| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/19/2024 | Complete | SUNRUN SOLAR ELECTL CORP | — |
| 03/22/2024 | Complete | CUNNINGHAM ELECTRIC CORP | General Wiring |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 12/30/2022 | $1.0M | — | — → — | $600/sf building |
| 05/17/2018 | $780K | — | — → — | $455/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| PARKER AND WEST ENGINEERING, PLLC | 1 | 04/22/2024 |
| NS ENGINEERS, P.C. | 1 | 03/12/2024 |
| Representative | Filings | Most Recent |
|---|---|---|
| SUNRUN | 1 | 03/21/2026 |
| BUILD NYC SAFER | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| SUNRUN SOLAR ELECTL CORP | Electrical | 1 | 03/22/2026 |
| SUNRUN INSTALLATION SVC | General Contractor | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| PARKER AND WEST ENGINEERI | 5272 | 1 | 04/22/2024 |
| NS ENGINEERS, P.C. | 1442 | 1 | 03/12/2024 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Solar | Signed-off | SUNRUN INSTALLATION SVC | 04/24/2024 |
| BIS | OT | ISSUED | SOLTERIX CORPORATION | 01/06/2017 |
| BIS | — | ISSUED | AJAY GENERAL CONTRACTING CO. INC | 07/29/1996 |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 03/22/2024 | Fire-Resistant Penetrations and Joints | Walid Abdulla | special |
| 03/22/2024 | Structural Stability – Alterations of existing buildings | Walid Abdulla | special |
| 03/22/2024 | Energy Code Compliance Inspections | Walid Abdulla | progress |
| 03/22/2024 | Final | Walid Abdulla | progress |
| 03/22/2024 | Air barrier - visual inspection | Walid Abdulla | energy_progress |