← Back
BuildNYC
Office, 20+ stories, with or without commercial
Roosevelt Building
841 BROADWAY · Greenwich Village · BIN 1080132
💬 Discuss this project
1900Year Built
21Stories
O4Building Class
C6-1Zoning
218,953 sfGross Floor Area
180Units
LL97 Covered0 Active Violations 1 old, status unconfirmed ▸FISP: SAFE
Office, 20+ stories, with or without commercial · Owner of record: 841-853 Fee Owner · 17,877 sf lot · 12.25 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralElectricalMechanicalPlumbingFire ProtectionEquipmentCivilGeneral
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
Permit Issued — active, not yet Signed-off
RoofRobinhoodUnder Construction14p · 4 filings · 20 docs
Floor 8RobinhoodUnder Construction45p · 2 filings · 13 docs
Floor 7RobinhoodUnder Construction43p · 2 filings · 13 docs
Floor 6RobinhoodUnder Construction43p · 2 filings · 13 docs
Floor 5Robinhood, DNTL BarUnder Construction45p · 4 filings · 20 docs
Floor 4Perplexity, DNTL BarUnder Construction60p · 3 filings · 20 docs
Floor 3DNTL Bar32p · 5 filings · 20 docs
Floor 2DNTL Bar28p · 8 filings · 20 docs
Floor 1Santander, DNTL Bar +3Under Construction44p · 11 filings · 20 docs
MezzanineExcelsior Dental, Maison Kayser +118p · 5 filings · 20 docs
CellarMaison Kayser3 filings · 11 docs
Site & exteriorMax Brenner25p · 5 filings · 17 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
841-853 Broadway Associates17403/21/2026
841-853 Broadway Fee Owner3103/21/2026
257 Park Avenue Associates803/21/2026
NYC School Construction Authority403/21/2026
841-853 Fee Owner303/22/2026
Maison Kayser303/21/2026
370 7th Ave Associates203/21/2026
Feil Organization203/21/2026
841-851 Broadway Associates203/21/2026
853 Broadway Association203/21/2026
841-853 BR103/21/2026
250 Park103/21/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
Goldman Copeland Associates2108/14/2026
Murray Engineering108/10/2026
Bai Group708/06/2026
Tohfaz Uddin PE208/12/2025
Mdeas Architects105/12/2025
Gilsanz Murray Steficek105/12/2025
Concessi Engineering105/02/2023
Active Design Group Engineering104/28/2023
Patuxent Engineering103/18/2022
Socotec111/11/2021
Intellect Design409/12/2021
Jose L. Pena, P.E101/11/2021
KZ Engineering208/31/2020
Studio JS2 Architect104/22/2019
Gensler103/26/2019
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
William Vitacco Associates3503/21/2026
DVA Advisors403/21/2026
Whidden Silver403/21/2026
Spring Scaffolding403/21/2026
Synergy Building Consultants203/21/2026
Socotec203/21/2026
Louis Striar203/21/2026
Concept Design Group403/21/2026
Studio JS2 Architect103/21/2026
Patuxent Engineering203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
Accord Contracting and ManagementGeneral Contractor1008/18/2026
Universal Management & ContGeneral Contractor807/08/2026
FMG General Contracting *General Contractor609/17/2026
CS BridgeScaffold507/08/2026
Structure Tek ConstructionGeneral Contractor507/08/2026
Urban IntelligenceScaffold407/08/2026
Comfort Zone Mechanicalspecialty_contractor303/21/2026
Troy ContractorGeneral Contractor303/21/2026
Sean Coakley P & HFire Protection307/08/2026
Jam Service CoPlumbing307/08/2026
Norlin Electrical ContractorsElectrical303/21/2026
Metrotech MechanicalPlumbing208/20/2026
Staten Island Electric ContElectrical203/21/2026
Marotta & Son P&H ContractingPlumbing207/08/2026
Manhattan D EnterprisesScaffold207/08/2026
New Roc ContractingGeneral Contractor207/08/2026
Universal Fire SprinklerFire Protection107/08/2026
Top Shelf ElectricElectrical103/21/2026
Michael LifrieriElectrical103/21/2026
Norlin Electrical ContractorsElectrical103/22/2026
Centennial Elevator IndustriesElectrical103/21/2026
AL-Lectric Elect'l ContractingElectrical103/21/2026
Spring ScaffoldingScaffold104/09/2026
Neptune Signs & AwningsSign hanger107/08/2026
Bedrock Plumbing & HeatingPlumbing107/08/2026
Five Borough NYCFire Protection108/21/2026
PSI PartnersFire Protection106/28/2026
Safety Fire SprinklerFire Protection107/08/2026
R.N.R. AssociatesElectrical103/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
Goldman Copeland Associates28261208/14/2026
Domani Inspection Service843708/10/2026
Gilsanz Murray Steficek240105/12/2025
Concessi Engineering540105/02/2023
Active Design Group Engineering6666104/28/2023
Socotec301111/11/2021
CDG Architects LLC /Dba1327409/12/2021
Building Lifecycle
All (253)Filed (47)Permit Issued (51)Signed Off (14)Facade (FISP) (16)Violation (60)Inspection (12)Objection (23)Special Inspection (30)
09/16/2026
Permit issued — Structural
M01405089-S2-ST
09/15/2026
Permit issued — General Construction
M01405089-I1-GC
09/12/2026
Signed off — Alteration
Inspection using industrial rope access techniques and methods. See attached plans designated primary site supervisor: Gabriel Hurtado
M01381135-I1
08/20/2026
Permit issued — Sprinklers
M01395433-S3-EW-SP
08/18/2026
Permit issued — Plumbing
M01395433-S2-PL
08/17/2026
Permit issued — General Construction
M01395433-I1-GC
08/14/2026
Filed — Alteration
Plumbing work as shown on plans filed herewith. No change in use, egress, or occupancy
M01395433-S2
08/14/2026
Filed — Alteration
Plumbing work as shown on plans filed herewith. No change in use, egress, or occupancy
M01395433-S3
08/10/2026
Filed — Alteration
Structural work as shown on plans filed herewith. No change in use, egress, or occupancy
M01405089-S2
08/10/2026
Special inspection requirement — Masonry
08/06/2026
Filed — Alteration
Plumbing work as shown on plans filed herewith. No change in use, egress, or occupancy
M01395433-I1
07/27/2026
Filed — Alteration
Structural work as shown on plans filed herewith. No change in use, egress, or occupancy
M01405089-I1
06/23/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
DANIEL COLOMBINI
06/18/2026
Signed off — Alteration
interior renovation to include demolition of existing and construction of new partitions. No change in use, egress or occupancy.
M01246052-S2
06/04/2026
Special inspection requirement — Structural Stability – Alterations of existing buildings
06/04/2026
Special inspection requirement — Structural Steel - High Strength Bolting
06/04/2026
Special inspection requirement — Structural Steel - Details
06/04/2026
Special inspection requirement — Sprayed fire-resistant materials
06/04/2026
Special inspection requirement — Structural Steel - Welding
05/20/2026
Special inspection requirement — Final
05/19/2026
Permit issued — Mechanical Systems
M01246052-S1-MS
05/19/2026
Permit issued — General Construction
M01246052-I1-GC
05/08/2026
Permit issued — General Construction
M01385345-I1-GC
05/05/2026
Signed off — Alteration
Additions/Modification to existing plumbing. No change to use, egress, or occupancy.
M08014257-I1
04/30/2026
Filed — Alteration
interior renovation to include demolition of existing partitions. No change in use, egress or occupancy.
M01385345-I1
04/30/2026
Special inspection requirement — Sprinkler Systems
DANIEL COLOMBINI
04/13/2026
Permit issued — Suspended Scaffold
M01381135-I1-SC
04/06/2026
Special inspection requirement — Sprinkler Systems
DANIEL COLOMBINI
04/06/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
DANIEL COLOMBINI
04/03/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
JOHN MCMONAGLE
04/03/2026
Special inspection requirement — Fire-Resistance Rated Construction
Michael Haack
04/03/2026
Special inspection requirement — Final
DANIEL COLOMBINI
04/03/2026
Special inspection requirement — Final
Michael Haack
04/03/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
DANIEL COLOMBINI
04/03/2026
Special inspection requirement — Mechanical Systems
DANIEL COLOMBINI
04/02/2026
Filed — Alteration
interior renovation to include demolition of existing and construction of new partitions. No change in use, egress or occupancy.
M01246052-P2
04/02/2026
Filed — Alteration
interior renovation to include demolition of existing and construction of new partitions. No change in use, egress or occupancy.
M01246052-P3
04/02/2026
Filed — Alteration
interior renovation to include demolition of existing and construction of new partitions. No change in use, egress or occupancy.
M01246052-P4
03/31/2026
Filed — Alteration
Inspection using industrial rope access techniques and methods. See attached plans designated primary site supervisor: Gabriel Hurtado
M01381135-I1
03/26/2026
Special inspection requirement — Sprinkler Systems
DANIEL COLOMBINI
03/26/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
DANIEL COLOMBINI
03/24/2026
Permit issued — General Construction
M01205637-I1-GC
03/24/2026
Permit issued — Structural
M01205637-S1-ST
02/12/2026
Inspection — Certified Remove/Cap - work done in accordance with code
Certified
View inspection ↗
02/12/2026
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
01/08/2026
Permit issued — General Construction
M01205637-I1-GC
12/01/2025
Signed off — Alteration
INSTALLATION OF TEMPORARY PLYWOOD FENCE AS PER PLAN. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.THE PLYWOOD FENCE IN FRONT OF THE MAX BRENNER CHOCOLATE BAR STORE FROM THE GROUND TO THE TOP OF THE MEZZANINE LEVEL.
M01264463-I1
11/24/2025
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
11/05/2025
Filed — Alteration
interior renovation to include demolition of existing and construction of new partitions. No change in use, egress or occupancy.
M01246052-P1
11/05/2025
Special inspection requirement — Final
DANIEL COLOMBINI
11/05/2025
Special inspection requirement — Mechanical Systems
DANIEL COLOMBINI
11/05/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
DANIEL COLOMBINI
09/04/2025
Permit issued — Plumbing
M01246052-S2-PL
08/28/2025
Permit issued — Sprinklers
M01246052-S3-EW-SP
08/13/2025
Permit issued — Mechanical Systems
M01246052-S1-MS
08/13/2025
Permit issued — General Construction
M01246052-I1-GC
08/12/2025
Filed — Alteration
INSTALLATION OF TEMPORARY PLYWOOD FENCE AS PER PLAN. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.THE PLYWOOD FENCE IN FRONT OF THE MAX BRENNER CHOCOLATE BAR STORE FROM THE GROUND TO THE TOP OF THE MEZZANINE LEVEL.
M01264463-P1
08/01/2025
Filed — Alteration
interior renovation to include demolition of existing and construction of new partitions. No change in use, egress or occupancy.
M01246052-S2
08/01/2025
Filed — Alteration
interior renovation to include demolition of existing and construction of new partitions. No change in use, egress or occupancy.
M01246052-I1
08/01/2025
Filed — Alteration
interior renovation to include demolition of existing and construction of new partitions. No change in use, egress or occupancy.
M01246052-S1
Latest 60 of 253 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWStructuralPermit IssuedFMG General Contracting *09/16/2026
DOB NOWGeneral ConstructionPermit IssuedFMG General Contracting *09/15/2026
DOB NOWSprinklersPermit IssuedFive Borough NYC08/20/2026
DOB NOWPlumbingPermit IssuedMetrotech Mechanical08/18/2026
DOB NOWGeneral ConstructionPermit IssuedAccord Contracting and Management08/17/2026
DOB NOWMechanical SystemsPermit IssuedFMG General Contracting *05/19/2026
DOB NOWGeneral ConstructionPermit IssuedFMG General Contracting *05/19/2026
DOB NOWGeneral ConstructionPermit IssuedAccord Contracting and Management05/08/2026
DOB NOWSuspended ScaffoldSigned-offStreamline Consultants NY04/13/2026
DOB NOWGeneral ConstructionPermit IssuedUniversal Management & Cont03/24/2026
DOB NOWStructuralPermit IssuedUniversal Management & Cont03/24/2026
DOB NOWGeneral ConstructionPermit IssuedUniversal Management & Cont01/08/2026
DOB NOWPlumbingSigned-offJam Service Co09/04/2025
DOB NOWSprinklersPermit IssuedMora Fire Protection08/28/2025
DOB NOWMechanical SystemsPermit IssuedFMG General Contracting *08/13/2025
DOB NOWGeneral ConstructionPermit IssuedFMG General Contracting *08/13/2025
DOB NOWConstruction FenceSigned-offSpring Scaffolding08/01/2025
DOB NOWStructuralPermit IssuedUniversal Management & Cont05/27/2025
DOB NOWGeneral ConstructionPermit IssuedUniversal Management & Cont05/14/2025
DOB NOWGeneral ConstructionPermit IssuedAccord Contracting Management06/27/2024
DOB NOWMechanical SystemsPermit IssuedAccord Contracting Management06/27/2024
DOB NOWGeneral ConstructionSigned-offStructure Tek Construction06/24/2024
DOB NOWMechanical SystemsSigned-offComfort Zone Mechanical04/04/2024
DOB NOWSprinklersPermit IssuedUniversal Fire Sprinkler04/02/2024
DOB NOWStructuralSigned-offStructure Tek Construction01/31/2024
DOB NOWSidewalk ShedSigned-offUrban Intelligence01/05/2024
DOB NOWSprinklersPermit IssuedSean Coakley P & H10/13/2023
DOB NOWGeneral ConstructionSigned-offStructure Tek Construction06/23/2023
DOB NOWMechanical SystemsPermit IssuedAccord Contracting Management05/24/2023
DOB NOWGeneral ConstructionPermit IssuedAccord Contracting Management05/24/2023
DOB NOWSidewalk ShedSigned-offUrban Intelligence05/23/2023
DOB NOWPlumbingSigned-offMetrotech Mechanical05/16/2023
DOB NOWGeneral ConstructionPermit IssuedAccord Contracting Management04/27/2023
DOB NOWMechanical SystemsPermit IssuedAccord Contracting Management04/27/2023
DOB NOWSidewalk ShedSigned-offManhattan D Enterprises03/21/2023
DOB NOWGeneral ConstructionSigned-offNew Roc Contracting01/31/2023
DOB NOWMechanical SystemsPermit IssuedUniversal Management & Cont08/25/2022
DOB NOWGeneral ConstructionPermit IssuedUniversal Management & Cont08/23/2022
DOB NOWGeneral ConstructionSigned-offNew Roc Contracting07/19/2022
DOB NOWSprinklersPermit IssuedSean Coakley P & H03/31/2022
+ 60 more permits on file
5 projects · most recent 08/14/2026
Air Conditioning Systems Ventilation Systems Others
FiledStatusContractorScopeMake / Model / Capacity
08/14/2026Permit IssuedAccord Contracting and ManagementAir Conditioning Systems, Ventilation Systems—
04/02/2026Permit IssuedFMG General Contracting *Ventilation Systems—
08/22/2022Permit IssuedUniversal Management & ContAir Conditioning Systems
Cooling
Task TGU203CAV-TOP 20 tons ×2
03/11/2020Permit IssuedTroy ContractorOthers—
11/27/2019——Others—
6 projects · most recent 08/14/2026
Sprinkler System
FiledStatusContractorScope
08/14/2026Permit IssuedFive Borough NYCSprinkler System
04/02/2026Permit IssuedPSI PartnersSprinkler System
04/24/2023Permit IssuedUniversal Fire Sprinkler—
03/15/2022Permit IssuedSean Coakley P & H234 heads
09/12/2021Permit IssuedSafety Fire Sprinkler182 heads
08/04/2021Signed-offSean Coakley P & H118 heads
2 projects · most recent 08/14/2026
Water/Sanitary
FiledStatusContractorScope
08/14/2026Permit IssuedMetrotech MechanicalWater/Sanitary
04/02/2026Signed-offJam Service CoWater/Sanitary
15 projects · most recent 08/18/2026
General Wiring
FiledStatusContractorScope
08/18/2026Permit IssuedM.O.S. Electrical ContractingGeneral Wiring
05/15/2025Permit IssuedTop Shelf Electric—
06/21/2023Permit IssuedNyco ElectricGeneral Wiring
03/23/2022Complete5 J'S Electl Conts—
03/21/2022Permit IssuedNorlin Electrical ContractorsGeneral Wiring
07/30/2020Permit IssuedNorlin Electrical Contractors—
05/29/2020CompleteNash Electric Services—
05/13/2020Permit IssuedArlington Electrical ContractingGeneral Wiring
07/05/2019CompleteTritech Electl & DataGeneral Wiring
10/30/2018CancelledAnco Electl ContctngGeneral Wiring
05/10/2018Permit IssuedHY-Lee Electric CoGeneral Wiring
04/18/2018Permit IssuedNational Maintenance—
04/18/2018Permit IssuedNational Maintenance—
04/18/2018Permit IssuedNational Maintenance—
04/12/2018CompleteNorlin Electrical ContractorsGeneral Wiring
3 projects · most recent 08/14/2026
Steel
FiledStatusContractorScope
08/14/2026Permit IssuedFive Borough NYC2 scope_items
08/10/2026Permit IssuedFMG General Contracting *Steel
05/12/2025Permit IssuedUniversal Management & ContSteel
▾Field Inspections (DOB CAP) — 12
DateTypeResultReport
02/12/2026Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
02/12/2026Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
11/24/2025Pass-Final PL - Up to 3 Requested FloorsPassView ↗
04/17/2024Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
04/15/2024Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
08/21/2023Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
05/25/2023Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
01/17/2023Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
01/17/2023Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
08/24/2022Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
12/16/2021Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
11/03/2021Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 64
DateRequirementInspectorRole
08/10/2026Masonry—special
06/23/2026Fire-Resistant Penetrations and JointsDANIEL COLOMBINIspecial
06/04/2026Structural Steel - Details—special
06/04/2026Sprayed fire-resistant materials—special
06/04/2026Structural Steel - High Strength Bolting—special
06/04/2026Structural Stability – Alterations of existing buildings—special
06/04/2026Structural Steel - Welding—special
05/20/2026Final—progress
04/30/2026Sprinkler SystemsDANIEL COLOMBINIspecial
04/06/2026Sprinkler SystemsDANIEL COLOMBINIspecial
04/06/2026Fire-Resistant Penetrations and JointsDANIEL COLOMBINIspecial
04/03/2026FinalDANIEL COLOMBINIprogress
04/03/2026Fire-Resistant Penetrations and JointsDANIEL COLOMBINIspecial
04/03/2026Mechanical SystemsDANIEL COLOMBINIspecial
04/03/2026Fire-Resistant Penetrations and JointsJOHN MCMONAGLEspecial
04/03/2026FinalMichael Haackprogress
04/03/2026Fire-Resistance Rated ConstructionMichael Haackprogress
03/26/2026Fire-Resistant Penetrations and JointsDANIEL COLOMBINIspecial
03/26/2026Sprinkler SystemsDANIEL COLOMBINIspecial
11/05/2025Fire-Resistant Penetrations and JointsDANIEL COLOMBINIspecial
11/05/2025Mechanical SystemsDANIEL COLOMBINIspecial
11/05/2025FinalDANIEL COLOMBINIprogress
04/25/2025Fire-Resistant Penetrations and JointsJOHN MCMONAGLEspecial
04/21/2025Structural Steel - DetailsKarl Rubenackerspecial
04/21/2025Structural Steel - High Strength BoltingKarl Rubenackerspecial
Latest 25 of 64.
▾Tenants in the building
TenantSpaceFloorsRenovation projects
RobinhoodOfficeFloors 5–8
Project M01395433 Alteration · Permit Entire · 08/06/2026
PerplexityOfficeFloor 4
Project M01405089 Alteration · Permit Entire · 07/27/2026
SantanderBank / Financial branchFloor 1
Project M00811947 Alteration · LOC Issued · 05/02/2023
Project M00810779 Alteration · LOC Issued · 04/28/2023
DNTL BarMedical / HealthcareFloors 1–5
Project M00445282 Alteration · LOC Issued · 01/11/2021
Excelsior DentalMedical / HealthcareFloor 1, Mezzanine
Project M00339109 Alteration · LOC Issued · 03/31/2020
Project M00327142 Alteration · Permit Entire · 03/17/2020
Project M00327108 Alteration · Permit Entire · 03/11/2020
Maison KayserRestaurant / Food ServiceCellar, Floor 1, Mezzanine
Project M00251506 Alteration · Approved · 12/09/2019
Project M00251485 Alteration · Approved · 11/27/2019
Project M00251519 Alteration · Approved · 11/27/2019
Max BrennerRestaurant / Food ServiceFloor 1, Mezzanine
Project M00116215 No Work · Objections · 04/22/2019
Names are taken automatically from the text of each project’s filed documents (title blocks and cover sheets) and screened to exclude owners, landlords and designers. They may be incomplete or wrong; check the filing.
▾Documents — 1,400 on file (BIS + DOB NOW)
▸Plans & Drawings47
▸DOB NOWPlans/Sketch32
09/03/2026M00551815-I1Request digital key ↗
09/02/2026M00682457-I1Request digital key ↗
09/02/2026M00687707-I1Request digital key ↗
Showing 3 of 32 on file for this type
▸DOB NOWPlans/Sketch - Sprinkler4
09/05/2026M00251519-I1Request digital key ↗
09/03/2026M00392088-I1Request digital key ↗
09/03/2026M00327142-I1Request digital key ↗
Showing 3 of 4 on file for this type
▸DOB NOWPlans/Sketch - Mechanical Systems3
09/05/2026M00251485-I1Request digital key ↗
09/05/2026M00327108-I1Request digital key ↗
09/03/2026M00332222-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Plumbing3
09/05/2026M00251506-I1Request digital key ↗
09/05/2026M00339109-I1Request digital key ↗
09/03/2026M00389381-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Place of Assembly2
09/05/2026M00116215-I1Request digital key ↗
08/15/2026M00145845-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Construction Fence1
09/04/2026M00353038-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Sidewalk Shed1
09/04/2026M00353034-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Sign1
09/04/2026M00445282-I1Request digital key ↗
▸Applications & Permits257
▸BISPLAN / WORK APPROVAL APPLICATION127
06/16/2021140912528Open ↗
02/16/2021140912528Open ↗
01/11/2021140912528Open ↗
Showing 3 of 127 on file for this type
▸BISWORK PERMIT APPLICATION94
04/07/2023140912528Open ↗
05/13/2020123703812Open ↗
05/13/2020123703812Open ↗
Showing 3 of 94 on file for this type
▸DOB NOWLPC Approval/Permit26
09/05/2026M00251506-I1Open ↗
08/16/2026M01405089-S2Open ↗
08/16/2026M01405089-I1Open ↗
Showing 3 of 26 on file for this type
▸BISNon-Directive 14 Construction Sign Off Including Sign Applications4
11/25/2019122444998Open ↗
Showing 1 of 4 on file for this type
▸BISCERTIFICATE OF OCCUPANCY: APPLICATION3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸BISPLACE OF ASSEMBLY3
08/28/2025104389403Open ↗
Showing 1 of 3 on file for this type
▸Seals & Professional Certifications353
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION150
05/13/2020123703812Open ↗
05/11/2020123703812Open ↗
05/11/2020123703812Open ↗
Showing 3 of 150 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature49
09/05/2026M00116215-I1Open ↗
09/05/2026M00251519-I1Open ↗
09/05/2026M00251506-I1Open ↗
Showing 3 of 49 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST44
11/27/2019123845900Open ↗
Showing 1 of 44 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT42
03/06/2020140890187Open ↗
11/27/2019123845900Open ↗
Showing 2 of 42 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature30
09/23/2026M01246052-S3Open ↗
09/23/2026M01246052-S1Open ↗
09/23/2026M01246052-S1Open ↗
Showing 3 of 30 on file for this type
▸DOB NOWProgress Inspector Seal & Signature21
09/23/2026M01246052-S1Open ↗
09/02/2026M00682315-I1Open ↗
09/02/2026M00682315-I1Open ↗
Showing 3 of 21 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM9
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 9 on file for this type
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION3
03/06/2020140890187Open ↗
Showing 1 of 3 on file for this type
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY3
03/06/2020140890187Open ↗
Showing 1 of 3 on file for this type
▸BISAPPLICANT OWNER SIGNATURE2
07/30/2020140912528Open ↗
Showing 1 of 2 on file for this type
▸Trade Schedules & Equipment116
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE35
09/10/2019122798062Open ↗
09/06/2019122798062Open ↗
08/29/2019122444998Open ↗
Showing 3 of 35 on file for this type
▸BISSELF-CERT PLUMBING NOTICE23
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 23 on file for this type
▸BISEQUIPMENT USE PERMITS15
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 15 on file for this type
▸BISEQUIPMENT USE APPLICATION/PERMIT13
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 13 on file for this type
▸BISFA - FDNY APPROVAL : FD-FAA11
08/20/2020122797562Open ↗
12/09/2019123249822Open ↗
Showing 2 of 11 on file for this type
▸BISSCHEDULE B - PLUMBING10
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 10 on file for this type
▸BISSIGN HANGER CERTIFICATE6
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 6 on file for this type
▸BISSPRINKLER INSP REPORT : FP-853
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸Safety & Tenant Protection1
▸BISTENANT PROTECTION PLAN AND NOTES1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Environmental & Asbestos112
▸BISASBESTOS: CERTIFICATION (DEP ACP5)59
02/25/2022140912528Open ↗
10/06/2021140912528Open ↗
07/27/2021140912528Open ↗
Showing 3 of 59 on file for this type
▸DOB NOWDEP ACP-5: Asbestos Assessment Report37
09/05/2026M00251519-I1Open ↗
09/05/2026M00251506-I1Open ↗
09/03/2026M00392088-I1Open ↗
Showing 3 of 37 on file for this type
▸BISTHIS IS 'NOT AN ASBESTOS PROJECT'7
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 7 on file for this type
▸DOB NOWDEP ACP-20/ACP-21: Asbestos Project Conditional Completion Form/Asbestos Project Completion Form5
08/31/2026M08013685-I1Open ↗
08/31/2026M08014298-I1Open ↗
08/31/2026M08014257-I1Open ↗
Showing 3 of 5 on file for this type
▸BISASBESTOS EXEMPTION CERTIFICATION LETTER2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISACP5 ASBESTOS: CERTIFICATION (DEP ACP5)2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸Energy Compliance82
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS44
12/06/2019122444998Open ↗
08/06/2019122878760Open ↗
07/23/2019122798071Open ↗
Showing 3 of 44 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS24
11/05/2020122444998Open ↗
10/29/2020122444998Open ↗
12/06/2019122444998Open ↗
Showing 3 of 24 on file for this type
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY5
03/06/2020140890187Open ↗
Showing 1 of 5 on file for this type
▸BISTR8: Energy Code Progress Inspections3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY FOR ENERGY CODE PROGRESS INSPECTIONS3
03/06/2020140890187Open ↗
Showing 1 of 3 on file for this type
▸BISTECHNICAL REPORT: ENERGY1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISNYCECC EXEMPTION1
07/27/2021140912528Open ↗
▸BISNYCECC ANALYSIS1
03/06/2020140890187Open ↗
▸Inspections & Test Reports23
▸BISTECHNICAL REPORT: RESPONSIBILITY15
08/28/2025104389403Open ↗
03/10/2023140912528Open ↗
03/10/2023140912528Open ↗
Showing 3 of 15 on file for this type
▸BISINSPECTION REPORT - SUPPORTING DOCUMENTATION5
12/06/2019122444998Open ↗
12/02/2019122444998Open ↗
07/19/2019121189114Open ↗
Showing 3 of 5 on file for this type
▸BISFIRE-RESISTANT PENETRATIONS AND JOINTS (FIRESTOP)1
03/10/2023140912528Open ↗
▸BISFIRE-RESISTIVE RATED CONSTRUCTION1
03/10/2023140912528Open ↗
▸BISDIR-14 ID OF RESPONSIBILITY (TR1)1
07/30/2020140912528Open ↗
▸Approvals, Objections & Sign-offs105
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST69
02/10/2021104041859Open ↗
01/13/2021121189114Open ↗
11/18/2020104041859Open ↗
Showing 3 of 69 on file for this type
▸BISADMINISTRATIVE OBJECTIONS9
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 9 on file for this type
▸BISSCHEDULE A - OCCUPANCY / USE9
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 9 on file for this type
▸BISLETTERS - SUPPORTING DOCUMENTATION8
07/19/2019121189114Open ↗
07/19/2019121189114Open ↗
07/19/2019121189114Open ↗
Showing 3 of 8 on file for this type
▸BISLANDMARKS APPROVAL6
01/13/2021140912528Open ↗
04/06/2020123703812Open ↗
03/06/2020140890187Open ↗
Showing 3 of 6 on file for this type
▸BISCONSTRUCTION CODE DETERMINATION2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISLANDMARKS SIGNOFF1
07/19/2019121189114Open ↗
▸BISSUPERSEDING LETTER1
08/29/2019122798062Open ↗
▸Cost, Insurance & Ownership125
▸BISCOST AFFIDAVIT124
01/13/2021140912528Open ↗
01/13/2021140912528Open ↗
01/11/2021140912528Open ↗
Showing 3 of 124 on file for this type
▸BISCOST AFFIDAVIT ESTIMATE: (PW3)1
06/23/2022140912528Open ↗
▸Filing & Intake Forms145
▸BISEFILING COVER SHEET70
01/30/2020123703812Open ↗
01/30/2020123703812Open ↗
11/27/2019123845900Open ↗
Showing 3 of 70 on file for this type
▸BISBOROUGH INTAKE FORM38
05/13/2020123703812Open ↗
05/11/2020123703812Open ↗
04/13/2020140890187Open ↗
Showing 3 of 38 on file for this type
▸BISADDITIONAL INFORMATION32
11/13/2025104389403Open ↗
11/13/2025104389403Open ↗
06/23/2022140912528Open ↗
Showing 3 of 32 on file for this type
▸BISEFILING JOB APPLICATION COVER SHEET5
07/30/2020140912528Open ↗
03/06/2020140890187Open ↗
Showing 2 of 5 on file for this type
▸Other Documents27
▸DOB NOWProof of Historic Building11
08/13/2026M08014206-I1Open ↗
08/13/2026M00978416-I1Open ↗
08/13/2026M08013685-I1Open ↗
Showing 3 of 11 on file for this type
▸BISEXTERNAL FORMS - SUPPORTING DOCUMENTATION8
06/23/2022140912528Open ↗
04/06/2020123703812Open ↗
07/19/2019121189114Open ↗
Showing 3 of 8 on file for this type
▸BISSupporting Document: Fee Exempt2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISPLOT DIAGRAM2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISLOFT BOARD CERTIFICATE2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸DOB NOWIRA Certification1
08/13/2026M01381135-I1Open ↗
▸DOB NOWAlternate Plan 11
08/15/2026M00145845-I1Open ↗