← Back
Two family converted from one family
85-15 239 STREET
QUEENS · Bellerose · BIN 4166624
💬 Discuss this project
1940Year Built
2Stories
B3Building Class
R3AZoning
2,700 sfGross Floor Area
2Units
0 Open ViolationsFDNY Report ↗
Two family converted from one family · 4,000 sf lot · 0.68 FAR built · Flood zone X
Locations of Work
ArchitectureElectricalMechanical
Floor 23p · 1 filing · 20 docs
Floor 12p · 1 filing · 20 docs
Cellar4p · 1 filing · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
SKYLARK CONSTRUCTION103/22/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
05/13/2021$500K—Private party → Private party$185/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
ARCHITECTURAL CONCEPT812/16/2025
MOMENTUM SOLAR111/24/2025
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
ARCHITECTUAL CONCEPT1603/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
SKYLARK CONSTRUCTION CORPGeneral Contractor903/21/2026
ISLAND ELECTRIC CORPElectrical103/22/2026
HORBRIDGE PLUMBING & HEATINGPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
ARCHITECTURAL CONCEPT3642612/16/2025
MXV SIA LLC9281111/24/2025
Building Lifecycle
All (73)Filed (9)Permit Issued (5)Signed Off (3)Violation (1)Inspection (9)Objection (16)Special Inspection (30)
05/01/2026
Signed off — Alteration
INSTALL NEW PLUMBING FIXTURES AND RELATED PIPING AS PER DRAWING. Energy drawings have been approved under the house application.
Q00572872-I1
04/30/2026
Objection resolved — Resolved
04/07/2026
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
03/25/2026
Signed off — Alteration
installation of solar panels, rooftop, railed, grid-tied, 30 modules, 12.3 KW
Q01323853-I1
12/26/2025
Special inspection requirement — Permanent certificate
MUZAFFAR JAMAL
12/26/2025
Special inspection requirement — Electric vehicle service equipment requirements
MUZAFFAR JAMAL
12/26/2025
Special inspection requirement — Protection of exposed foundation insulation
MUZAFFAR JAMAL
12/26/2025
Special inspection requirement — HVAC-R and service water heating equipment
MUZAFFAR JAMAL
12/26/2025
Special inspection requirement — Fenestration areas
MUZAFFAR JAMAL
12/26/2025
Special inspection requirement — Metering
MUZAFFAR JAMAL
12/26/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
MUZAFFAR JAMAL
12/26/2025
Special inspection requirement — Fireplaces
MUZAFFAR JAMAL
12/26/2025
Special inspection requirement — Mechanical Systems
MUZAFFAR JAMAL
12/26/2025
Special inspection requirement — Excavations - Sheeting, Shoring, and Bracing
MUZAFFAR JAMAL
12/26/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
MUZAFFAR JAMAL
12/26/2025
Special inspection requirement — Concrete - Cast-In-Place
MUZAFFAR JAMAL
12/26/2025
Special inspection requirement — Heating Systems
MUZAFFAR JAMAL
12/26/2025
Special inspection requirement — Masonry
MUZAFFAR JAMAL
12/26/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
MUZAFFAR JAMAL
12/26/2025
Special inspection requirement — Final
TARIQ SIDDIQUI
12/26/2025
Special inspection requirement — Footing and Foundation
MUZAFFAR JAMAL
12/26/2025
Special inspection requirement — Energy Code Compliance Inspections
MUZAFFAR JAMAL
12/26/2025
Special inspection requirement — Fire-Resistance Rated Construction
MUZAFFAR JAMAL
12/26/2025
Special inspection requirement — Ventilation and air distribution system
MUZAFFAR JAMAL
12/26/2025
Special inspection requirement — Insulation placement and R values
MUZAFFAR JAMAL
12/26/2025
Special inspection requirement — Air barrier - visual inspection
MUZAFFAR JAMAL
12/26/2025
Special inspection requirement — Fenestration air leakage
MUZAFFAR JAMAL
12/26/2025
Special inspection requirement — HVAC-R and service water heating system controls
MUZAFFAR JAMAL
12/26/2025
Special inspection requirement — Maintenance information
MUZAFFAR JAMAL
12/26/2025
Special inspection requirement — Interior lighting power
MUZAFFAR JAMAL
12/26/2025
Special inspection requirement — Fenestration and door U-factor and product ratings
MUZAFFAR JAMAL
12/16/2025
Filed — ALT-CO - New Building with Existing Elements to Remain
Addition and alteration of existing one family house to convert into two family house as per drawings herewith field.
Q00554783-P2
12/05/2025
Permit issued — Solar
Q01323853-I1-SL
11/24/2025
Filed — Alteration
installation of solar panels, rooftop, railed, grid-tied, 30 modules, 12.3 KW
Q01323853-I1
11/24/2025
Special inspection requirement — Air barrier - visual inspection
Mina Makar
11/24/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
Mina Makar
11/24/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Mina Makar
11/03/2025
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
09/06/2024
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
05/13/2024
Signed off — Alteration
Q00572871-I1
11/27/2023
Objection resolved — Addressed
08/08/2023
Permit issued — Construction Fence
Q00572871-I1-FN
06/21/2023
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
06/12/2023
Objection raised — Inspections
06/12/2023
Objection raised — Scope
06/07/2023
Filed — Alteration
APPLICATION FILLED TO INSTALL NEW CURBCUT.
Q00884145-I1
06/02/2023
Filed — ALT-CO - New Building with Existing Elements to Remain
Addition and alteration of existing one family house to convert into two family house as per drawings herewith field.
Q00554783-P1
02/16/2023
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
02/06/2023
Filed — Alteration
INSTALL NEW PLUMBING FIXTURES AND RELATED PIPING AS PER DRAWING. Energy drawings have been approved under the house application.
Q00572872-P2
01/25/2023
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
01/13/2023
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
12/28/2022
Filed — Alteration
INSTALL NEW PLUMBING FIXTURES AND RELATED PIPING AS PER DRAWING. Energy drawings have been approved under the house application.
Q00572872-P1
12/07/2022
Inspection — Fail-Final PL - Up to 3 Requested Floors
Fail
View inspection ↗
09/15/2022
Inspection — Certified Storm Drainage-ST-Piping-Underground
Certified
View inspection ↗
07/18/2022
Permit issued — Plumbing
Q00572872-I1-PL
05/03/2022
Violation issued (ECB, closed)
Construction
04/29/2022
Permit issued — Mechanical Systems
Q00554783-I1-GC-CX
04/15/2022
Permit issued — Construction Fence
Q00572871-I1-FN
03/29/2022
Filed — Alteration
Q00572871-I1
03/06/2022
Objection raised — Inspections
Latest 60 of 73 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarSigned-offMOMENTUM SOLAR12/05/2025
DOB NOWConstruction FenceSigned-offSKYLARK CONSTRUCTION CORP08/08/2023
DOB NOWPlumbingSigned-offHORBRIDGE PLUMBING & HEAT07/18/2022
DOB NOWMechanical SystemsPermit IssuedSKYLARK CONSTRUCTION CORP04/29/2022
DOB NOWConstruction FenceSigned-offSKYLARK CONSTRUCTION CORP04/15/2022
BIS—ISSUEDROBERT J. HOCHBERG, ARCHITECT10/24/1989
2 projects · most recent 11/24/2025
General Wiring
FiledStatusContractorScope
11/24/2025CompleteISLAND ELECTRIC CORP—
05/26/2022CompletePOWER SURGE ELECTRIC, INCGeneral Wiring
1 project · most recent 12/16/2025
FiledStatusContractorScope
12/16/2025Permit IssuedSKYLARK CONSTRUCTION CORP1 scope_items
▾Field Inspections (DOB CAP) — 9
DateTypeResultReport
04/07/2026Pass-Final CND-Occupancy InspectionPassView ↗
11/03/2025Pass-Final CND-Occupancy InspectionPassView ↗
09/06/2024Pass-Final CND-Occupancy InspectionPassView ↗
06/21/2023Pass-Final CND-Occupancy InspectionPassView ↗
02/16/2023Pass-Final CND-Occupancy InspectionPassView ↗
01/25/2023Pass-Final PL - Up to 3 Requested FloorsPassView ↗
01/13/2023Pass-Final PL - Up to 3 Requested FloorsPassView ↗
12/07/2022Fail-Final PL - Up to 3 Requested FloorsFailView ↗
09/15/2022Certified Storm Drainage-ST-Piping-UndergroundCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 40
DateRequirementInspectorRole
12/26/2025Permanent certificateMUZAFFAR JAMALenergy_progress
12/26/2025Electric vehicle service equipment requirementsMUZAFFAR JAMALenergy_progress
12/26/2025Protection of exposed foundation insulationMUZAFFAR JAMALenergy_progress
12/26/2025HVAC-R and service water heating equipmentMUZAFFAR JAMALenergy_progress
12/26/2025Fenestration areasMUZAFFAR JAMALenergy_progress
12/26/2025MeteringMUZAFFAR JAMALenergy_progress
12/26/2025HVAC-R and service water piping design and insulationMUZAFFAR JAMALenergy_progress
12/26/2025FireplacesMUZAFFAR JAMALenergy_progress
12/26/2025Mechanical SystemsMUZAFFAR JAMALspecial
12/26/2025Excavations - Sheeting, Shoring, and BracingMUZAFFAR JAMALspecial
12/26/2025Structural Stability – Alterations of existing buildingsMUZAFFAR JAMALspecial
12/26/2025Concrete - Cast-In-PlaceMUZAFFAR JAMALspecial
12/26/2025Heating SystemsMUZAFFAR JAMALspecial
12/26/2025MasonryMUZAFFAR JAMALspecial
12/26/2025Fire-Resistant Penetrations and JointsMUZAFFAR JAMALspecial
12/26/2025FinalTARIQ SIDDIQUIprogress
12/26/2025Footing and FoundationMUZAFFAR JAMALprogress
12/26/2025Energy Code Compliance InspectionsMUZAFFAR JAMALprogress
12/26/2025Fire-Resistance Rated ConstructionMUZAFFAR JAMALprogress
12/26/2025Ventilation and air distribution systemMUZAFFAR JAMALenergy_progress
12/26/2025Insulation placement and R valuesMUZAFFAR JAMALenergy_progress
12/26/2025Air barrier - visual inspectionMUZAFFAR JAMALenergy_progress
12/26/2025Fenestration air leakageMUZAFFAR JAMALenergy_progress
12/26/2025HVAC-R and service water heating system controlsMUZAFFAR JAMALenergy_progress
12/26/2025Maintenance informationMUZAFFAR JAMALenergy_progress
Latest 25 of 40.
▾Documents — 91 on file (BIS + DOB NOW)
▸Plans & Drawings9
▸DOB NOWPlans/Sketch9
08/27/2026Q00572872-P2Request digital key ↗
08/27/2026Q00572872-P1Request digital key ↗
08/26/2026Q00572871-I1Request digital key ↗
Showing 3 of 9 on file for this type
▸Applications & Permits3
▸BISBPP-5 - Authorization to the Department of Transportation2
06/02/2023440768108Open ↗
02/04/2023440768108Open ↗
▸BISPLAN / WORK APPROVAL APPLICATION1
02/04/2023440768108Open ↗
▸Zoning, Tax Lot & Property Records4
▸DOB NOWZD1: DOB Zoning Diagram3
08/13/2026Q00554783-I1Open ↗
08/13/2026Q00554783-P1Open ↗
08/13/2026Q00554783-P2Open ↗
▸DOB NOWHouse Number Verification: TOPO Stamp1
08/13/2026Q00554783-I1Open ↗
▸Seals & Professional Certifications43
▸DOB NOWProgress Inspector Seal & Signature24
09/02/2026Q01323853-I1Open ↗
09/02/2026Q01323853-I1Open ↗
08/28/2026Q00554783-I1Open ↗
Showing 3 of 24 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature9
08/27/2026Q00572872-P1Open ↗
08/27/2026Q00572872-I1Open ↗
08/26/2026Q00572871-I1Open ↗
Showing 3 of 9 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature9
09/02/2026Q01323853-I1Open ↗
08/28/2026Q00554783-I1Open ↗
08/28/2026Q00554783-I1Open ↗
Showing 3 of 9 on file for this type
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY1
02/04/2023440768108Open ↗
▸Trade Schedules & Equipment3
▸DOB NOWDEP: Sewer Certification (Sanitary/Storm)3
08/13/2026Q00554783-P2Open ↗
08/13/2026Q00554783-I1Open ↗
08/13/2026Q00554783-P1Open ↗
▸Safety & Tenant Protection4
▸BISSTREET TREE CHECKLIST1
06/02/2023440768108Open ↗
▸DOB NOWStreet Trees Site Plan1
08/13/2026Q00554783-I1Open ↗
▸DOB NOWParks Department Acknowledgment Letter for Street Trees Plan1
08/13/2026Q00554783-I1Open ↗
▸DOB NOWStreet Tree Sign Off1
08/13/2026Q00554783-I1Open ↗
▸Environmental & Asbestos7
▸DOB NOWDEP ACP-5: Asbestos Assessment Report7
08/27/2026Q00572872-P1Open ↗
08/18/2026Q01323853-I1Open ↗
08/15/2026Q00572872-I1Open ↗
Showing 3 of 7 on file for this type
▸Energy Compliance2
▸DOB NOWEN2: As Built Energy Analysis.2
08/15/2026Q00572872-I1Open ↗
08/13/2026Q00554783-I1Open ↗
▸Approvals, Objections & Sign-offs1
▸DOB NOWUtility Company Final Acceptance Letter1
08/13/2026Q01323853-I1Open ↗
▸Cost, Insurance & Ownership2
▸DOB NOWCertificate of Insurance1
08/13/2026Q00554783-I1Open ↗
▸DOB NOWCertification by Insurance Broker or Agency1
08/13/2026Q00554783-I1Open ↗
▸Filing & Intake Forms2
▸BISBPP: CHECKLIST IN LIEU OF PLANS-ALT31
02/04/2023440768108Open ↗
▸BISEFILING JOB APPLICATION COVER SHEET1
02/04/2023440768108Open ↗
▸Other Documents11
▸DOB NOWSite Survey: Initial3
08/13/2026Q00554783-P1Open ↗
08/13/2026Q00554783-P2Open ↗
08/13/2026Q00554783-I1Open ↗
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone3
08/13/2026Q00554783-P2Open ↗
08/13/2026Q00554783-P1Open ↗
08/13/2026Q00554783-I1Open ↗
▸BISBPP - SUPPORTING DOCUMENTATION2
06/02/2023440768108Open ↗
02/04/2023440768108Open ↗
▸DOB NOWFinal Survey1
08/13/2026Q00554783-I1Open ↗
▸DOB NOWAdjoining Owners Notification1
08/13/2026Q00554783-I1Open ↗
▸DOB NOWAdditional Insured Authorizations1
08/13/2026Q00554783-I1Open ↗