boiler Equipment Inspection
Pass
View inspection ↗
04/04/2024
Permit issued — Boiler Equipment
Q00853449-S1-BE
03/27/2024
Filed — Alteration
APPLICATION FILE TO REMOVE & CAP EXIST. BOILER AND INSTALL TANKLESS 02 COMBINATION UNITS AT 2ND FLOOR SEPARATELY TWO APARTMENTS AS PER PLAN. NO CHANGE IN USE EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
Q00853449-S1
03/12/2024
Inspection — Certified Remove/Cap - work done in accordance with code
Certified
View inspection ↗
03/11/2024
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
03/07/2024
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
02/29/2024
Filed — Alteration
APPLICATION FILE TO INTERIOR RENOVATION CELLAR THRU 2ND FLOOR AS TILES, CEILING, SHEETROCK, INSTALL SPLIT A/C UNIT (ELECTRICAL) ON THE ROOF TOP. NO CHANGE IN USE OR EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
Q00850921-P1
02/27/2024
Special inspection requirement — Final
FAZAL BANGASH
02/27/2024
Special inspection requirement — Structural Stability – Alterations of existing buildings
FAZAL BANGASH
02/27/2024
Special inspection requirement — Mechanical Systems
Jay Kavi
02/27/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
FAZAL BANGASH
02/09/2024
Inspection — Certified Gas-Gas-Piping-Roughing
Certified
View inspection ↗
01/17/2024
Permit issued — Mechanical Systems
Q00850921-I1-MS
12/26/2023
Permit issued — Structural
Q00571031-I1-GC-CX
12/26/2023
Permit issued — Supported Scaffold
Q00847709-I1-SF
12/26/2023
Permit issued — General Construction
Q00890859-I1-GC
12/26/2023
Permit issued — General Construction
Q00850921-I1-GC
12/06/2023
Permit issued — Structural
Q00571031-I1-GC-CX
08/17/2023
Permit issued — General Construction
Q00850921-I1-GC
Latest 60 of 94 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWMechanical SystemsSigned-offGREAT AMERICAN CONSTR SER05/13/2024
DOB NOWPlumbingSigned-offJOHNNY NANHU05/10/2024
DOB NOWBoiler EquipmentSigned-offJOHNNY NANHU04/04/2024
DOB NOWMechanical SystemsSigned-offA TAHER CONTRACTING CO IN01/17/2024
DOB NOWStructuralSigned-offA TAHER CONTRACTING CO IN12/26/2023
DOB NOWSupported ScaffoldSigned-offA TAHER CONTRACTING CO IN12/26/2023
DOB NOWGeneral ConstructionSigned-offA TAHER CONTRACTING CO IN12/26/2023
DOB NOWGeneral ConstructionSigned-offA TAHER CONTRACTING CO IN12/26/2023
DOB NOWStructuralSigned-offA TAHER CONTRACTING CO IN12/06/2023
DOB NOWGeneral ConstructionSigned-offA TAHER CONTRACTING CO IN08/17/2023
DOB NOWGeneral ConstructionSigned-offA TAHER CONTRACTING CO IN07/06/2023
DOB NOWGeneral ConstructionSigned-offA TAHER CONTRACTING CO IN04/18/2023
DOB NOWMechanical SystemsSigned-offA TAHER CONTRACTING CO IN04/18/2023
DOB NOWPlumbingSigned-offJOHNNY NANHU04/14/2023
DOB NOWSupported ScaffoldSigned-offA TAHER CONTRACTING CO IN03/24/2023
DOB NOWStructuralSigned-offLAPRIP INVESTORS INC10/25/2021
DOB NOWConstruction FenceSigned-offEMPIRE CONSTRUCTION ASSOC07/22/2021
1 project · most recent 07/30/2024
Ventilation Systems
FiledStatusContractorScopeMake / Model / Capacity
07/30/2024Signed-offGREAT AMERICAN CONSTR SERVentilation Systems
Ventilation
Floaire BDU24 2,400 CFM · Kitchen Exhaust ×1
1 project · most recent 07/30/2024
Gas Water/Sanitary
FiledStatusContractorScope
07/30/2024Signed-offJOHNNY'S P&H CONTRAC INCGas, Water/Sanitary
1 project · most recent 07/18/2023
General Wiring
FiledStatusContractorScope
07/18/2023CompleteHI-RITE ELECTRIC CORPGeneral Wiring
▾Field Inspections (DOB CAP) — 10
DateTypeResultReport
08/16/2024Pass-Final PL - Up to 3 Requested FloorsPassView ↗
07/25/2024Pass-Final PL - Up to 3 Requested FloorsPassView ↗
07/15/2024Fail-Final PL - Up to 3 Requested FloorsFailView ↗
07/05/2024Certified Gas-Gas-Piping-RoughingCertifiedView ↗
07/05/2024Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
04/09/2024Pass-Final Boiler Equipment InspectionPassView ↗
03/12/2024Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
03/11/2024Pass-Final PL - Up to 3 Requested FloorsPassView ↗
03/07/2024Pass-Final PL - Up to 3 Requested FloorsPassView ↗
02/09/2024Certified Gas-Gas-Piping-RoughingCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 11
DateRequirementInspectorRole
09/18/2024Structural Steel - DetailsFAZAL BANGASHspecial
09/18/2024FinalFAZAL BANGASHprogress
09/18/2024Structural Stability – Alterations of existing buildingsFAZAL BANGASHspecial
09/18/2024MasonryFAZAL BANGASHspecial
07/31/2024Fire-Resistant Penetrations and JointsFAZAL BANGASHspecial
07/04/2024Fire-Resistant Penetrations and JointsFAZAL BANGASHspecial
04/17/2024Fire-Resistant Penetrations and JointsFAZAL BANGASHspecial
02/27/2024FinalFAZAL BANGASHprogress
02/27/2024Structural Stability – Alterations of existing buildingsFAZAL BANGASHspecial
02/27/2024Mechanical SystemsJay Kavispecial
02/27/2024Fire-Resistant Penetrations and JointsFAZAL BANGASHspecial
▾Documents — 58 on file (BIS + DOB NOW)
▸Plans & Drawings18
▸DOB NOWPlans/Sketch18
08/27/2026Q00546985-I1Request digital key ↗
08/25/2026Q00847709-I1Request digital key ↗
08/24/2026Q00890859-I1Request digital key ↗
Showing 3 of 18 on file for this type
▸Seals & Professional Certifications27
▸DOB NOWDPL-1: Design Professional Seal & Signature18
08/24/2026Q00890859-I1Open ↗
08/23/2026Q00850921-I1Open ↗
08/23/2026Q00850921-P2Open ↗
Showing 3 of 18 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature7
09/23/2026Q00571031-I1Open ↗
08/31/2026Q01036301-S1Open ↗
08/29/2026Q01036301-P1Open ↗
Showing 3 of 7 on file for this type
▸DOB NOWProgress Inspector Seal & Signature2
09/23/2026Q00571031-I1Open ↗
08/26/2026Q00850921-P1Open ↗
▸Environmental & Asbestos13
▸DOB NOWDEP ACP-5: Asbestos Assessment Report13
08/24/2026Q00890859-I1Open ↗
08/23/2026Q00850921-I1Open ↗
08/23/2026Q00850921-P2Open ↗
Showing 3 of 13 on file for this type