← Back
Two family converted from one family
84-44 121 STREET
QUEENS · BIN 4192936
💬 Discuss this project
1920Year Built
2.5Stories
B3Building Class
R4AZoning
2,338 sfGross Floor Area
2Units
1 Open Violation 0 unresolved · 1 paperwork only ▸FDNY Report ↗
Two family converted from one family · 3,420 sf lot · 0.68 FAR built · Flood zone X
Locations of Work
ArchitectureElectrical
Floor 213p · 1 filing · 20 docs
Floor 113p · 1 filing · 20 docs
Cellar13p · 1 filing · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
B BUILDERS GROUP503/22/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
07/02/2021$900K—Private party → Private party$385/sf building
02/08/2016$350K—— → —$150/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
GERALD CALIENDO ARCHITECTS311/21/2024
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
GERALD J. CALIENDO R.A., P.C.303/21/2026
GERALD J CALIENDO R A P C303/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
B BUILDERS GROUP LLCGeneral Contractor203/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
AA BUILDING & INSPECTION1519211/21/2024
Building Lifecycle
All (61)Filed (3)Permit Issued (1)Violation (15)Inspection (4)Objection (8)Special Inspection (30)
01/15/2026
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
12/19/2025
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
01/02/2025
Special inspection requirement — Fenestration air leakage
Younes Abouyaala
01/02/2025
Special inspection requirement — Protection of exposed foundation insulation
Younes Abouyaala
01/02/2025
Special inspection requirement — Fenestration and door U-factor and product ratings
Younes Abouyaala
01/02/2025
Special inspection requirement — Air barrier - visual inspection
Younes Abouyaala
01/02/2025
Special inspection requirement — Fenestration areas
Younes Abouyaala
01/02/2025
Special inspection requirement — Insulation placement and R values
Younes Abouyaala
01/02/2025
Special inspection requirement — Interior lighting power
Younes Abouyaala
01/02/2025
Special inspection requirement — Air barrier — testing
Younes Abouyaala
01/02/2025
Special inspection requirement — Fire-Resistance Rated Construction
Younes Abouyaala
01/02/2025
Special inspection requirement — Masonry
Younes Abouyaala
11/21/2024
Filed — Alteration CO
HEREWITH FILE ALTERATION TYPE ONE FOR CONVERSION FROM ONE FAMILY TO A TWO FAMILY DWELLING, HORIZONTAL EXTENSION ON FIRST FLOOR, INTERIOR RENOVATION, OBTAIN A NEW CERTIFICATE OF OCCUPANCY. SEE COMMENTS
Q01027085-P2
11/20/2024
Special inspection requirement — Masonry
Younes Abouyaala
11/20/2024
Special inspection requirement — Fire-Resistance Rated Construction
Younes Abouyaala
11/20/2024
Special inspection requirement — Protection of exposed foundation insulation
Younes Abouyaala
11/20/2024
Special inspection requirement — Air barrier — testing
Younes Abouyaala
11/20/2024
Special inspection requirement — Fenestration areas
Younes Abouyaala
11/20/2024
Special inspection requirement — Air barrier - visual inspection
Younes Abouyaala
11/20/2024
Special inspection requirement — Interior lighting power
Younes Abouyaala
11/20/2024
Special inspection requirement — Fenestration and door U-factor and product ratings
Younes Abouyaala
11/20/2024
Special inspection requirement — Insulation placement and R values
Younes Abouyaala
11/20/2024
Special inspection requirement — Fenestration air leakage
Younes Abouyaala
10/04/2024
Inspection — Certified Sprinkler-SP-Fixtures-Finish
Certified
View inspection ↗
10/01/2024
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
08/21/2024
Permit issued — General Construction
Q01027085-I1-GC
08/07/2024
Filed — Alteration CO
HEREWITH FILE ALTERATION TYPE ONE FOR CONVERSION FROM ONE FAMILY TO A TWO FAMILY DWELLING, HORIZONTAL EXTENSION ON FIRST FLOOR, INTERIOR RENOVATION, OBTAIN A NEW CERTIFICATE OF OCCUPANCY. SEE COMMENTS
Q01027085-P1
08/07/2024
Special inspection requirement — Interior lighting power
08/07/2024
Special inspection requirement — Fenestration air leakage
08/07/2024
Special inspection requirement — Insulation placement and R values
08/07/2024
Special inspection requirement — Air barrier — testing
08/07/2024
Special inspection requirement — Fenestration areas
08/07/2024
Special inspection requirement — Air barrier - visual inspection
08/07/2024
Special inspection requirement — Fenestration and door U-factor and product ratings
08/07/2024
Special inspection requirement — Protection of exposed foundation insulation
08/07/2024
Special inspection requirement — Fire-Resistance Rated Construction
08/07/2024
Special inspection requirement — Masonry
07/29/2024
Objection raised — Other
07/29/2024
Objection resolved — Addressed
07/16/2024
Objection resolved — Addressed
07/16/2024
Objection resolved — Addressed
06/20/2024
Objection resolved — Addressed
06/13/2024
Objection raised — Other
06/13/2024
Objection raised — Zoning
04/30/2024
Objection raised — Zoning
04/16/2024
Filed — Alteration CO
HEREWITH FILE ALTERATION TYPE ONE FOR CONVERSION FROM ONE FAMILY TO A TWO FAMILY DWELLING, HORIZONTAL EXTENSION ON FIRST FLOOR, INTERIOR RENOVATION, OBTAIN A NEW CERTIFICATE OF OCCUPANCY. SEE COMMENTS
Q01027085-I1
10/25/2022
Violation issued (ECB, closed)
Construction
10/25/2022
Violation issued (ECB, closed)
Quality of Life
10/25/2022
Violation issued (ECB, closed)
Quality of Life
10/25/2022
Violation issued (ECB, closed)
Quality of Life
10/25/2022
Violation issued (ECB, closed)
Construction
10/25/2022
Violation issued (ECB, closed)
Construction
10/25/2022
Violation issued (ECB, closed)
Quality of Life
10/25/2022
Violation issued (ECB, closed)
Construction
10/25/2022
Violation issued (ECB, closed)
Quality of Life
10/25/2022
Violation issued (ECB, closed)
Quality of Life
10/25/2022
Violation issued (ECB, closed)
Quality of Life
10/17/2022
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
09/15/2022
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
12/04/2018
Violation issued (ECB, closed)
Construction
Latest 60 of 61 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWGeneral ConstructionPermit IssuedB BUILDERS GROUP08/21/2024
BISPLISSUEDSUPERIOR PLUMBING & HEATING12/06/2018
BIS—ISSUEDFOREFRONT CONTRACTING INC12/03/2018
BISOTISSUEDIDEAL BUILDERS AND CONSTR04/30/2012
Nothing on file for this building.
▾Field Inspections (DOB CAP) — 4
DateTypeResultReport
01/15/2026Pass-Final CND-Occupancy InspectionPassView ↗
12/19/2025Pass-Final CND-Occupancy InspectionPassView ↗
10/04/2024Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
10/01/2024Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 30
DateRequirementInspectorRole
01/02/2025Fenestration air leakageYounes Abouyaalaenergy_progress
01/02/2025Protection of exposed foundation insulationYounes Abouyaalaenergy_progress
01/02/2025Fenestration and door U-factor and product ratingsYounes Abouyaalaenergy_progress
01/02/2025Air barrier - visual inspectionYounes Abouyaalaenergy_progress
01/02/2025Fenestration areasYounes Abouyaalaenergy_progress
01/02/2025Insulation placement and R valuesYounes Abouyaalaenergy_progress
01/02/2025Interior lighting powerYounes Abouyaalaenergy_progress
01/02/2025Air barrier — testing Younes Abouyaalaenergy_progress
01/02/2025Fire-Resistance Rated ConstructionYounes Abouyaalaprogress
01/02/2025MasonryYounes Abouyaalaspecial
11/20/2024MasonryYounes Abouyaalaspecial
11/20/2024Fire-Resistance Rated ConstructionYounes Abouyaalaprogress
11/20/2024Protection of exposed foundation insulationYounes Abouyaalaenergy_progress
11/20/2024Air barrier — testing Younes Abouyaalaenergy_progress
11/20/2024Fenestration areasYounes Abouyaalaenergy_progress
11/20/2024Air barrier - visual inspectionYounes Abouyaalaenergy_progress
11/20/2024Interior lighting powerYounes Abouyaalaenergy_progress
11/20/2024Fenestration and door U-factor and product ratingsYounes Abouyaalaenergy_progress
11/20/2024Insulation placement and R valuesYounes Abouyaalaenergy_progress
11/20/2024Fenestration air leakageYounes Abouyaalaenergy_progress
08/07/2024Interior lighting power—energy_progress
08/07/2024Fenestration air leakage—energy_progress
08/07/2024Insulation placement and R values—energy_progress
08/07/2024Air barrier — testing —energy_progress
08/07/2024Fenestration areas—energy_progress
Latest 25 of 30.
▾Documents — 80 on file (BIS + DOB NOW)
▸Plans & Drawings3
▸DOB NOWPlans/Sketch3
08/21/2026Q01027085-P1Request digital key ↗
08/21/2026Q01027085-I1Request digital key ↗
08/21/2026Q01027085-P2Request digital key ↗
▸Applications & Permits14
▸BISPLAN / WORK APPROVAL APPLICATION11
03/04/2026420362896Open ↗
02/17/2026421620240Open ↗
09/17/2025420362896Open ↗
Showing 3 of 11 on file for this type
▸BISWORK PERMIT APPLICATION3
12/18/2018421620240Open ↗
12/14/2018421620240Open ↗
05/03/2012420362896Open ↗
▸Zoning, Tax Lot & Property Records9
▸DOB NOWRestrictive Declaration/Easement 13
08/13/2026Q01027085-I1Open ↗
08/13/2026Q01027085-P1Open ↗
08/13/2026Q01027085-P2Open ↗
▸DOB NOWZD1: DOB Zoning Diagram3
08/13/2026Q01027085-P2Open ↗
08/13/2026Q01027085-P1Open ↗
08/13/2026Q01027085-I1Open ↗
▸BISTAX LOT- FINAL LOT NUMBER ISSUED1
08/15/2011420362896Open ↗
▸BISEASEMENT AND RESTRICTIVE DECLARATIONS - SUPPPORTING DOCUMENTATION1
04/08/2019420362896Open ↗
▸BISZONING DIAGRAM1
11/13/2018421620240Open ↗
▸Seals & Professional Certifications12
▸DOB NOWProgress Inspector Seal & Signature4
08/23/2026Q01027085-P2Open ↗
08/23/2026Q01027085-P2Open ↗
08/23/2026Q01027085-I1Open ↗
Showing 3 of 4 on file for this type
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION3
12/14/2018421620240Open ↗
04/13/2018421620240Open ↗
06/20/2011420362896Open ↗
▸DOB NOWDPL-1: Design Professional Seal & Signature3
08/13/2026Q01027085-I1Open ↗
08/13/2026Q01027085-P1Open ↗
08/13/2026Q01027085-P2Open ↗
▸DOB NOWSpecial Inspector Seal & Signature2
08/23/2026Q01027085-P2Open ↗
08/23/2026Q01027085-I1Open ↗
▸Trade Schedules & Equipment3
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE3
11/10/2018421620240Open ↗
09/24/2018421620240Open ↗
04/13/2018421620240Open ↗
▸Safety & Tenant Protection7
▸DOB NOWStreet Tree Checklist3
08/13/2026Q01027085-P2Open ↗
08/13/2026Q01027085-I1Open ↗
08/13/2026Q01027085-P1Open ↗
▸BISSTREET TREE CHECKLIST2
04/13/2018421620240Open ↗
06/20/2011420362896Open ↗
▸BISTenant Protection Plan and Notes1
04/13/2018421620240Open ↗
▸BISDS1-Demolition Submittal Certification Form1
12/14/2011420362896Open ↗
▸Environmental & Asbestos5
▸DOB NOWDEP ACP-5: Asbestos Assessment Report3
08/13/2026Q01027085-P1Open ↗
08/13/2026Q01027085-P2Open ↗
08/13/2026Q01027085-I1Open ↗
▸BISASBESTOS: CERTIFICATION (DEP ACP5)1
04/13/2018421620240Open ↗
▸BISTHIS IS 'NOT AN ASBESTOS PROJECT'1
06/20/2011420362896Open ↗
▸Energy Compliance2
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS1
12/14/2018421620240Open ↗
▸BISTR8: Energy Code Progress Inspections1
12/14/2011420362896Open ↗
▸Approvals, Objections & Sign-offs7
▸BISLETTERS - SUPPORTING DOCUMENTATION3
04/08/2019420362896Open ↗
05/04/2012420362896Open ↗
08/15/2011420362896Open ↗
▸BISSCHEDULE A - OCCUPANCY / USE3
06/20/2018421620240Open ↗
05/17/2018421620240Open ↗
04/13/2018421620240Open ↗
▸BISADMINISTRATIVE OBJECTIONS1
06/20/2011420362896Open ↗
▸Cost, Insurance & Ownership3
▸BISCOST AFFIDAVIT3
11/26/2018421620240Open ↗
04/13/2018421620240Open ↗
06/20/2011420362896Open ↗
▸Filing & Intake Forms3
▸BISEFILING COVER SHEET2
04/13/2018421620240Open ↗
06/20/2011420362896Open ↗
▸BISBOROUGH INTAKE FORM1
04/08/2019420362896Open ↗
▸Other Documents12
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone3
08/13/2026Q01027085-P2Open ↗
08/13/2026Q01027085-P1Open ↗
08/13/2026Q01027085-I1Open ↗
▸DOB NOWSite Survey: Initial3
08/13/2026Q01027085-P2Open ↗
08/13/2026Q01027085-P1Open ↗
08/13/2026Q01027085-I1Open ↗
▸DOB NOWPlot Diagram3
08/13/2026Q01027085-P2Open ↗
08/13/2026Q01027085-P1Open ↗
08/13/2026Q01027085-I1Open ↗
▸DOB NOWProperty Ownership Certification3
08/13/2026Q01027085-P2Open ↗
08/13/2026Q01027085-I1Open ↗
08/13/2026Q01027085-P1Open ↗