← Back
Four families
85 4 PLACE
BROOKLYN · BIN 3005426
💬 Discuss this project
1910Year Built
3Stories
C3Building Class
R6BZoning
3,780 sfGross Floor Area
4Units
Rent Stabilized10 Open Violations ▸
Four families · Owner of record: PLT BROOKLYN LLC · 2,125 sf lot · 1.78 FAR built · Flood zone X
Locations of Work
ArchitectureElectricalPlumbing
Roof3p · 1 filing · 20 docs
Floor 31p · 1 filing · 20 docs
Floor 21p · 1 filing · 20 docs
Floor 11p · 1 filing · 20 docs
Cellar4p · 1 filing · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
BARCLAYS1307/08/2026
PLT BROOKLYN LLC103/22/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
07/01/2021$3.1M—Private party → PLT BROOKLYN LLC$820/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
NY BUILDING ASSOCIATES INC109/10/2025
WILLIAM F. RYAN, JR. P.E. PC305/01/2023
PAUL SCOTT, ARCHITECT PC208/10/2022
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
CLARKE CONSTRUCTION CONSULTANTS503/21/2026
BROOKLYN SOLARWORKS103/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
CREDENCE CONSTRUCTION CORGeneral Contractor303/21/2026
SAMUEL & SONS P & H INCPlumbing307/08/2026
C A ELECTRICAL CORP 003149General Contractor203/22/2026
BROOKLYN SOLARWORKS LLCGeneral Contractor203/21/2026
BROOKYLN SOLARWORKS, LLCElectrical103/22/2026
ARC ELECTRICAL & MECH CONElectrical103/21/2026
COMMON BUILDERS INCGeneral Contractor107/08/2026
STEVEN BURKEElectrical103/21/2026
SAMUEL SONS P HGeneral Contractor103/22/2026
ARC ELECTRICAL & MECH CONGeneral Contractor103/22/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
NKM ENGINEERING PLLC6244109/10/2025
PAUL SCOTT, ARCHITECT P.C7717208/10/2022
Building Lifecycle
All (126)Filed (6)Permit Issued (5)Signed Off (3)Violation (13)Inspection (5)Objection (80)Special Inspection (14)
04/30/2026
Violation issued (HPD, open)
A
11/20/2025
Violation issued (HPD, open)
I
11/05/2025
Signed off — Alteration
INSTALLATION OF SOLAR PV SYSTEM. NO CHANGE TO USE, EGRESS, OR OCCUPANCY.
B01282829-I1
09/16/2025
Permit issued — Solar
B01282829-I1-SL
09/10/2025
Filed — Alteration
INSTALLATION OF SOLAR PV SYSTEM. NO CHANGE TO USE, EGRESS, OR OCCUPANCY.
B01282829-I1
06/05/2025
Violation issued (HPD, open)
A
11/29/2024
Violation issued (HPD, open)
I
04/03/2024
Violation issued (HPD, open)
A
01/02/2024
Signed off — Alteration
PL FIXTURES IN APTS OF BAS AND 1ST FL. IN ADDITION TO INTERIOR RENOVATIONS OF ALL LISTED FLOORS. NO CHANGE IN USE, OCCUPANY OR EGRESS.
B00562382-I1
12/12/2023
Signed off — Alteration
PL FIXTURES IN APTS OF BAS AND 1ST FL. IN ADDITION TO INTERIOR RENOVATIONS OF ALL LISTED FLOORS. NO CHANGE IN USE, OCCUPANY OR EGRESS.
B00562382-S1
11/22/2023
Violation issued (HPD, open)
I
05/11/2023
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
05/01/2023
Filed — Alteration
PL FIXTURES IN APTS OF BAS AND 1ST FL. IN ADDITION TO INTERIOR RENOVATIONS OF ALL LISTED FLOORS. NO CHANGE IN USE, OCCUPANY OR EGRESS.
B00562382-P3
04/04/2023
Special inspection requirement — Fire-Resistant Penetrations and Joints
Paul Scott
04/04/2023
Special inspection requirement — Fire-Resistance Rated Construction
Paul Scott
04/04/2023
Special inspection requirement — Final
Paul Scott
04/04/2023
Special inspection requirement — Energy Code Compliance Inspections
Paul Scott
04/04/2023
Special inspection requirement — Lighting in dwelling units
Paul Scott
04/04/2023
Special inspection requirement — Air barrier - visual inspection
Paul Scott
04/04/2023
Special inspection requirement — Insulation placement and R values
Paul Scott
03/31/2023
Objection resolved — Addressed
03/17/2023
Violation issued (HPD, open)
A
02/28/2023
Permit issued — Plumbing
B00562382-S1-PL
01/26/2023
Objection resolved — Addressed
01/04/2023
Objection raised — Mechanical
12/23/2022
Objection resolved — Addressed
12/22/2022
Objection raised — Scope
12/20/2022
Objection resolved — Addressed
12/20/2022
Objection resolved — Addressed
12/13/2022
Filed — Alteration
PL FIXTURES IN APTS OF BAS AND 1ST FL. IN ADDITION TO INTERIOR RENOVATIONS OF ALL LISTED FLOORS. NO CHANGE IN USE, OCCUPANY OR EGRESS.
B00562382-P2
12/12/2022
Objection resolved — Addressed
12/12/2022
Objection resolved — Addressed
12/12/2022
Objection resolved — Addressed
12/12/2022
Objection resolved — Addressed
12/12/2022
Objection resolved — Addressed
12/12/2022
Objection resolved — Addressed
12/12/2022
Objection resolved — Addressed
12/12/2022
Objection resolved — Addressed
11/14/2022
Violation issued (HPD, open)
I
10/06/2022
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
08/17/2022
Objection raised — Other
08/16/2022
Objection raised — Fire_Protection
08/16/2022
Objection raised — Other
08/16/2022
Objection raised — Other
08/16/2022
Objection raised — Fire_Protection
08/16/2022
Objection raised — Scope
08/16/2022
Objection raised — Accessibility
08/16/2022
Objection raised — Inspections
08/16/2022
Objection raised — Scope
08/16/2022
Objection raised — Admin
08/16/2022
Objection raised — Accessibility
08/10/2022
Filed — Alteration
PL FIXTURES IN APTS OF BAS AND 1ST FL. IN ADDITION TO INTERIOR RENOVATIONS OF ALL LISTED FLOORS. NO CHANGE IN USE, OCCUPANY OR EGRESS.
B00562382-P1
08/04/2022
Special inspection requirement — Fire-Resistant Penetrations and Joints
Paul Scott
08/04/2022
Special inspection requirement — Energy Code Compliance Inspections
Paul Scott
08/04/2022
Special inspection requirement — Final
Paul Scott
08/04/2022
Special inspection requirement — Fire-Resistance Rated Construction
Paul Scott
08/04/2022
Special inspection requirement — Lighting in dwelling units
Paul Scott
08/04/2022
Special inspection requirement — Air barrier - visual inspection
Paul Scott
08/04/2022
Special inspection requirement — Insulation placement and R values
Paul Scott
07/01/2022
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
Latest 60 of 126 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarSigned-offBROOKLYN SOLARWORKS LLC09/16/2025
DOB NOWPlumbingSigned-offSAMUEL & SONS P & H INC02/28/2023
DOB NOWPlumbingSigned-offSAMUEL & SONS P & H INC03/09/2022
DOB NOWGeneral ConstructionSigned-offCOMMON BUILDERS INC12/29/2021
DOB NOWGeneral ConstructionSigned-offCREDENCE CONSTRUCTION COR11/15/2021
2 projects · most recent 11/04/2025
General Wiring
FiledStatusContractorScope
11/04/2025CompleteBROOKYLN SOLARWORKS, LLC2 meters
03/04/2022CompleteC & A ELECTRICAL CORPGeneral Wiring
▾Field Inspections (DOB CAP) — 5
DateTypeResultReport
05/11/2023Pass-Final PL - Up to 3 Requested FloorsPassView ↗
10/06/2022Pass-Final PL - Up to 3 Requested FloorsPassView ↗
07/01/2022Pass-Final PL - Up to 3 Requested FloorsPassView ↗
04/26/2022Certified Gas-Gas-Piping-RoughingCertifiedView ↗
04/26/2022Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 14
DateRequirementInspectorRole
04/04/2023Fire-Resistant Penetrations and JointsPaul Scottspecial
04/04/2023Fire-Resistance Rated ConstructionPaul Scottprogress
04/04/2023FinalPaul Scottprogress
04/04/2023Energy Code Compliance InspectionsPaul Scottprogress
04/04/2023Lighting in dwelling unitsPaul Scottenergy_progress
04/04/2023Air barrier - visual inspectionPaul Scottenergy_progress
04/04/2023Insulation placement and R valuesPaul Scottenergy_progress
08/04/2022Fire-Resistant Penetrations and JointsPaul Scottspecial
08/04/2022Energy Code Compliance InspectionsPaul Scottprogress
08/04/2022FinalPaul Scottprogress
08/04/2022Fire-Resistance Rated ConstructionPaul Scottprogress
08/04/2022Lighting in dwelling unitsPaul Scottenergy_progress
08/04/2022Air barrier - visual inspectionPaul Scottenergy_progress
08/04/2022Insulation placement and R valuesPaul Scottenergy_progress
▾Documents — 34 on file (BIS + DOB NOW)
▸Plans & Drawings6
▸DOB NOWPlans/Sketch6
09/01/2026B00562382-S1Request digital key ↗
09/01/2026B00562382-P3Request digital key ↗
08/20/2026B01282829-I1Request digital key ↗
Showing 3 of 6 on file for this type
▸Seals & Professional Certifications20
▸DOB NOWProgress Inspector Seal & Signature12
08/30/2026B00562382-I1Open ↗
08/30/2026B00562382-I1Open ↗
08/30/2026B00562382-I1Open ↗
Showing 3 of 12 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature6
09/01/2026B00562382-S1Open ↗
09/01/2026B00562382-I1Open ↗
09/01/2026B00562382-P3Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature2
08/30/2026B00562382-I1Open ↗
08/22/2026B00562382-P1Open ↗
▸Environmental & Asbestos6
▸DOB NOWDEP ACP-5: Asbestos Assessment Report6
09/01/2026B00562382-P3Open ↗
09/01/2026B00562382-S1Open ↗
08/15/2026B00562382-P2Open ↗
Showing 3 of 6 on file for this type
▸Energy Compliance1
▸DOB NOWEN2: As Built Energy Analysis.1
08/13/2026B00562382-I1Open ↗
▸Approvals, Objections & Sign-offs1
▸DOB NOWUtility Company Final Acceptance Letter1
08/13/2026B01282829-I1Open ↗