← Back
BuildNYC
Large suburban residence
84-56 260TH STREET
QUEENS · BIN 4179847
💬 Discuss this project
1950Year Built
2Stories
A3Building Class
R2AZoning
3,323 sfGross Floor Area
1Units
1 Active Violation 0 unresolved · 1 paperwork only ▸FDNY Report ↗
Large suburban residence · Owner of record: 92-22 Corona Avenue Realty · 6,240 sf lot · 0.53 FAR built · Flood zone X
Locations of Work
ArchitectureMechanicalPlumbingGeneral
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
Roof1p · 1 filing · 20 docs
Attic2p · 1 filing · 20 docs
Floor 28p · 2 filings · 20 docs
Floor 18p · 2 filings · 20 docs
Cellar8p · 2 filings · 20 docs
Site & exteriorInstallation of construction fence3p · 1 filing · 2 docs
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
01/23/2018$655K—— → —$197/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
Architectural Concept808/14/2024
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
Architectual Concept1603/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
Patti ConstructionScaffold807/08/2026
Patti ConstructionGeneral Contractor403/21/2026
Sai JI PlumbingPlumbing207/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
Architectural Concept3642908/14/2024
Triangle Inspection & Tes7495112/10/2021
Building Lifecycle
All (64)Filed (8)Permit Issued (9)Inspection (4)Objection (13)Special Inspection (30)
08/29/2025
Inspection — Certified Storm Drainage-ST-Piping-Underground
Certified
View inspection ↗
08/12/2025
Permit issued — Plumbing
Q00574529-I1-PL
08/27/2024
Objection raised — Other
08/21/2024
Special inspection requirement — HVAC-R and service water piping design and insulation
MUZAFFAR JAMAL
08/21/2024
Special inspection requirement — Energy Code Compliance Inspections
MUZAFFAR JAMAL
08/21/2024
Special inspection requirement — HVAC-R and service water heating equipment
MUZAFFAR JAMAL
08/21/2024
Special inspection requirement — Permanent certificate
MUZAFFAR JAMAL
08/21/2024
Special inspection requirement — Soil Percolation Test - Private On-Site Storm Water Drainage Disposal Systems, and Detention Facilities
Rajasekhar Sakhamuri
08/21/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
MUZAFFAR JAMAL
08/21/2024
Special inspection requirement — Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation
MUZAFFAR JAMAL
08/21/2024
Special inspection requirement — HVAC-R and service water heating system controls
MUZAFFAR JAMAL
08/21/2024
Special inspection requirement — Metering
MUZAFFAR JAMAL
08/21/2024
Special inspection requirement — Maintenance information
MUZAFFAR JAMAL
08/14/2024
Filed — ALT-CO - New Building with Existing Elements to Remain
ONE FAMILY HOUSE WITH SEPARATE GARAGE.
Q00573733-P1
08/14/2024
Filed — Alteration
Addition and alteration of one family house. Install new plumbing fixtures and related piping as per drawing.
Q00574529-P4
07/23/2024
Special inspection requirement — Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation
MUZAFFAR JAMAL
07/23/2024
Special inspection requirement — Maintenance information
MUZAFFAR JAMAL
07/23/2024
Special inspection requirement — HVAC-R and service water piping design and insulation
MUZAFFAR JAMAL
07/23/2024
Special inspection requirement — HVAC-R and service water heating system controls
MUZAFFAR JAMAL
07/23/2024
Special inspection requirement — HVAC-R and service water heating equipment
MUZAFFAR JAMAL
07/23/2024
Special inspection requirement — Permanent certificate
MUZAFFAR JAMAL
07/23/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
MUZAFFAR JAMAL
07/23/2024
Special inspection requirement — Soil Percolation Test - Private On-Site Storm Water Drainage Disposal Systems, and Detention Facilities
07/23/2024
Special inspection requirement — Energy Code Compliance Inspections
MUZAFFAR JAMAL
07/23/2024
Special inspection requirement — Metering
MUZAFFAR JAMAL
12/26/2023
Permit issued — Construction Fence
Q00574530-I1-FN
04/07/2023
Filed — Alteration
Addition and alteration of one family house. Install new plumbing fixtures and related piping as per drawing.
Q00574529-P3
03/15/2023
Permit issued — Construction Fence
Q00574530-I1-FN
02/17/2023
Filed — Alteration
Addition and alteration of one family house. Install new plumbing fixtures and related piping as per drawing.
Q00574529-P2
02/15/2023
Special inspection requirement — HVAC-R and service water piping design and insulation
MUZAFFAR JAMAL
02/15/2023
Special inspection requirement — Metering
MUZAFFAR JAMAL
02/15/2023
Special inspection requirement — HVAC-R and service water heating equipment
MUZAFFAR JAMAL
02/15/2023
Special inspection requirement — Soil Percolation Test - Private On-Site Storm Water Drainage Disposal Systems, and Detention Facilities
02/15/2023
Special inspection requirement — Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation
MUZAFFAR JAMAL
02/15/2023
Special inspection requirement — HVAC-R and service water heating system controls
MUZAFFAR JAMAL
02/15/2023
Special inspection requirement — Fire-Resistant Penetrations and Joints
MUZAFFAR JAMAL
02/15/2023
Special inspection requirement — Energy Code Compliance Inspections
MUZAFFAR JAMAL
02/15/2023
Special inspection requirement — Maintenance information
MUZAFFAR JAMAL
02/15/2023
Special inspection requirement — Permanent certificate
MUZAFFAR JAMAL
01/23/2023
Inspection — Certified Gas-Gas-Piping-Roughing
Certified
View inspection ↗
01/23/2023
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
01/23/2023
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Underground
Certified
View inspection ↗
01/07/2023
Permit issued — Mechanical Systems
Q00573733-I1-GC-CX
01/02/2023
Objection resolved — Addressed
12/13/2022
Permit issued — Construction Fence
Q00574530-I1-FN
12/10/2022
Objection raised — Scope
12/07/2022
Filed — Alteration
Addition and alteration of one family house. Install new plumbing fixtures and related piping as per drawing.
Q00574529-P1
09/30/2022
Permit issued — Plumbing
Q00574529-I1-PL
05/26/2022
Permit issued — Mechanical Systems
Q00573733-I1-GC-CX
05/18/2022
Permit issued — Construction Fence
Q00574530-I1-FN
12/16/2021
Permit issued — Construction Fence
Q00574530-I1-FN
12/11/2021
Objection raised — Scope
12/11/2021
Objection resolved — Addressed
12/11/2021
Objection raised — Inspections
12/11/2021
Objection resolved — Addressed
12/11/2021
Objection raised — Zoning
12/11/2021
Objection resolved — Addressed
12/11/2021
Objection raised — Inspections
12/11/2021
Objection resolved — Addressed
12/11/2021
Objection raised — Mechanical
Latest 60 of 64 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingPermit IssuedSai JI Plumbing08/12/2025
DOB NOWConstruction FencePermit IssuedPatti Construction12/26/2023
DOB NOWConstruction FencePermit IssuedPatti Construction03/15/2023
DOB NOWMechanical SystemsPermit IssuedPatti Construction01/07/2023
DOB NOWConstruction FencePermit IssuedPatti Construction12/13/2022
DOB NOWPlumbingPermit IssuedSai JI Plumbing09/30/2022
DOB NOWMechanical SystemsPermit IssuedPatti Construction05/26/2022
DOB NOWConstruction FencePermit IssuedPatti Construction05/18/2022
DOB NOWConstruction FencePermit IssuedPatti Construction12/16/2021
1 project · most recent 08/14/2024
Air Conditioning Systems Associated Ducts and Piping Heating Systems Ventilation Systems
FiledStatusContractorScopeMake / Model / Capacity
08/14/2024Permit IssuedPatti ConstructionAir Conditioning Systems, Associated Ducts and Piping, Heating Systems, Ventilation Systems
Cooling
Goodman GSXC18 0361B, GSXC18 0481B 36,000 BTU · Condensing Unit ×2
Heating
A.O. Smith GDHE 75 100,000 BTU · Water Heater ×1
Ventilation
Greenheck SP-C50-QD 50 CFM · Exhaust Fan ×6
SP-B90 100 CFM · Exhaust Fan ×1
Ducts & Piping
Williamson GWA 70 70,000 BTU · Boiler ×1
1 project · most recent 08/14/2024
Gas Storm Water/Sanitary
FiledStatusContractorScope
08/14/2024Permit IssuedSai JI PlumbingGas, Storm, Water/Sanitary
1 project · most recent 09/27/2022
General Wiring
FiledStatusContractorScope
09/27/2022CompleteJoseph Weinstein ElectricGeneral Wiring
1 project · most recent 08/14/2024
Wood
FiledStatusContractorScope
08/14/2024Permit IssuedPatti ConstructionWood
▾Field Inspections (DOB CAP) — 4
DateTypeResultReport
08/29/2025Certified Storm Drainage-ST-Piping-UndergroundCertifiedView ↗
01/23/2023Certified Gas-Gas-Piping-RoughingCertifiedView ↗
01/23/2023Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
01/23/2023Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 94
DateRequirementInspectorRole
08/21/2024Private On-Site Storm Water Disposal Systems-, and Detention Facilities, InstallationMUZAFFAR JAMALspecial
08/21/2024Energy Code Compliance InspectionsMUZAFFAR JAMALprogress
08/21/2024HVAC-R and service water piping design and insulationMUZAFFAR JAMALenergy_progress
08/21/2024HVAC-R and service water heating system controlsMUZAFFAR JAMALenergy_progress
08/21/2024HVAC-R and service water heating equipmentMUZAFFAR JAMALenergy_progress
08/21/2024Permanent certificateMUZAFFAR JAMALenergy_progress
08/21/2024Maintenance informationMUZAFFAR JAMALenergy_progress
08/21/2024MeteringMUZAFFAR JAMALenergy_progress
08/21/2024Soil Percolation Test - Private On-Site Storm Water Drainage Disposal Systems, and Detention FacilitiesRajasekhar Sakhamurispecial
08/21/2024Fire-Resistant Penetrations and JointsMUZAFFAR JAMALspecial
07/23/2024Permanent certificateMUZAFFAR JAMALenergy_progress
07/23/2024HVAC-R and service water heating equipmentMUZAFFAR JAMALenergy_progress
07/23/2024HVAC-R and service water piping design and insulationMUZAFFAR JAMALenergy_progress
07/23/2024HVAC-R and service water heating system controlsMUZAFFAR JAMALenergy_progress
07/23/2024MeteringMUZAFFAR JAMALenergy_progress
07/23/2024Energy Code Compliance InspectionsMUZAFFAR JAMALprogress
07/23/2024Soil Percolation Test - Private On-Site Storm Water Drainage Disposal Systems, and Detention Facilities—special
07/23/2024Private On-Site Storm Water Disposal Systems-, and Detention Facilities, InstallationMUZAFFAR JAMALspecial
07/23/2024Maintenance informationMUZAFFAR JAMALenergy_progress
07/23/2024Fire-Resistant Penetrations and JointsMUZAFFAR JAMALspecial
02/15/2023HVAC-R and service water heating system controlsMUZAFFAR JAMALenergy_progress
02/15/2023HVAC-R and service water piping design and insulationMUZAFFAR JAMALenergy_progress
02/15/2023Maintenance informationMUZAFFAR JAMALenergy_progress
02/15/2023MeteringMUZAFFAR JAMALenergy_progress
02/15/2023Energy Code Compliance InspectionsMUZAFFAR JAMALprogress
Latest 25 of 94.
▾Documents — 104 on file (BIS + DOB NOW)
▸Plans & Drawings8
▸DOB NOWPlans/Sketch8
08/26/2026Q00574530-I1Request digital key ↗
08/21/2026Q00573733-I1Request digital key ↗
08/21/2026Q00574529-P4Request digital key ↗
Showing 3 of 8 on file for this type
▸Applications & Permits3
▸BISPLAN / WORK APPROVAL APPLICATION2
10/08/2024440819465Open ↗
09/10/2024440819465Open ↗
▸BISBPP-5 - Authorization to the Department of Transportation1
11/20/2024440819465Open ↗
▸Zoning, Tax Lot & Property Records2
▸DOB NOWZD1: DOB Zoning Diagram2
08/13/2026Q00573733-I1Open ↗
08/13/2026Q00573733-P1Open ↗
▸Seals & Professional Certifications60
▸DOB NOWProgress Inspector Seal & Signature38
09/01/2026Q00574529-P4Open ↗
09/01/2026Q00574529-P4Open ↗
09/01/2026Q00574529-P4Open ↗
Showing 3 of 38 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature12
09/01/2026Q00574529-P4Open ↗
08/31/2026Q00574529-P2Open ↗
08/28/2026Q00574529-P1Open ↗
Showing 3 of 12 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature8
08/26/2026Q00574530-I1Open ↗
08/21/2026Q00573733-P1Open ↗
08/21/2026Q00573733-I1Open ↗
Showing 3 of 8 on file for this type
▸BISAPPLICANT OWNER SIGNATURE1
09/10/2024440819465Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY1
09/10/2024440819465Open ↗
▸Trade Schedules & Equipment2
▸DOB NOWDEP: Sewer Certification (Sanitary/Storm)2
08/13/2026Q00573733-I1Open ↗
08/13/2026Q00573733-P1Open ↗
▸Safety & Tenant Protection6
▸BISSTREET TREE CHECKLIST2
09/23/2024440819465Open ↗
09/10/2024440819465Open ↗
▸BISSTREET TREE SUPPORTING DOCUMENT1
10/21/2024440819465Open ↗
▸BISBPP: STREET TREES SITE PLAN1
09/23/2024440819465Open ↗
▸DOB NOWStreet Trees Site Plan1
08/13/2026Q00573733-I1Open ↗
▸DOB NOWParks Department Acknowledgment Letter for Street Trees Plan1
08/13/2026Q00573733-I1Open ↗
▸Environmental & Asbestos7
▸DOB NOWDEP ACP-5: Asbestos Assessment Report7
08/21/2026Q00573733-I1Open ↗
08/15/2026Q00573733-P1Open ↗
08/13/2026Q00574529-I1Open ↗
Showing 3 of 7 on file for this type
▸Inspections & Test Reports5
▸DOB NOWSOIL REPORT2
08/13/2026Q00573733-I1Open ↗
08/13/2026Q00573733-P1Open ↗
▸BISTECHNICAL REPORT: RESPONSIBILITY1
09/10/2024440819465Open ↗
▸DOB NOWTR4 Plot Diagram1
08/13/2026Q00573733-I1Open ↗
▸DOB NOWTR4 Test Report and Plot Diagram1
08/13/2026Q00573733-I1Open ↗
▸Filing & Intake Forms2
▸BISBPP: CHECKLIST IN LIEU OF PLANS-ALT31
09/10/2024440819465Open ↗
▸BISEFILING JOB APPLICATION COVER SHEET1
09/10/2024440819465Open ↗
▸Other Documents9
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone2
08/13/2026Q00573733-P1Open ↗
08/13/2026Q00573733-I1Open ↗
▸DOB NOWSURVEY: INITIAL2
08/13/2026Q00573733-P1Open ↗
08/13/2026Q00573733-I1Open ↗
▸BISBPP: TOPOGRAPHIC SURVEY1
10/21/2024440819465Open ↗
▸BISBPP - SUPPORTING DOCUMENTATION1
11/20/2024440819465Open ↗
▸DOB NOWProject Specific General Liability (PGL1)1
08/13/2026Q00573733-I1Open ↗
▸DOB NOWAdjoining Owners Notification1
08/13/2026Q00573733-I1Open ↗
▸DOB NOWSite Survey: Initial1
08/13/2026Q00573733-P1Open ↗