← Back
BuildNYC
Church, synagogue, chapel
Jamaica Muslim Center
85-37 168TH STREET · Name © OpenStreetMap contributors · BIN 4210720
💬 Discuss this project
1996Year Built
2Stories
M1Building Class
R4AZoning
6,336 sfGross Floor Area
1Units
0 Active Violations 1 likely answered ▸FDNY Report ↗
Church, synagogue, chapel · 10,000 sf lot · 0.63 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralMechanicalPlumbingFire ProtectionEquipmentCivilGeneralOther
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
Permit Issued — active, not yet Signed-off
RoofJamaica Muslim CenterUnder Construction40p · 2 filings · 20 docs
Floor 4Jamaica Muslim CenterUnder Construction58p · 1 filing · 20 docs
Floor 3Jamaica Muslim CenterUnder Construction57p · 1 filing · 20 docs
Floor 2Jamaica Muslim CenterUnder Construction59p · 1 filing · 20 docs
Floor 1Jamaica Muslim CenterUnder Construction59p · 1 filing · 20 docs
CellarJamaica Muslim Center, India HomeUnder Construction50p · 3 filings · 20 docs
Site & exteriorInstallation of pipe scaffoldingUnder Construction19p · 3 filings · 8 docs
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
Askon Architects809/23/2026
Ikra Consulting107/06/2026
Ashraf211/09/2025
Hernandez-Eli Architecture203/07/2023
Green Design106/30/2020
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
Askon Architects P C403/21/2026
PT203/21/2026
Anzalone Architecture403/21/2026
Ugb Construction203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
Ugb ConstructionScaffold506/28/2026
Ugb ConstructionGeneral Contractor506/28/2026
Rapid ContractingScaffold210/14/2026
IR ContractingGeneral Contractor204/09/2026
IR ContractingScaffold104/09/2026
Case PlumbingFire Protection107/04/2026
BPRT Construction of NYGeneral Contractor106/27/2026
Rock E Small Plumbing & HeatingPlumbing107/08/2026
MSNP ManagementGeneral Contractor104/09/2026
Simple Air HVACspecialty_contractor108/07/2026
All Over ConstructionScaffold107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
HRF Services5616509/23/2026
NS Engineers1442111/19/2025
Building Lifecycle
All (105)Filed (14)Permit Issued (21)Signed Off (2)Violation (24)Inspection (6)Objection (8)Special Inspection (30)
10/14/2026
Objection raised — Zoning
10/14/2026
Objection raised — Other
10/13/2026
Permit issued — Supported Scaffold
Q01426381-I1-SF
09/23/2026
Filed — Alteration CO
Installation of a wet-type sprinkler system including a fire booster pump and jockey pump and controllers, flow switches and tamper switches including a 4" fire water service line and backflow preventer.
Q01085251-P5
09/16/2026
Special inspection requirement — Structural Stability – Alterations of existing buildings
FAHAD FATEH
09/16/2026
Special inspection requirement — Masonry
FAHAD FATEH
09/16/2026
Special inspection requirement — Fire-Resistance Rated Construction
FAHAD FATEH
09/16/2026
Special inspection requirement — Fenestration areas
FAHAD FATEH
09/16/2026
Special inspection requirement — Energy Code Compliance Inspections
FAHAD FATEH
09/16/2026
Special inspection requirement — Fenestration air leakage
FAHAD FATEH
09/16/2026
Special inspection requirement — Air barrier - visual inspection
FAHAD FATEH
09/16/2026
Special inspection requirement — Lighting controls
FAHAD FATEH
09/16/2026
Special inspection requirement — Interior lighting power
FAHAD FATEH
09/16/2026
Special inspection requirement — Exterior lighting power
FAHAD FATEH
09/16/2026
Special inspection requirement — Concrete - Cast-In-Place
FAHAD FATEH
09/16/2026
Special inspection requirement — Insulation placement and R values
FAHAD FATEH
09/16/2026
Special inspection requirement — Fenestration and door U-factor and product ratings
FAHAD FATEH
09/16/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
FAHAD FATEH
09/16/2026
Special inspection requirement — Tenant Protection Plan Compliance
08/22/2026
Inspection — Certified Remove/Cap - work done in accordance with code
Certified
View inspection ↗
08/21/2026
Inspection — Certified Sprinkler (SP) - Booster Pump Test
Certified
View inspection ↗
08/18/2026
Inspection — Certified Sprinkler-SP-Fixtures-Finish
Certified
View inspection ↗
08/06/2026
Permit issued — Mechanical Systems
Q01085251-S4-MS
07/10/2026
Permit issued — Supported Scaffold
Q01426381-I1-SF
07/06/2026
Filed — Alteration
INSTALLATION OF PIPE SCAFFOLDING AS PER PLANS. ALL EQUIPMENT SHALL COMPLY WITH CH #33 OF THE NYC CODE 2022. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
Q01426381-I1
06/24/2026
Permit issued — General Construction
Q01085251-I1-GC
06/22/2026
Permit issued — Sidewalk Shed
Q01270231-I1-SH
06/16/2026
Special inspection requirement — Tenant Protection Plan Compliance
05/11/2026
Permit issued — Sprinklers
Q01085251-S5-EW-SP
03/09/2026
Permit issued — General Construction
Q01085251-I1-GC
03/09/2026
Permit issued — Sidewalk Shed
Q01270231-I1-SH
02/27/2026
Special inspection requirement — Shutoff dampers
SHAHRIAR QUAYYUM
02/04/2026
Objection raised — Admin
02/04/2026
Objection raised — Other
02/04/2026
Objection raised — Scope
02/04/2026
Objection raised — Energy
01/21/2026
Filed — Alteration CO
Installation of a wet-type sprinkler system including a fire booster pump and jockey pump and controllers, flow switches and tamper switches including a 4" fire water service line and backflow preventer.
Q01085251-S3
01/20/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
12/05/2025
Filed — Alteration CO
Installation of a wet-type sprinkler system including a fire booster pump and jockey pump and controllers, flow switches and tamper switches including a 4" fire water service line and backflow preventer.
Q01085251-S4
11/25/2025
Permit issued — Supported Scaffold
Q01270231-S1-SF
11/20/2025
Special inspection requirement — Post-installed Anchors
SHAHRIAR QUAYYUM
11/20/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
SHAHRIAR QUAYYUM
11/20/2025
Special inspection requirement — Tenant Protection Plan Compliance
SHAHRIAR QUAYYUM
11/20/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
SHAHRIAR QUAYYUM
11/20/2025
Special inspection requirement — Maintenance information
SHAHRIAR QUAYYUM
11/20/2025
Special inspection requirement — HVAC-R and service water heating system controls
SHAHRIAR QUAYYUM
11/20/2025
Special inspection requirement — Duct leakage testing, insulation and design
SHAHRIAR QUAYYUM
11/20/2025
Special inspection requirement — HVAC-R and service water heating equipment
SHAHRIAR QUAYYUM
11/20/2025
Special inspection requirement — Energy Code Compliance Inspections
SHAHRIAR QUAYYUM
11/19/2025
Filed — Alteration CO
Installation of a wet-type sprinkler system including a fire booster pump and jockey pump and controllers, flow switches and tamper switches including a 4" fire water service line and backflow preventer.
Q01085251-S5
11/09/2025
Filed — Alteration
INSTALLATION OF MEDIUM DUTY PIPE SCAFFOLD.
Q01270231-S1
09/29/2025
Permit issued — Structural
Q01085251-S1-ST
09/29/2025
Permit issued — Sidewalk Shed
Q01270231-I1-SH
09/26/2025
Permit issued — General Construction
Q01085251-I1-GC
09/18/2025
Permit issued — Sidewalk Shed
Q01270231-I1-SH
08/15/2025
Permit issued — Sidewalk Shed
Q01270231-I1-SH
08/12/2025
Filed — Alteration
INSTALLATION OF MEDIUM DUTY PIPE SCAFFOLD.
Q01270231-I1
05/29/2025
Permit issued — Structural
Q01085251-S1-ST
05/21/2025
Permit issued — General Construction
Q01085251-I1-GC
05/08/2025
Permit issued — Earth Work
Q01085251-S2-FO-EA
Latest 60 of 105 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSupported ScaffoldPermit IssuedRapid Contracting10/13/2026
DOB NOWMechanical SystemsPermit IssuedSimple Air HVAC08/06/2026
DOB NOWSupported ScaffoldPermit IssuedRapid Contracting07/10/2026
DOB NOWGeneral ConstructionPermit IssuedBPRT Construction of NY06/24/2026
DOB NOWSidewalk ShedPermit IssuedUgb Construction06/22/2026
DOB NOWSprinklersPermit IssuedCase Plumbing05/11/2026
DOB NOWGeneral ConstructionPermit IssuedUgb Construction03/09/2026
DOB NOWSidewalk ShedPermit IssuedUgb Construction03/09/2026
DOB NOWSupported ScaffoldPermit IssuedUgb Construction11/25/2025
DOB NOWStructuralPermit IssuedIR Contracting09/29/2025
DOB NOWSidewalk ShedPermit IssuedIR Contracting09/29/2025
DOB NOWGeneral ConstructionPermit IssuedIR Contracting09/26/2025
DOB NOWSidewalk ShedPermit IssuedUgb Construction09/18/2025
DOB NOWSidewalk ShedPermit IssuedUgb Construction08/15/2025
DOB NOWStructuralPermit IssuedUgb Construction05/29/2025
DOB NOWGeneral ConstructionPermit IssuedUgb Construction05/21/2025
DOB NOWEarth WorkPermit IssuedUgb Construction05/08/2025
DOB NOWGeneral ConstructionPermit IssuedUgb Construction04/18/2025
DOB NOWPlumbingSigned-offRock E Small Plumbing & Heating03/29/2023
DOB NOWGeneral ConstructionSigned-offMSNP Management03/28/2023
DOB NOWSupported ScaffoldPermit IssuedAll Over Construction07/02/2020
BISOTISSUEDAll Over Construction07/09/2020
BISOTISSUEDAll Over Construction07/08/2020
BISPLISSUEDZone Plumbing & Heating04/05/2017
BISOTISSUEDAtco Restoration03/30/2017
BISOTISSUEDAgo & Alaudin General Con07/01/2014
BISPLISSUEDAvon Plumbing & Heating04/23/2004
BISFPISSUEDMega Fire Protection09/08/2003
BISEQISSUEDJ and I Construction12/17/2002
BIS—ISSUEDJ and I Construction12/17/2002
BISPLISSUEDAvon Plumbing & Heating08/12/2002
BIS—ISSUEDJ and I Construction11/09/2001
BISEQISSUEDJ and I Construction09/24/2001
BISEQISSUEDJ&I Construction11/22/1996
BISCCISSUEDJ&I Construction11/22/1996
BISCCISSUEDJ & I Construction02/28/1996
BISMHISSUEDJ & I Construction02/28/1996
BISPLISSUEDAvon Plumbing & Heating02/05/1996
BIS—ISSUEDJ & I Construction07/11/1995
BIS—ISSUEDJ & I Construction10/21/1994
+ 1 more permits on file
1 project · most recent 09/23/2026
Sprinkler System
FiledStatusContractorScope
09/23/2026Permit IssuedCase PlumbingSprinkler System
5 projects · most recent 12/20/2025
General Wiring
FiledStatusContractorScope
12/20/2025Permit IssuedExpert Electric Cont NY IGeneral Wiring
12/16/2025Permit IssuedExpert Electric Cont NY I—
08/14/2025Permit IssuedRichard Neu—
06/11/2025CompleteExpert Electric Cont NY I—
06/04/2023CompleteAyyub ElectricGeneral Wiring
3 projects · most recent 07/06/2026
Scaffold Sidewalk Shed
FiledStatusContractorScope
07/06/2026Permit IssuedRapid ContractingScaffold
11/09/2025Permit IssuedUgb ConstructionScaffold, Sidewalk Shed
06/30/2020Permit IssuedAll Over ConstructionScaffold
▾Field Inspections (DOB CAP) — 6
DateTypeResultReport
08/22/2026Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
08/21/2026Certified Sprinkler (SP) - Booster Pump TestCertifiedView ↗
08/18/2026Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
06/07/2023Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
06/02/2023Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
06/01/2023Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 76
DateRequirementInspectorRole
09/16/2026Lighting controlsFAHAD FATEHenergy_progress
09/16/2026Concrete - Cast-In-PlaceFAHAD FATEHspecial
09/16/2026Fire-Resistant Penetrations and JointsFAHAD FATEHspecial
09/16/2026Interior lighting powerFAHAD FATEHenergy_progress
09/16/2026MasonryFAHAD FATEHspecial
09/16/2026Fenestration and door U-factor and product ratingsFAHAD FATEHenergy_progress
09/16/2026Insulation placement and R valuesFAHAD FATEHenergy_progress
09/16/2026Structural Stability – Alterations of existing buildingsFAHAD FATEHspecial
09/16/2026Tenant Protection Plan Compliance—special
09/16/2026Energy Code Compliance InspectionsFAHAD FATEHprogress
09/16/2026Fire-Resistance Rated ConstructionFAHAD FATEHprogress
09/16/2026Fenestration air leakageFAHAD FATEHenergy_progress
09/16/2026Fenestration areasFAHAD FATEHenergy_progress
09/16/2026Exterior lighting powerFAHAD FATEHenergy_progress
09/16/2026Air barrier - visual inspectionFAHAD FATEHenergy_progress
06/16/2026Tenant Protection Plan Compliance—special
02/27/2026Shutoff dampersSHAHRIAR QUAYYUMenergy_progress
01/20/2026Fire-Resistant Penetrations and Joints—special
11/20/2025Fire-Resistant Penetrations and JointsSHAHRIAR QUAYYUMspecial
11/20/2025Energy Code Compliance InspectionsSHAHRIAR QUAYYUMprogress
11/20/2025HVAC-R and service water heating equipmentSHAHRIAR QUAYYUMenergy_progress
11/20/2025Duct leakage testing, insulation and designSHAHRIAR QUAYYUMenergy_progress
11/20/2025HVAC-R and service water heating system controlsSHAHRIAR QUAYYUMenergy_progress
11/20/2025Maintenance informationSHAHRIAR QUAYYUMenergy_progress
11/20/2025HVAC-R and service water piping design and insulationSHAHRIAR QUAYYUMenergy_progress
Latest 25 of 76.
▾Tenants in the building
TenantSpaceFloorsRenovation projects
Jamaica Muslim CenterReligiousCellar, Floors 1–4, Roof
Project Q01085251 Alteration CO · Permit Entire · 08/09/2024
India HomeCommunity FacilityCellar
Project Q00831290 Alteration · LOC Issued · 03/07/2023
Project Q00831514 Alteration · LOC Issued · 03/07/2023
Names are taken automatically from the text of each project’s filed documents (title blocks and cover sheets) and screened to exclude owners, landlords and designers. They may be incomplete or wrong; check the filing.
▾Documents — 150 on file (BIS + DOB NOW)
▸Plans & Drawings15
▸DOB NOWPlans/Sketch14
08/25/2026Q00831290-I1Request digital key ↗
08/18/2026Q01270231-S1Request digital key ↗
08/18/2026Q01270231-I1Request digital key ↗
Showing 3 of 14 on file for this type
▸DOB NOWPlans/Sketch - Supported Scaffold1
08/28/2026Q00364417-I1Request digital key ↗
▸Applications & Permits16
▸BISPLAN / WORK APPROVAL APPLICATION7
07/01/2020440604026Open ↗
01/25/2018440230929Open ↗
04/25/2017440230929Open ↗
Showing 3 of 7 on file for this type
▸BISWORK PERMIT APPLICATION4
07/08/2020440604026Open ↗
04/13/2017440230929Open ↗
03/30/2017440230929Open ↗
Showing 3 of 4 on file for this type
▸BISPLACE OF ASSEMBLY4
07/24/2018401741692Open ↗
07/24/2018401741692Open ↗
10/24/2016401741709Open ↗
Showing 3 of 4 on file for this type
▸BISNon-Directive 14 Construction Sign Off Including Sign Applications1
07/31/2018440230929Open ↗
▸Zoning, Tax Lot & Property Records5
▸DOB NOWZD1: DOB Zoning Diagram3
10/04/2026Q01085251-P5Open ↗
08/13/2026Q01085251-P1Open ↗
08/13/2026Q01085251-I1Open ↗
▸DOB NOWHouse Number Verification: TOPO Stamp2
08/13/2026Q01085251-P1Open ↗
08/13/2026Q01085251-I1Open ↗
▸Seals & Professional Certifications43
▸DOB NOWDPL-1: Design Professional Seal & Signature16
10/04/2026Q01085251-P5Open ↗
08/25/2026Q00831290-I1Open ↗
08/25/2026Q00831514-I1Open ↗
Showing 3 of 16 on file for this type
▸DOB NOWProgress Inspector Seal & Signature9
10/04/2026Q01085251-P5Open ↗
10/04/2026Q01085251-P5Open ↗
09/01/2026Q01085251-I1Open ↗
Showing 3 of 9 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature8
10/04/2026Q01085251-P5Open ↗
09/01/2026Q01085251-I1Open ↗
08/31/2026Q01085251-P2Open ↗
Showing 3 of 8 on file for this type
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION3
07/01/2020440604026Open ↗
07/26/2015440230929Open ↗
06/30/2014440148859Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT3
07/01/2020440604026Open ↗
07/26/2015440230929Open ↗
06/30/2014440148859Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY3
07/01/2020440604026Open ↗
07/26/2015440230929Open ↗
06/30/2014440148859Open ↗
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION1
07/31/2018440230929Open ↗
▸Trade Schedules & Equipment4
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE3
01/25/2018440230929Open ↗
04/25/2017440230929Open ↗
02/28/2017440230929Open ↗
▸BISSCHEDULE B - PLUMBING1
07/26/2015440230929Open ↗
▸Safety & Tenant Protection4
▸DOB NOWStreet Tree Checklist3
10/04/2026Q01085251-P5Open ↗
08/17/2026Q01085251-I1Open ↗
08/17/2026Q01085251-P1Open ↗
▸DOB NOWParks Department Acknowledgment Letter for Street Trees Plan1
08/13/2026Q01085251-I1Open ↗
▸Environmental & Asbestos5
▸BISASBESTOS: CERTIFICATION (DEP ACP5)3
07/01/2020440604026Open ↗
07/26/2015440230929Open ↗
06/30/2014440148859Open ↗
▸DOB NOWDEP ACP-5: Asbestos Assessment Report2
08/25/2026Q00831290-I1Open ↗
08/14/2026Q00831514-I1Open ↗
▸Energy Compliance9
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY4
07/08/2020440604026Open ↗
07/01/2020440604026Open ↗
03/30/2017440230929Open ↗
Showing 3 of 4 on file for this type
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY FOR ENERGY CODE PROGRESS INSPECTIONS3
07/01/2020440604026Open ↗
07/26/2015440230929Open ↗
06/30/2014440148859Open ↗
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS1
07/31/2018440230929Open ↗
▸BISAS-BUILT ENERGY ANALYSIS1
07/31/2018440230929Open ↗
▸Inspections & Test Reports8
▸BISTECHNICAL REPORT: RESPONSIBILITY5
07/08/2020440604026Open ↗
07/01/2020440604026Open ↗
03/30/2017440230929Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWSOIL REPORT2
08/13/2026Q01085251-S2Open ↗
08/13/2026Q01085251-P2Open ↗
▸DOB NOWTR4 Test Report and Plot Diagram1
08/13/2026Q01085251-S2Open ↗
▸Approvals, Objections & Sign-offs16
▸DOB NOWFee Exempt Supporting Document - DOF ACRIS report or BIB letter15
10/04/2026Q01085251-P5Open ↗
08/17/2026Q01085251-P3Open ↗
08/17/2026Q01085251-P2Open ↗
Showing 3 of 15 on file for this type
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST1
07/31/2018440230929Open ↗
▸Cost, Insurance & Ownership4
▸BISCOST AFFIDAVIT4
07/01/2020440604026Open ↗
07/31/2018440230929Open ↗
07/26/2015440230929Open ↗
Showing 3 of 4 on file for this type
▸Filing & Intake Forms6
▸BISADDITIONAL INFORMATION3
04/25/2017440230929Open ↗
10/24/2016401741709Open ↗
10/24/2016401741692Open ↗
▸BISEFILING JOB APPLICATION COVER SHEET3
07/01/2020440604026Open ↗
07/26/2015440230929Open ↗
06/30/2014440148859Open ↗
▸Other Documents15
▸DOB NOWPlot Diagram5
10/04/2026Q01085251-P5Open ↗
08/13/2026Q01085251-I1Open ↗
08/13/2026Q01085251-P1Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWSite Survey: Initial3
10/04/2026Q01085251-P5Open ↗
08/13/2026Q01085251-I1Open ↗
08/13/2026Q01085251-P1Open ↗
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone3
10/04/2026Q01085251-P5Open ↗
08/13/2026Q01085251-P1Open ↗
08/13/2026Q01085251-I1Open ↗
▸DOB NOWProperty Ownership Certification3
10/04/2026Q01085251-P5Open ↗
08/17/2026Q01085251-I1Open ↗
08/17/2026Q01085251-P1Open ↗
▸DOB NOWAdjoining Owners Notification1
08/13/2026Q01085251-S2Open ↗