| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 08/22/2023 | $805K | — | Private party → Private party | $745/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| MOMENTUM SOLAR | 2 | 03/25/2026 |
| ANTHONY CUCICH ARCHITECT | 6 | 10/23/2025 |
| Representative | Filings | Most Recent |
|---|---|---|
| ANTHONY CUCICH ARCHITECT | 6 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| KAG CONSTRUCTION CORP | General Contractor | 4 | 07/08/2026 |
| ASCUATECH ELECTRICAL CORP | Electrical | 1 | 03/22/2026 |
| BYPASS MECHANICAL CORP | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| MXV SIA LLC | 9281 | 2 | 03/25/2026 |
| ANTHONY CUCICH ARCHITECT | 6081 | 5 | 10/23/2025 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Solar | Signed-off | MOMENTUM SOLAR | 12/12/2025 |
| DOB NOW | Plumbing | Signed-off | BYPASS MECHANICAL CORP | 10/17/2024 |
| DOB NOW | Construction Fence | Signed-off | KAG CONSTRUCTION CORP | 09/25/2024 |
| DOB NOW | General Construction | Permit Issued | KAG CONSTRUCTION CORP | 09/25/2024 |
| BIS | OT | ISSUED | LONG ISLAND POWER SOLUTIO | 09/14/2022 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 12/11/2025 | Complete | ISLAND ELECTRIC CORP | — |
| 06/19/2025 | Complete | ASCUATECH ELECTRICAL CORP | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/23/2025 | Permit Issued | KAG CONSTRUCTION CORP | Wood |
| Date | Type | Result | Report |
|---|---|---|---|
| 07/07/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 03/26/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 11/26/2024 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 11/08/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 11/08/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 10/11/2024 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 10/07/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 10/07/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 04/02/2026 | Air barrier - visual inspection | Mina Makar | energy_progress |
| 04/02/2026 | Final | Mina Makar | progress |
| 04/02/2026 | Structural Stability – Alterations of existing buildings | Mina Makar | special |
| 04/02/2026 | Fire-Resistant Penetrations and Joints | Mina Makar | special |
| 04/02/2026 | Energy Code Compliance Inspections | Mina Makar | progress |
| 12/11/2025 | Permanent certificate | ANTHONY CUCICH | energy_progress |
| 12/11/2025 | Fenestration and door U-factor and product ratings | ANTHONY CUCICH | energy_progress |
| 12/11/2025 | Fenestration air leakage | ANTHONY CUCICH | energy_progress |
| 12/11/2025 | Maintenance information | ANTHONY CUCICH | energy_progress |
| 12/11/2025 | Fenestration areas | ANTHONY CUCICH | energy_progress |
| 12/11/2025 | Structural Stability – Alterations of existing buildings | ANTHONY CUCICH | special |
| 12/11/2025 | Fire-Resistance Rated Construction | ANTHONY CUCICH | progress |
| 12/11/2025 | Energy Code Compliance Inspections | ANTHONY CUCICH | progress |
| 12/11/2025 | Final | ANTHONY CUCICH | progress |
| 12/11/2025 | Electric vehicle service equipment requirements | ANTHONY CUCICH | energy_progress |
| 12/11/2025 | Insulation placement and R values | ANTHONY CUCICH | energy_progress |
| 12/11/2025 | Interior lighting power | ANTHONY CUCICH | energy_progress |
| 12/11/2025 | Air barrier - visual inspection | ANTHONY CUCICH | energy_progress |
| 10/22/2025 | Maintenance information | ANTHONY CUCICH | energy_progress |
| 10/22/2025 | Fenestration areas | ANTHONY CUCICH | energy_progress |
| 10/22/2025 | Fenestration and door U-factor and product ratings | ANTHONY CUCICH | energy_progress |
| 10/22/2025 | Air barrier - visual inspection | ANTHONY CUCICH | energy_progress |
| 10/22/2025 | Fire-Resistance Rated Construction | ANTHONY CUCICH | progress |
| 10/22/2025 | Final | ANTHONY CUCICH | progress |
| 10/22/2025 | Energy Code Compliance Inspections | ANTHONY CUCICH | progress |