| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 08/24/2021 | $948K | — | Private party → Private party | $433/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| CHUN FENG, ARCHITECT | 1 | 09/10/2025 |
| ZHENG & ASSOCIATES LLC | 4 | 06/01/2023 |
| Representative | Filings | Most Recent |
|---|---|---|
| AMERGY SOLAR | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| AMERGY SOLAR INC | General Contractor | 1 | 04/09/2026 |
| ZAQ CONSTRUCTION INC | General Contractor | 1 | 07/08/2026 |
| HP SERVICES INC | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| SQ. ARCH, LLC | 4802 | 1 | 09/10/2025 |
| ZHENG & ASSOCIATES LLC | 7330 | 4 | 06/01/2023 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Solar | Signed-off | AMERGY SOLAR INC | 09/15/2025 |
| DOB NOW | General Construction | Permit Issued | ZAQ CONSTRUCTION INC | 12/28/2022 |
| DOB NOW | Plumbing | Signed-off | HP SERVICES INC | 12/15/2022 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/09/2025 | Complete | I.P. ELECTRIC INC | — |
| 01/04/2023 | Complete | R & T ELECTRICAL CORP | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/01/2023 | Permit Issued | ZAQ CONSTRUCTION INC | 1 scope_items |
| Date | Type | Result | Report |
|---|---|---|---|
| 08/29/2023 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 07/05/2023 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 06/05/2023 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 04/12/2023 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 02/21/2023 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 02/21/2023 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 06/12/2023 | Interior lighting power | Jinfar Liu | energy_progress |
| 06/12/2023 | Metering | Jinfar Liu | energy_progress |
| 06/12/2023 | Fire-Resistant Penetrations and Joints | Jinfar Liu | special |
| 06/12/2023 | Lighting controls | Jinfar Liu | energy_progress |
| 06/12/2023 | Energy Code Compliance Inspections | Jinfar Liu | progress |
| 06/01/2023 | Metering | Jinfar Liu | energy_progress |
| 06/01/2023 | Fire-Resistant Penetrations and Joints | Jinfar Liu | special |
| 06/01/2023 | Energy Code Compliance Inspections | Jinfar Liu | progress |
| 06/01/2023 | Interior lighting power | Jinfar Liu | energy_progress |
| 06/01/2023 | Lighting controls | Jinfar Liu | energy_progress |
| 11/29/2022 | Fire-Resistant Penetrations and Joints | Jinfar Liu | special |
| 11/29/2022 | HVAC-R and service water piping design and insulation | Jinfar Liu | energy_progress |
| 11/29/2022 | HVAC-R and service water heating system controls | Jinfar Liu | energy_progress |
| 11/29/2022 | HVAC-R and service water heating equipment | Jinfar Liu | energy_progress |
| 11/29/2022 | Energy Code Compliance Inspections | Jinfar Liu | progress |