← Back
Church, synagogue, chapel
Jamaica Muslim Center
85-37 168 STREET · Name © OpenStreetMap contributors · Jamaica Hills-Briarwood · BIN 4210720
💬 Discuss this project
1996Year Built
2Stories
M1Building Class
R4AZoning
6,336 sfGross Floor Area
1Units
3 Open Violations ▸FDNY Report ↗
Church, synagogue, chapel · 10,000 sf lot · 0.63 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralMechanicalPlumbingFire ProtectionCivil
Permit Issued — active, not yet Signed-off
RoofUnder Construction23p · 2 filings · 20 docs
Floor 4Under Construction46p · 1 filing · 20 docs
Floor 3Under Construction45p · 1 filing · 20 docs
Floor 2Under Construction46p · 1 filing · 20 docs
Floor 1Under Construction45p · 1 filing · 20 docs
CellarUnder Construction38p · 3 filings · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
RAPID CONTRACTING107/11/2026
ALL OVER CONSTRUCTION407/08/2026
UGB CONSTRUCTION906/28/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
IKRA CONSULTING LLC107/06/2026
ASKON ARCHITECTS, P.C.701/21/2026
ASHRAF CORP211/09/2025
HERNANDEZ-ELI ARCHITECTURE DPC203/07/2023
GREEN DESIGN106/30/2020
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
ASKON ARCHITECTS P C403/21/2026
PT203/21/2026
ANZALONE ARCHITECTURE403/21/2026
UGB CONSTRUCTION203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
UGB CONSTRUCTION INCGeneral Contractor1006/28/2026
IR CONTRACTING INCGeneral Contractor304/09/2026
BPRT CONSTRUCTION OF NYGeneral Contractor106/27/2026
MSNP MANAGEMENT INCGeneral Contractor104/09/2026
RAPID CONTRACTING INCGeneral Contractor107/11/2026
SIMPLE AIR HVAC CORPGeneral Contractor108/07/2026
CASE PLUMBING LLCFire Protection107/04/2026
ROCK E SMALL PLBG&HTG INCPlumbing107/08/2026
ALL OVER CONSTRUCTION CORGeneral Contractor107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
HRF SERVICES CORP5616412/05/2025
NS ENGINEERS, P.C.1442111/19/2025
Building Lifecycle
All (103)Filed (13)Permit Issued (20)Signed Off (2)Violation (24)Inspection (8)Objection (6)Special Inspection (30)
08/22/2026
Inspection — Certified Remove/Cap - work done in accordance with code
Certified
View inspection ↗
08/21/2026
Inspection — Certified Sprinkler (SP) - Booster Pump Test
Certified
View inspection ↗
08/18/2026
Inspection — Certified Sprinkler-SP-Fixtures-Finish
Certified
View inspection ↗
08/12/2026
Inspection — Pass-Final PL - Underground
Pass
View inspection ↗
08/06/2026
Permit issued — Mechanical Systems
Q01085251-S4-MS
07/31/2026
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
07/10/2026
Permit issued — Supported Scaffold
Q01426381-I1-SF
07/06/2026
Filed — Alteration
INSTALLATION OF PIPE SCAFFOLDING AS PER PLANS. ALL EQUIPMENT SHALL COMPLY WITH CH #33 OF THE NYC CODE 2022. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
Q01426381-I1
06/24/2026
Permit issued — General Construction
Q01085251-I1-GC
06/22/2026
Permit issued — Sidewalk Shed
Q01270231-I1-SH
06/16/2026
Special inspection requirement — Tenant Protection Plan Compliance
05/11/2026
Permit issued — Sprinklers
Q01085251-S5-EW-SP
03/09/2026
Permit issued — General Construction
Q01085251-I1-GC
03/09/2026
Permit issued — Sidewalk Shed
Q01270231-I1-SH
02/27/2026
Special inspection requirement — Shutoff dampers
SHAHRIAR QUAYYUM
02/04/2026
Objection raised — Admin
02/04/2026
Objection raised — Scope
02/04/2026
Objection raised — Energy
02/04/2026
Objection raised — Other
01/21/2026
Filed — Alteration CO
Installation of a wet-type sprinkler system including a fire booster pump and jockey pump and controllers, flow switches and tamper switches including a 4" fire water service line and backflow preventer.
Q01085251-S3
01/20/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
12/05/2025
Filed — Alteration CO
Installation of a wet-type sprinkler system including a fire booster pump and jockey pump and controllers, flow switches and tamper switches including a 4" fire water service line and backflow preventer.
Q01085251-S4
11/25/2025
Permit issued — Supported Scaffold
Q01270231-S1-SF
11/20/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
SHAHRIAR QUAYYUM
11/20/2025
Special inspection requirement — Energy Code Compliance Inspections
SHAHRIAR QUAYYUM
11/20/2025
Special inspection requirement — Post-installed Anchors
SHAHRIAR QUAYYUM
11/20/2025
Special inspection requirement — HVAC-R and service water heating system controls
SHAHRIAR QUAYYUM
11/20/2025
Special inspection requirement — HVAC-R and service water heating equipment
SHAHRIAR QUAYYUM
11/20/2025
Special inspection requirement — Tenant Protection Plan Compliance
SHAHRIAR QUAYYUM
11/20/2025
Special inspection requirement — Maintenance information
SHAHRIAR QUAYYUM
11/20/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
SHAHRIAR QUAYYUM
11/20/2025
Special inspection requirement — Duct leakage testing, insulation and design
SHAHRIAR QUAYYUM
11/19/2025
Filed — Alteration CO
Installation of a wet-type sprinkler system including a fire booster pump and jockey pump and controllers, flow switches and tamper switches including a 4" fire water service line and backflow preventer.
Q01085251-S5
11/09/2025
Filed — Alteration
INSTALLATION OF MEDIUM DUTY PIPE SCAFFOLD.
Q01270231-S1
09/29/2025
Permit issued — Structural
Q01085251-S1-ST
09/29/2025
Permit issued — Sidewalk Shed
Q01270231-I1-SH
09/26/2025
Permit issued — General Construction
Q01085251-I1-GC
09/18/2025
Permit issued — Sidewalk Shed
Q01270231-I1-SH
08/15/2025
Permit issued — Sidewalk Shed
Q01270231-I1-SH
08/12/2025
Filed — Alteration
INSTALLATION OF MEDIUM DUTY PIPE SCAFFOLD.
Q01270231-I1
05/29/2025
Permit issued — Structural
Q01085251-S1-ST
05/21/2025
Permit issued — General Construction
Q01085251-I1-GC
05/08/2025
Permit issued — Earth Work
Q01085251-S2-FO-EA
04/18/2025
Permit issued — General Construction
Q01085251-I1-GC
02/26/2025
Special inspection requirement — Concrete - Cast-In-Place
FAHAD FATEH
02/26/2025
Special inspection requirement — Exterior lighting power
FAHAD FATEH
02/26/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
FAHAD FATEH
02/26/2025
Special inspection requirement — Air barrier - visual inspection
FAHAD FATEH
02/26/2025
Special inspection requirement — Fenestration areas
FAHAD FATEH
02/26/2025
Special inspection requirement — Lighting controls
FAHAD FATEH
02/26/2025
Special inspection requirement — Energy Code Compliance Inspections
FAHAD FATEH
02/26/2025
Special inspection requirement — Fenestration and door U-factor and product ratings
FAHAD FATEH
02/26/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
FAHAD FATEH
02/26/2025
Special inspection requirement — Tenant Protection Plan Compliance
FAHAD FATEH
02/26/2025
Special inspection requirement — Masonry
FAHAD FATEH
02/26/2025
Special inspection requirement — Fenestration air leakage
FAHAD FATEH
02/26/2025
Special inspection requirement — Fire-Resistance Rated Construction
FAHAD FATEH
02/26/2025
Special inspection requirement — Interior lighting power
FAHAD FATEH
02/26/2025
Special inspection requirement — Insulation placement and R values
FAHAD FATEH
02/04/2025
Filed — Alteration CO
Installation of a wet-type sprinkler system including a fire booster pump and jockey pump and controllers, flow switches and tamper switches including a 4" fire water service line and backflow preventer.
Q01085251-P1
Latest 60 of 103 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWMechanical SystemsPermit IssuedSIMPLE AIR HVAC CORP08/06/2026
DOB NOWSupported ScaffoldPermit IssuedRAPID CONTRACTING INC07/10/2026
DOB NOWGeneral ConstructionPermit IssuedBPRT CONSTRUCTION OF NY06/24/2026
DOB NOWSidewalk ShedPermit IssuedUGB CONSTRUCTION INC06/22/2026
DOB NOWSprinklersPermit IssuedCASE PLUMBING LLC05/11/2026
DOB NOWGeneral ConstructionPermit IssuedUGB CONSTRUCTION INC03/09/2026
DOB NOWSidewalk ShedPermit IssuedUGB CONSTRUCTION INC03/09/2026
DOB NOWSupported ScaffoldPermit IssuedUGB CONSTRUCTION INC11/25/2025
DOB NOWStructuralPermit IssuedIR CONTRACTING INC09/29/2025
DOB NOWSidewalk ShedPermit IssuedIR CONTRACTING INC09/29/2025
DOB NOWGeneral ConstructionPermit IssuedIR CONTRACTING INC09/26/2025
DOB NOWSidewalk ShedPermit IssuedUGB CONSTRUCTION INC09/18/2025
DOB NOWSidewalk ShedPermit IssuedUGB CONSTRUCTION INC08/15/2025
DOB NOWStructuralPermit IssuedUGB CONSTRUCTION INC05/29/2025
DOB NOWGeneral ConstructionPermit IssuedUGB CONSTRUCTION INC05/21/2025
DOB NOWEarth WorkPermit IssuedUGB CONSTRUCTION INC05/08/2025
DOB NOWGeneral ConstructionPermit IssuedUGB CONSTRUCTION INC04/18/2025
DOB NOWPlumbingSigned-offROCK E SMALL PLBG&HTG INC03/29/2023
DOB NOWGeneral ConstructionSigned-offMSNP MANAGEMENT INC03/28/2023
DOB NOWSupported ScaffoldPermit IssuedALL OVER CONSTRUCTION COR07/02/2020
BISOTISSUEDALL OVER CONSTRUCTION COR07/09/2020
BISOTISSUEDALL OVER CONSTRUCTION COR07/08/2020
BISPLISSUEDZONE PLUMBING & HEATING C04/05/2017
BISOTISSUEDATCO RESTORATION INC03/30/2017
BISOTISSUEDAGO & ALAUDIN GENERAL CON07/01/2014
BISPLISSUEDAVON PLBG & HTG INC04/23/2004
BISFPISSUEDMEGA FIRE PROTECTION INC09/08/2003
BISEQISSUEDJ AND I CONSTRUCTION CORP12/17/2002
BIS—ISSUEDJ AND I CONSTRUCTION CORP12/17/2002
BISPLISSUEDAVON PLBG & HTG INC08/12/2002
BIS—ISSUEDJ AND I CONSTRUCTION CORP11/09/2001
BISEQISSUEDJ AND I CONSTRUCTION CORP09/24/2001
BISEQISSUEDJ&I CONSTRUCTION CORP.11/22/1996
BISCCISSUEDJ&I CONSTRUCTION CORP.11/22/1996
BISCCISSUEDJ & I CONSTRUCTION CORPORATION02/28/1996
BISMHISSUEDJ & I CONSTRUCTION CORPORATION02/28/1996
BISPLISSUEDAVON PLBG & HTG INC02/05/1996
BIS—ISSUEDJ & I CONST.07/11/1995
BIS—ISSUEDJ & I CONST.10/21/1994
BISEQISSUEDNOSTRAND CONTRACTING CORP09/16/1994
1 project · most recent 01/21/2026
Sprinkler System
FiledStatusContractorScope
01/21/2026Permit IssuedCASE PLUMBING LLCSprinkler System
5 projects · most recent 12/20/2025
General Wiring
FiledStatusContractorScope
12/20/2025Permit IssuedEXPERT ELECTRIC.CONT NY IGeneral Wiring
12/16/2025Permit IssuedEXPERT ELECTRIC.CONT NY I—
08/14/2025Permit IssuedRICHARD NEU—
06/11/2025CompleteEXPERT ELECTRIC.CONT NY I—
06/04/2023CompleteAYYUB ELECTRIC CORPGeneral Wiring
3 projects · most recent 07/06/2026
Scaffold Sidewalk Shed
FiledStatusContractorScope
07/06/2026Permit IssuedRAPID CONTRACTING INCScaffold
11/09/2025Permit IssuedUGB CONSTRUCTION INCScaffold, Sidewalk Shed
06/30/2020Permit IssuedALL OVER CONSTRUCTION CORScaffold
▾Field Inspections (DOB CAP) — 8
DateTypeResultReport
08/22/2026Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
08/21/2026Certified Sprinkler (SP) - Booster Pump TestCertifiedView ↗
08/18/2026Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
08/12/2026Pass-Final PL - UndergroundPassView ↗
07/31/2026Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
06/07/2023Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
06/02/2023Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
06/01/2023Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 61
DateRequirementInspectorRole
06/16/2026Tenant Protection Plan Compliance—special
02/27/2026Shutoff dampersSHAHRIAR QUAYYUMenergy_progress
01/20/2026Fire-Resistant Penetrations and Joints—special
11/20/2025Duct leakage testing, insulation and designSHAHRIAR QUAYYUMenergy_progress
11/20/2025HVAC-R and service water heating system controlsSHAHRIAR QUAYYUMenergy_progress
11/20/2025Maintenance informationSHAHRIAR QUAYYUMenergy_progress
11/20/2025Fire-Resistant Penetrations and JointsSHAHRIAR QUAYYUMspecial
11/20/2025HVAC-R and service water piping design and insulationSHAHRIAR QUAYYUMenergy_progress
11/20/2025Post-installed AnchorsSHAHRIAR QUAYYUMspecial
11/20/2025Tenant Protection Plan ComplianceSHAHRIAR QUAYYUMspecial
11/20/2025Energy Code Compliance InspectionsSHAHRIAR QUAYYUMprogress
11/20/2025HVAC-R and service water heating equipmentSHAHRIAR QUAYYUMenergy_progress
02/26/2025MasonryFAHAD FATEHspecial
02/26/2025Exterior lighting powerFAHAD FATEHenergy_progress
02/26/2025Tenant Protection Plan ComplianceFAHAD FATEHspecial
02/26/2025Structural Stability – Alterations of existing buildingsFAHAD FATEHspecial
02/26/2025Concrete - Cast-In-PlaceFAHAD FATEHspecial
02/26/2025Interior lighting powerFAHAD FATEHenergy_progress
02/26/2025Fenestration areasFAHAD FATEHenergy_progress
02/26/2025Air barrier - visual inspectionFAHAD FATEHenergy_progress
02/26/2025Fenestration air leakageFAHAD FATEHenergy_progress
02/26/2025Insulation placement and R valuesFAHAD FATEHenergy_progress
02/26/2025Fenestration and door U-factor and product ratingsFAHAD FATEHenergy_progress
02/26/2025Lighting controlsFAHAD FATEHenergy_progress
02/26/2025Energy Code Compliance InspectionsFAHAD FATEHprogress
Latest 25 of 61.
▾Tenants in the building
TenantSpaceFloorsRenovation projects
India HomeOtherCellar
Project Q00831290 Alteration · LOC Issued · 03/07/2023
Project Q00831514 Alteration · LOC Issued · 03/07/2023
Read from each project’s drawing title blocks and cover sheets and checked twice; a name appears only when it is the occupant, never the owner, landlord or designer.
▾Documents — 139 on file (BIS + DOB NOW)
▸Plans & Drawings15
▸DOB NOWPlans/Sketch14
08/25/2026Q00831290-I1Request digital key ↗
08/18/2026Q01270231-S1Request digital key ↗
08/18/2026Q01270231-I1Request digital key ↗
Showing 3 of 14 on file for this type
▸DOB NOWPlans/Sketch - Supported Scaffold1
08/28/2026Q00364417-I1Request digital key ↗
▸Applications & Permits16
▸BISPLAN / WORK APPROVAL APPLICATION7
07/01/2020440604026Open ↗
01/25/2018440230929Open ↗
04/25/2017440230929Open ↗
Showing 3 of 7 on file for this type
▸BISWORK PERMIT APPLICATION4
07/08/2020440604026Open ↗
04/13/2017440230929Open ↗
03/30/2017440230929Open ↗
Showing 3 of 4 on file for this type
▸BISPLACE OF ASSEMBLY4
07/24/2018401741692Open ↗
07/24/2018401741692Open ↗
10/24/2016401741709Open ↗
Showing 3 of 4 on file for this type
▸BISNon-Directive 14 Construction Sign Off Including Sign Applications1
07/31/2018440230929Open ↗
▸Zoning, Tax Lot & Property Records4
▸DOB NOWZD1: DOB Zoning Diagram2
08/13/2026Q01085251-P1Open ↗
08/13/2026Q01085251-I1Open ↗
▸DOB NOWHouse Number Verification: TOPO Stamp2
08/13/2026Q01085251-I1Open ↗
08/13/2026Q01085251-P1Open ↗
▸Seals & Professional Certifications39
▸DOB NOWDPL-1: Design Professional Seal & Signature15
08/25/2026Q00831290-I1Open ↗
08/25/2026Q00831514-I1Open ↗
08/18/2026Q01270231-I1Open ↗
Showing 3 of 15 on file for this type
▸DOB NOWProgress Inspector Seal & Signature7
09/01/2026Q01085251-I1Open ↗
09/01/2026Q01085251-I1Open ↗
08/31/2026Q01085251-P2Open ↗
Showing 3 of 7 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature7
09/01/2026Q01085251-I1Open ↗
08/31/2026Q01085251-P2Open ↗
08/31/2026Q01085251-P2Open ↗
Showing 3 of 7 on file for this type
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION3
07/01/2020440604026Open ↗
07/26/2015440230929Open ↗
06/30/2014440148859Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT3
07/01/2020440604026Open ↗
07/26/2015440230929Open ↗
06/30/2014440148859Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY3
07/01/2020440604026Open ↗
07/26/2015440230929Open ↗
06/30/2014440148859Open ↗
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION1
07/31/2018440230929Open ↗
▸Trade Schedules & Equipment4
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE3
01/25/2018440230929Open ↗
04/25/2017440230929Open ↗
02/28/2017440230929Open ↗
▸BISSCHEDULE B - PLUMBING1
07/26/2015440230929Open ↗
▸Safety & Tenant Protection3
▸DOB NOWStreet Tree Checklist2
08/17/2026Q01085251-I1Open ↗
08/17/2026Q01085251-P1Open ↗
▸DOB NOWParks Department Acknowledgment Letter for Street Trees Plan1
08/13/2026Q01085251-I1Open ↗
▸Environmental & Asbestos5
▸BISASBESTOS: CERTIFICATION (DEP ACP5)3
07/01/2020440604026Open ↗
07/26/2015440230929Open ↗
06/30/2014440148859Open ↗
▸DOB NOWDEP ACP-5: Asbestos Assessment Report2
08/25/2026Q00831290-I1Open ↗
08/14/2026Q00831514-I1Open ↗
▸Energy Compliance9
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY4
07/08/2020440604026Open ↗
07/01/2020440604026Open ↗
03/30/2017440230929Open ↗
Showing 3 of 4 on file for this type
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY FOR ENERGY CODE PROGRESS INSPECTIONS3
07/01/2020440604026Open ↗
07/26/2015440230929Open ↗
06/30/2014440148859Open ↗
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS1
07/31/2018440230929Open ↗
▸BISAS-BUILT ENERGY ANALYSIS1
07/31/2018440230929Open ↗
▸Inspections & Test Reports8
▸BISTECHNICAL REPORT: RESPONSIBILITY5
07/08/2020440604026Open ↗
07/01/2020440604026Open ↗
03/30/2017440230929Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWSOIL REPORT2
08/13/2026Q01085251-S2Open ↗
08/13/2026Q01085251-P2Open ↗
▸DOB NOWTR4 Test Report and Plot Diagram1
08/13/2026Q01085251-S2Open ↗
▸Approvals, Objections & Sign-offs15
▸DOB NOWFee Exempt Supporting Document - DOF ACRIS report or BIB letter14
08/17/2026Q01085251-S4Open ↗
08/17/2026Q01085251-P3Open ↗
08/17/2026Q01085251-P2Open ↗
Showing 3 of 14 on file for this type
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST1
07/31/2018440230929Open ↗
▸Cost, Insurance & Ownership4
▸BISCOST AFFIDAVIT4
07/01/2020440604026Open ↗
07/31/2018440230929Open ↗
07/26/2015440230929Open ↗
Showing 3 of 4 on file for this type
▸Filing & Intake Forms6
▸BISADDITIONAL INFORMATION3
04/25/2017440230929Open ↗
10/24/2016401741709Open ↗
10/24/2016401741692Open ↗
▸BISEFILING JOB APPLICATION COVER SHEET3
07/01/2020440604026Open ↗
07/26/2015440230929Open ↗
06/30/2014440148859Open ↗
▸Other Documents11
▸DOB NOWPlot Diagram4
08/13/2026Q01085251-I1Open ↗
08/13/2026Q01085251-P2Open ↗
08/13/2026Q01085251-S2Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWSite Survey: Initial2
08/13/2026Q01085251-P1Open ↗
08/13/2026Q01085251-I1Open ↗
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone2
08/13/2026Q01085251-I1Open ↗
08/13/2026Q01085251-P1Open ↗
▸DOB NOWProperty Ownership Certification2
08/17/2026Q01085251-I1Open ↗
08/17/2026Q01085251-P1Open ↗
▸DOB NOWAdjoining Owners Notification1
08/13/2026Q01085251-S2Open ↗