| Owner | Filings | Most Recent |
|---|---|---|
| RELATED MANAGEMENT | 69 | 07/08/2026 |
| 14TH STREET ASSOCIATES | 43 | 07/08/2026 |
| BTM DEVELOPMENT PARTNERS | 3 | 07/08/2026 |
| MKF MANAGEMENT | 45 | 07/08/2026 |
| STERLING UNION SQ LLC ATT | 5 | 03/22/2026 |
| 14 STREET ASSOCIATES | 11 | 03/22/2026 |
| CIRCUIT CITY INC | 5 | 03/22/2026 |
| CIRCUIT CITY STORES INC | 4 | 03/22/2026 |
| RELATED COMPANIES | 31 | 03/22/2026 |
| CIRCIT CITY / 14 STREET A | 1 | 03/22/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| GKV ARCHITECTS | 3 | 08/18/2025 |
| HBC ARCHITECTS | 1 | 07/31/2024 |
| MSM ENGINEERING SERVICES, PLLC | 1 | 06/11/2024 |
| VENTROP ENGINEERING CONSULTING GROU | 6 | 05/15/2024 |
| SOCOTEC, INC. | 1 | 04/23/2024 |
| ABS ENGINEERING, PLLC | 7 | 03/05/2024 |
| M + K DEVELOPMENT, LLC | 1 | 07/17/2023 |
| TOHFAZ UDDIN PE PC | 3 | 04/07/2022 |
| BORO ARCHITECTS LLC | 1 | 03/31/2022 |
| ENIGMA ENGINEERING PLLC | 1 | 02/23/2022 |
| JKRP ARCHITECTS | 14 | 07/09/2020 |
| MJ ENGINEERING & DESIGN | 1 | 05/06/2020 |
| MESZAROS ENGINEERING PLLC | 1 | 03/04/2020 |
| TECTONIC ENGINEERING | 2 | 05/14/2019 |
| MISRA & ASSOCIATES, P.C. | 1 | 09/27/2018 |
| LIGHT HOUSE | 1 | 06/25/2018 |
| Representative | Filings | Most Recent |
|---|---|---|
| WALTER T GORMAN PE | 24 | 03/21/2026 |
| J A EXPEDITING | 2 | 03/21/2026 |
| LOMBARDO BUILDING CONSULTANTS | 2 | 03/21/2026 |
| ROBERT S SCHNITZER | 12 | 03/21/2026 |
| HH BUILDING CONSULTING & ARCHITECTU | 2 | 03/21/2026 |
| SPRING SCAFFOLDING LLC | 4 | 03/21/2026 |
| RIZZO GROUP | 28 | 03/21/2026 |
| A1 EXPEDITING SERVICE | 2 | 03/21/2026 |
| RYBAK DEVELOPMENT | 2 | 03/21/2026 |
| SOTIR ASSOCIATES | 1 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| ICON INTERIORS INC | General Contractor | 12 | 07/08/2026 |
| INTERSYSTEM INSTALLATION | General Contractor | 10 | 07/08/2026 |
| SPRING SCAFFOLDING LLC | General Contractor | 8 | 07/08/2026 |
| PUMPING SOL PLBG & MECH I | Plumbing | 4 | 07/08/2026 |
| METRO INTERIOR CARPENTRY | General Contractor | 3 | 03/21/2026 |
| ANDAMIO SCAFFOLDING LLC | General Contractor | 3 | 03/21/2026 |
| WILLIAM C. GERAKARIS P&H | Plumbing | 2 | 07/08/2026 |
| AVRON CORP | General Contractor | 2 | 03/21/2026 |
| LINKED MECHANICAL LLC | General Contractor | 2 | 03/21/2026 |
| CLEARCOM WIRELESS SERVICE | General Contractor | 1 | 07/08/2026 |
| GARDNER, HORACE | Electrical | 1 | 03/21/2026 |
| STANDARD FIRE PROTECT LLC | Fire Protection | 1 | 07/08/2026 |
| NEWBRIDGE DATACOM, INC | General Contractor | 1 | 07/08/2026 |
| RALLY RESTORATION CORP | General Contractor | 1 | 07/08/2026 |
| WALDEN, LEE | Electrical | 1 | 03/21/2026 |
| OMD ELECTRICAL CORP | Electrical | 1 | 03/22/2026 |
| EDMUND S. JOSEPH | General Contractor | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| WALTER T. GORMAN, P.E., P | 268 | 11 | 08/18/2025 |
| COLE TECHNOLOGIES/CONTROL | 1290 | 1 | 07/31/2024 |
| VENTROP ENGINEERING CONSU | 450 | 3 | 05/15/2024 |
| SOCOTEC, INC. | 301 | 1 | 04/23/2024 |
| M + K DEVELOPMENT VENTURE | 8486 | 1 | 07/17/2023 |
| BORO ARCHITECTS LLC | 5981 | 1 | 03/31/2022 |
| ENGINEERING CONSULTING SE | 2050 | 1 | 05/06/2020 |
| MESZAROS ENGINEERING PLLC | 963 | 2 | 03/04/2020 |
| TECTONIC ENGINEERING CONS | 106 | 2 | 05/14/2019 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Signed-off | ICON INTERIORS INC | 09/05/2025 |
| DOB NOW | Suspended Scaffold | Signed-off | STRUCTUAL PRESV SYSTEM | 12/23/2024 |
| DOB NOW | Suspended Scaffold | Permit Issued | RALLY RESTORATION CORP | 08/15/2024 |
| DOB NOW | General Construction | Signed-off | AVRON CORP | 08/15/2024 |
| DOB NOW | General Construction | Signed-off | RALLY RESTORATION CORP | 07/23/2024 |
| DOB NOW | Suspended Scaffold | Signed-off | RALLY RESTORATION CORP | 06/28/2024 |
| DOB NOW | Sidewalk Shed | Signed-off | ANDAMIO SCAFFOLDING LLC | 06/11/2024 |
| DOB NOW | Plumbing | Signed-off | WILLIAM C. GERAKARIS P&H | 04/19/2024 |
| DOB NOW | Boiler Equipment | Signed-off | JAG PLUMBING & MECHANICAL | 10/23/2023 |
| DOB NOW | Plumbing | Signed-off | JAG PLUMBING & MECHANICAL | 10/17/2023 |
| DOB NOW | Plumbing | Permit Issued | JAG PLUMBING & MECHANICAL | 10/10/2023 |
| DOB NOW | General Construction | Signed-off | METRO INTERIOR CARPENTRY | 09/15/2023 |
| DOB NOW | Antenna | Signed-off | CLEARCOM WIRELESS SERVICE | 08/02/2023 |
| DOB NOW | General Construction | Permit Issued | ICON INTERIORS INC | 06/09/2023 |
| DOB NOW | Sidewalk Shed | Signed-off | SPRING SCAFFOLDING LLC | 04/10/2023 |
| DOB NOW | Mechanical Systems | Signed-off | ICON INTERIORS INC | 03/27/2023 |
| DOB NOW | General Construction | Permit Issued | ICON INTERIORS INC | 03/27/2023 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | SPRING SCAFFOLDING LLC | 02/24/2023 |
| DOB NOW | Sprinklers | Signed-off | WILLIAM C. GERAKARIS P&H | 07/29/2022 |
| DOB NOW | Plumbing | Signed-off | JAG PLUMBING & MECHANICAL | 06/08/2022 |
| DOB NOW | Sidewalk Shed | Signed-off | SPRING SCAFFOLDING LLC | 04/08/2022 |
| DOB NOW | Structural | Permit Issued | ICON INTERIORS INC | 03/22/2022 |
| DOB NOW | Mechanical Systems | Signed-off | ICON INTERIORS INC | 03/21/2022 |
| DOB NOW | Sprinklers | Signed-off | STANDARD FIRE SUPP CORP | 03/21/2022 |
| DOB NOW | General Construction | Permit Issued | ICON INTERIORS INC | 03/14/2022 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | SPRING SCAFFOLDING LLC | 03/10/2022 |
| DOB NOW | Sidewalk Shed | Signed-off | INTERSYSTEM INSTALLATION | 12/22/2020 |
| DOB NOW | Mechanical Systems | Signed-off | LINKED MECHANICAL | 03/10/2020 |
| DOB NOW | Sidewalk Shed | Signed-off | INTERSYSTEM INSTALLATION | 10/01/2019 |
| DOB NOW | Antenna | Signed-off | NEWBRIDGE DATACOM, INC | 08/14/2019 |
| DOB NOW | Sidewalk Shed | Signed-off | INTERSYSTEM INSTALLATION | 10/09/2018 |
| DOB NOW | Construction Fence | Signed-off | EDMUND S. JOSEPH | 10/02/2018 |
| DOB NOW | Sidewalk Shed | Signed-off | INTERSYSTEM INSTALLATION | 06/25/2018 |
| BIS | PL | ISSUED | KATAN P & H INC | 10/14/2020 |
| BIS | OT | ISSUED | LINKED MECHANICAL LLC | 03/12/2020 |
| BIS | OT | ISSUED | CORBEX INC | 01/23/2020 |
| BIS | OT | ISSUED | CORBEX INC | 01/23/2020 |
| BIS | MH | ISSUED | CORBEX INC | 01/23/2020 |
| BIS | OT | ISSUED | LINKED MECHANICAL LLC | 06/14/2019 |
| BIS | PL | ISSUED | KATAN P & H INC | 03/11/2019 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/06/2020 | — | — | 321 heads |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/20/2022 | Permit Issued | PUMPING SOL PLBG & MECH I | Gas, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/30/2025 | Permit Issued | UNITED ELEC & LIGHTING CO | General Wiring |
| 05/10/2024 | Complete | BOROWIDE ELECT'L CONTR'S | — |
| 11/01/2023 | Permit Issued | OMD ELECTRICAL CORP | 1 meters, 1 new_meters |
| 08/16/2023 | Complete | UNITED ELEC & LIGHTING CO | General Wiring |
| 08/02/2023 | Complete | J.A. LEE ELEC SVCS LLC | — |
| 04/07/2022 | Complete | TOP SHELF ELECTRIC CORP | — |
| 03/22/2022 | Complete | UNITED ELEC & LIGHTING CO | — |
| 10/28/2021 | Permit Issued | JAM ELECTRICAL CORP | — |
| 09/18/2019 | Complete | STEVEN FARKAS | — |
| 06/25/2018 | Complete | STEVEN FARKAS | — |
| 03/26/2018 | Complete | NEW YORK EMPIRE ELECL CON | Lighting |
| Date | Type | Result | Report |
|---|---|---|---|
| 05/20/2024 | No Access-Final Boiler Equipment Inspection | No Access | View ↗ |
| 04/05/2024 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 06/19/2023 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 06/19/2023 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 03/16/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 12/21/2022 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 12/15/2022 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 12/15/2022 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 10/04/2022 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 09/29/2022 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 07/31/2025 | Lighting controls | Walter Gorman | energy_progress |
| 07/31/2025 | Fire-Resistant Penetrations and Joints | Walter Gorman | special |
| 07/31/2025 | Tenant Protection Plan Compliance | Walter Gorman | special |
| 07/31/2025 | Interior lighting power | Walter Gorman | energy_progress |
| 07/17/2025 | Final | Walter Gorman | progress |
| 08/15/2024 | Alternative Materials - OTCR Buildings Bulletin Number | Michael Lombardo | special |
| 08/06/2024 | Alternative Materials - OTCR Buildings Bulletin Number | Michael Lombardo | special |
| 05/15/2024 | HVAC-R and service water heating system controls | Wailoon Wong | energy_progress |
| 05/15/2024 | HVAC-R and service water piping design and insulation | Wailoon Wong | energy_progress |
| 05/15/2024 | HVAC-R and service water heating equipment | Wailoon Wong | energy_progress |
| 05/15/2024 | Maintenance information | Wailoon Wong | energy_progress |
| 05/15/2024 | Tenant Protection Plan Compliance | Wailoon Wong | special |
| 05/09/2024 | HVAC-R and service water heating equipment | Wailoon Wong | energy_progress |
| 05/09/2024 | Maintenance information | Wailoon Wong | energy_progress |
| 05/09/2024 | HVAC-R and service water piping design and insulation | Wailoon Wong | energy_progress |
| 05/09/2024 | Tenant Protection Plan Compliance | Wailoon Wong | special |
| 05/09/2024 | HVAC-R and service water heating system controls | Wailoon Wong | energy_progress |
| 02/16/2024 | Post-installed Anchors | Walter Gorman | special |
| 02/16/2024 | Fire-Resistant Penetrations and Joints | Walter Gorman | special |
| 02/16/2024 | Sprinkler Systems | Walter Gorman | special |
| 01/26/2024 | Sprinkler Systems | Walter Gorman | special |
| 01/26/2024 | Post-installed Anchors | Walter Gorman | special |
| 01/26/2024 | Fire-Resistant Penetrations and Joints | Walter Gorman | special |
| 07/19/2023 | Post-installed Anchors | Walter Gorman | special |
| 07/19/2023 | Fire-Resistant Penetrations and Joints | Walter Gorman | special |