| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/04/2025 | Complete | J Y ELECTRIC INC | General Wiring |
| 03/16/2025 | Complete | A.C. MORGAN ELECTRIC | General Wiring |
| 05/01/2023 | Complete | NASH ELECTRIC SERVICES IN | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/19/2023 | Permit Issued | TLS CONSTRUCTION GROUP I* | Steel, Concrete |
| Owner | Filings | Most Recent |
|---|---|---|
| GRAVITY STUDIO | 10 | 07/08/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 07/10/2020 | $1.7M | — | — → — | $526/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| BARRY DONALDSON ARCHITECTS | 1 | 08/08/2024 |
| NTD ENGINEERING CONSULTANT LLC | 2 | 06/19/2024 |
| S M TAM ARCHITECT, PLLC | 3 | 06/06/2024 |
| BAYSIDE ENGINEERING PC | 2 | 07/19/2023 |
| FL&M ENGINEERING DESIGN &INSPECTION | 1 | 05/08/2023 |
| Representative | Filings | Most Recent |
|---|---|---|
| S M TAM ARCHITECT | 4 | 03/21/2026 |
| Rigid Structural Design, LLC | 1 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| TLS CONSTRUCTION GROUP I* | General Contractor | 6 | 03/21/2026 |
| MC SUPERSTRUCTURE INC | General Contractor | 4 | 03/21/2026 |
| TRI BOROUGH SCAFFOLDING | General Contractor | 4 | 07/08/2026 |
| CATMAN PLUMBING INC | Plumbing | 2 | 07/08/2026 |
| CASE PLUMBING LLC | Fire Protection | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| SD TESTING & INSPECTION S | 7010 | 7 | 08/08/2024 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Boiler Equipment | Signed-off | CATMAN PLUMBING INC | 08/19/2024 |
| DOB NOW | Sprinklers | Signed-off | S & L PLUMBING INC | 01/30/2024 |
| DOB NOW | Plumbing | Signed-off | CATMAN PLUMBING INC | 01/30/2024 |
| DOB NOW | Sidewalk Shed | Signed-off | MC SUPERSTRUCTURE INC | 07/13/2023 |
| DOB NOW | Supported Scaffold | Signed-off | MC SUPERSTRUCTURE INC | 07/12/2023 |
| DOB NOW | Foundation | Permit Issued | TLS CONSTRUCTION GROUP I* | 05/23/2023 |
| DOB NOW | Construction Fence | Signed-off | TLS CONSTRUCTION GROUP I* | 05/19/2023 |
| DOB NOW | Supported Scaffold | Signed-off | TRI BOROUGH SCAFFOLDING | 05/08/2023 |
| DOB NOW | Supported Scaffold | Signed-off | TRI BOROUGH SCAFFOLDING | 05/08/2023 |
| BIS | — | ISSUED | TLS CONSTRUCTION GROUP I* | 08/11/2023 |
| BIS | — | ISSUED | TLS CONSTRUCTION GROUP I* | 06/20/2023 |
| BIS | — | ISSUED | TLS CONSTRUCTION GROUP I* | 06/20/2023 |
| BIS | — | ISSUED | TLS CONSTRUCTION GROUP I* | 06/07/2023 |
| BIS | EQ | RE-ISSUED | TLS CONSTRUCTION GROUP I* | 06/01/2023 |
| Date | Type | Result | Report |
|---|---|---|---|
| 01/23/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 09/23/2024 | Fail-Final General Construction Non-Directive 14 | Fail | View ↗ |
| 08/30/2024 | Pass-Final Boiler Equipment Inspection | Pass | View ↗ |
| 07/23/2024 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 07/22/2024 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 03/29/2024 | Certified Storm Drainage-ST-Piping-Roughing | Certified | View ↗ |
| 03/29/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 02/23/2024 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 02/23/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 08/05/2024 | Fire-Resistant Penetrations and Joints | XIUCHENG LI | special |
| 08/05/2024 | Maintenance information | XIUCHENG LI | energy_progress |
| 08/05/2024 | HVAC-R and service water piping design and insulation | XIUCHENG LI | energy_progress |
| 08/05/2024 | HVAC-R and service water heating system controls | XIUCHENG LI | energy_progress |
| 08/05/2024 | HVAC-R and service water heating equipment | XIUCHENG LI | energy_progress |
| 08/05/2024 | Heating Systems | XIUCHENG LI | special |
| 07/09/2024 | Sprinkler Systems | XIUCHENG LI | special |
| 06/17/2024 | Energy Code Compliance Inspections | XIUCHENG LI | progress |
| 06/17/2024 | Fire-Resistant Penetrations and Joints | XIUCHENG LI | special |
| 06/17/2024 | HVAC-R and service water piping design and insulation | XIUCHENG LI | energy_progress |
| 06/17/2024 | Maintenance information | XIUCHENG LI | energy_progress |
| 06/17/2024 | HVAC-R and service water heating system controls | XIUCHENG LI | energy_progress |
| 06/17/2024 | HVAC-R and service water heating equipment | XIUCHENG LI | energy_progress |
| 06/05/2024 | HVAC-R and service water heating equipment | XIUCHENG LI | energy_progress |
| 06/05/2024 | Fire-Resistant Penetrations and Joints | XIUCHENG LI | special |
| 06/05/2024 | Energy Code Compliance Inspections | XIUCHENG LI | progress |
| 06/05/2024 | HVAC-R and service water heating system controls | XIUCHENG LI | energy_progress |
| 06/05/2024 | HVAC-R and service water piping design and insulation | XIUCHENG LI | energy_progress |
| 06/05/2024 | Maintenance information | XIUCHENG LI | energy_progress |
| 07/19/2023 | Structural Steel - Details | XIUCHENG LI | special |
| 07/19/2023 | Masonry | XIUCHENG LI | special |
| 07/19/2023 | Concrete - Cast-In-Place | XIUCHENG LI | special |
| 07/19/2023 | Structural Steel - High Strength Bolting | XIUCHENG LI | special |
| 07/19/2023 | Structural Steel - Welding | XIUCHENG LI | special |
| 07/19/2023 | Structural Stability – Alterations of existing buildings | XIUCHENG LI | special |