| Owner | Filings | Most Recent |
|---|---|---|
| 8441 250 LLC | 11 | 03/22/2026 |
| DGJ CONTRACTING | 1 | 03/22/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 11/14/2024 | $1.3M | — | 8441 250 LLC → Private party | $654/sf building |
| 07/23/2021 | $575K | — | — → — | $300/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| AP PROFESSIONAL ENGINEERING PLLC | 8 | 09/03/2024 |
| MOMENTUM SOLAR | 1 | 05/13/2024 |
| Representative | Filings | Most Recent |
|---|---|---|
| SANDEEP KAUR | 1 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| DGJ CONTRACTING INC | General Contractor | 4 | 07/08/2026 |
| HYDRO MECHANICAL INC | Plumbing | 2 | 07/08/2026 |
| CYM ELECTRICAL CONTRACTOR | Electrical | 1 | 03/22/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| AP PROFESSIONAL ENGINEERI | 5974 | 7 | 09/03/2024 |
| MXV SIA LLC | 9281 | 1 | 05/13/2024 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Signed-off | HYDRO MECHANICAL INC | 01/24/2024 |
| DOB NOW | Plumbing | Signed-off | HYDRO MECHANICAL INC | 01/23/2023 |
| DOB NOW | Structural | Permit Issued | DGJ CONTRACTING INC | 11/29/2022 |
| DOB NOW | Construction Fence | Signed-off | DGJ CONTRACTING INC | 11/10/2022 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/03/2024 | Signed-off | HYDRO MECHANICAL INC | Gas, Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/08/2024 | Complete | ISLAND ELECTRIC CORP | — |
| 12/15/2023 | Complete | CYM ELECTRICAL CONTRACTOR | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/03/2024 | Signed-off | HYDRO MECHANICAL INC | Wood |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/03/2024 | Signed-off | HYDRO MECHANICAL INC | Fence |
| Date | Type | Result | Report |
|---|---|---|---|
| 03/01/2024 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 02/08/2024 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 10/25/2023 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 10/18/2023 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 05/03/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 04/24/2023 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 04/12/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 02/15/2023 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 02/13/2023 | Fail-Final CND-Occupancy Inspection | Fail | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 10/01/2024 | Fire-Resistance Rated Construction | GURVINDER SINGH | progress |
| 10/01/2024 | Final | GURVINDER SINGH | progress |
| 10/01/2024 | Protection of exposed foundation insulation | GURVINDER SINGH | energy_progress |
| 10/01/2024 | Air barrier - visual inspection | GURVINDER SINGH | energy_progress |
| 10/01/2024 | Fenestration air leakage | GURVINDER SINGH | energy_progress |
| 10/01/2024 | Fenestration and door U-factor and product ratings | GURVINDER SINGH | energy_progress |
| 10/01/2024 | Structural Stability – Alterations of existing buildings | GURVINDER SINGH | special |
| 10/01/2024 | Interior lighting power | GURVINDER SINGH | energy_progress |
| 10/01/2024 | Insulation placement and R values | GURVINDER SINGH | energy_progress |
| 10/01/2024 | Fenestration areas | GURVINDER SINGH | energy_progress |
| 10/01/2024 | Fire-Resistant Penetrations and Joints | GURVINDER SINGH | special |
| 10/01/2024 | Concrete - Cast-In-Place | GURVINDER SINGH | special |
| 10/01/2024 | Footing and Foundation | GURVINDER SINGH | progress |
| 10/01/2024 | Structural Wood Frame | GURVINDER SINGH | progress |
| 10/01/2024 | Energy Code Compliance Inspections | GURVINDER SINGH | progress |
| 09/02/2024 | Concrete - Cast-In-Place | GURVINDER SINGH | special |
| 09/02/2024 | Fire-Resistant Penetrations and Joints | GURVINDER SINGH | special |
| 09/02/2024 | Structural Stability – Alterations of existing buildings | GURVINDER SINGH | special |
| 09/02/2024 | Energy Code Compliance Inspections | GURVINDER SINGH | progress |
| 09/02/2024 | Final | GURVINDER SINGH | progress |
| 09/02/2024 | Fire-Resistance Rated Construction | GURVINDER SINGH | progress |
| 09/02/2024 | Footing and Foundation | GURVINDER SINGH | progress |
| 09/02/2024 | Structural Wood Frame | GURVINDER SINGH | progress |
| 09/02/2024 | Fenestration air leakage | GURVINDER SINGH | energy_progress |
| 09/02/2024 | Protection of exposed foundation insulation | GURVINDER SINGH | energy_progress |