← Back
Three families
86-22 101 AVENUE
QUEENS · Ozone Park (North) · BIN 4188999
💬 Discuss this project
1920Year Built
3Stories
C0Building Class
R6BZoning
3,306 sfGross Floor Area
3Units
Rent Stabilized0 Open ViolationsFDNY Report ↗
Three families · 2,040 sf lot · 1.62 FAR built · Flood zone X
Locations of Work
ArchitecturePlumbingCivil
Floor 37p · 1 filing · 20 docs
Floor 27p · 1 filing · 20 docs
Floor 17p · 1 filing · 20 docs
Cellar2p · 1 filing · 20 docs
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
11/10/2020$1.1M—— → —$342/sf building
01/13/2016$205K—Private party → Private party$62/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
CE ARCHITECT, PLLC305/07/2021
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
CE ARCHITECT, PLLC603/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
BALL MASONRY CONSTRUCTIONGeneral Contractor107/08/2026
TRI CITY MECHANICAL GROUP CORPPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
TRIANGLE INSPECTION & TES7495305/07/2021
Building Lifecycle
All (42)Filed (3)Permit Issued (2)Signed Off (2)Violation (10)Objection (6)Special Inspection (19)
05/07/2026
Violation issued (HPD, closed)
A
11/21/2025
Violation issued (HPD, closed)
I
03/04/2022
Violation issued (HPD, closed)
A
07/19/2021
Signed off — Alteration
HEREWITH FILED TO INSTALL A NEW BATHROOM ON 1ST THRU 3RD FLOORS, RELOCATE KITCHEN ON 1ST FLOOR WITH MINOR NON-LOAD BEARING PARTITIONS AND INSTALL NEW FLOOR FINISH OVER EXT'G VINYL TILE THROUGHOUT. NO CHANGE TO USE, EGRESS OR OCCUPANCY.
Q00447542-S1
06/23/2021
Signed off — Alteration
HEREWITH FILED TO INSTALL A NEW BATHROOM ON 1ST THRU 3RD FLOORS, RELOCATE KITCHEN ON 1ST FLOOR WITH MINOR NON-LOAD BEARING PARTITIONS AND INSTALL NEW FLOOR FINISH OVER EXT'G VINYL TILE THROUGHOUT. NO CHANGE TO USE, EGRESS OR OCCUPANCY.
Q00447542-I1
06/07/2021
Special inspection requirement — Fire-Resistant Penetrations and Joints
Rajasekhar Sakhamuri
06/07/2021
Special inspection requirement — Fire-Resistance Rated Construction
Rajasekhar Sakhamuri
06/07/2021
Special inspection requirement — Energy Code Compliance
Rajasekhar Sakhamuri
06/07/2021
Special inspection requirement — Fenestration areas
Rajasekhar Sakhamuri
06/07/2021
Special inspection requirement — Fenestration air leakage
Rajasekhar Sakhamuri
06/07/2021
Special inspection requirement — Insulation placement and R values
Rajasekhar Sakhamuri
06/07/2021
Special inspection requirement — Fenestration and door U-factor and product ratings
Rajasekhar Sakhamuri
06/07/2021
Special inspection requirement — Lighting in dwelling units
Rajasekhar Sakhamuri
06/07/2021
Special inspection requirement — Air barrier - visual inspection
Rajasekhar Sakhamuri
05/07/2021
Filed — Alteration
HEREWITH FILED TO INSTALL A NEW BATHROOM ON 1ST THRU 3RD FLOORS, RELOCATE KITCHEN ON 1ST FLOOR WITH MINOR NON-LOAD BEARING PARTITIONS AND INSTALL NEW FLOOR FINISH OVER EXT'G VINYL TILE THROUGHOUT. NO CHANGE TO USE, EGRESS OR OCCUPANCY.
Q00447542-P1
05/07/2021
Special inspection requirement — Lighting in dwelling units
Rajasekhar Sakhamuri
05/07/2021
Special inspection requirement — Fenestration areas
Rajasekhar Sakhamuri
05/07/2021
Special inspection requirement — Fire-Resistant Penetrations and Joints
Rajasekhar Sakhamuri
05/07/2021
Special inspection requirement — Energy Code Compliance
Rajasekhar Sakhamuri
05/07/2021
Special inspection requirement — Fire-Resistance Rated Construction
Rajasekhar Sakhamuri
05/07/2021
Special inspection requirement — Final
Rajasekhar Sakhamuri
05/07/2021
Special inspection requirement — Fenestration air leakage
Rajasekhar Sakhamuri
05/07/2021
Special inspection requirement — Air barrier - visual inspection
Rajasekhar Sakhamuri
05/07/2021
Special inspection requirement — Insulation placement and R values
Rajasekhar Sakhamuri
05/07/2021
Special inspection requirement — Fenestration and door U-factor and product ratings
Rajasekhar Sakhamuri
04/15/2021
Violation issued (HPD, closed)
A
03/24/2021
Permit issued — General Construction
Q00447542-I1-GC
02/10/2021
Permit issued — Plumbing
Q00447542-S1-PL
01/13/2021
Objection raised — Other
01/13/2021
Objection resolved — Addressed
01/13/2021
Objection raised — Other
01/13/2021
Objection resolved — Addressed
01/12/2021
Objection raised — Other
01/12/2021
Objection resolved — Addressed
01/07/2021
Filed — Alteration
HEREWITH FILED TO INSTALL A NEW BATHROOM ON 1ST THRU 3RD FLOORS, RELOCATE KITCHEN ON 1ST FLOOR WITH MINOR NON-LOAD BEARING PARTITIONS AND INSTALL NEW FLOOR FINISH OVER EXT'G VINYL TILE THROUGHOUT. NO CHANGE TO USE, EGRESS OR OCCUPANCY.
Q00447542-S1
01/07/2021
Filed — Alteration
HEREWITH FILED TO INSTALL A NEW BATHROOM ON 1ST THRU 3RD FLOORS, RELOCATE KITCHEN ON 1ST FLOOR WITH MINOR NON-LOAD BEARING PARTITIONS AND INSTALL NEW FLOOR FINISH OVER EXT'G VINYL TILE THROUGHOUT. NO CHANGE TO USE, EGRESS OR OCCUPANCY.
Q00447542-I1
12/04/2017
Violation issued (HPD, closed)
I
11/18/2016
Violation issued (HPD, closed)
I
10/15/2015
Violation issued (HPD, closed)
I
02/27/2015
Violation issued (HPD, closed)
I
12/22/2014
Violation issued (HPD, closed)
B
04/11/1997
Violation issued (HPD, closed)
A
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWGeneral ConstructionSigned-offBALL MASONRY CONSTRUCTION03/24/2021
DOB NOWPlumbingSigned-offFLAVIO MECHANICAL CORP02/10/2021
1 project · most recent 03/02/2021
General Wiring
FiledStatusContractorScope
03/02/2021CompleteA.M.A HOLDINGS INC.D/B/AGeneral Wiring
▾Special Inspection Requirements (DOB NOW) — 19
DateRequirementInspectorRole
06/07/2021Fire-Resistant Penetrations and JointsRajasekhar Sakhamurispecial
06/07/2021Fire-Resistance Rated ConstructionRajasekhar Sakhamuriprogress
06/07/2021Energy Code ComplianceRajasekhar Sakhamuriprogress
06/07/2021Fenestration areasRajasekhar Sakhamurienergy_progress
06/07/2021Fenestration air leakageRajasekhar Sakhamurienergy_progress
06/07/2021Insulation placement and R valuesRajasekhar Sakhamurienergy_progress
06/07/2021Fenestration and door U-factor and product ratingsRajasekhar Sakhamurienergy_progress
06/07/2021Lighting in dwelling unitsRajasekhar Sakhamurienergy_progress
06/07/2021Air barrier - visual inspectionRajasekhar Sakhamurienergy_progress
05/07/2021Lighting in dwelling unitsRajasekhar Sakhamurienergy_progress
05/07/2021Fenestration areasRajasekhar Sakhamurienergy_progress
05/07/2021Fire-Resistant Penetrations and JointsRajasekhar Sakhamurispecial
05/07/2021Energy Code ComplianceRajasekhar Sakhamuriprogress
05/07/2021Fire-Resistance Rated ConstructionRajasekhar Sakhamuriprogress
05/07/2021FinalRajasekhar Sakhamuriprogress
05/07/2021Fenestration air leakageRajasekhar Sakhamurienergy_progress
05/07/2021Air barrier - visual inspectionRajasekhar Sakhamurienergy_progress
05/07/2021Insulation placement and R valuesRajasekhar Sakhamurienergy_progress
05/07/2021Fenestration and door U-factor and product ratingsRajasekhar Sakhamurienergy_progress
▾Documents — 29 on file (BIS + DOB NOW)
▸Plans & Drawings3
▸DOB NOWPlans/Sketch - General Construction2
08/27/2026Q00447542-P1Request digital key ↗
08/14/2026Q00447542-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Plumbing1
08/15/2026Q00447542-S1Request digital key ↗
▸Seals & Professional Certifications22
▸DOB NOWProgress Inspector Seal & Signature17
08/23/2026Q00447542-I1Open ↗
08/23/2026Q00447542-I1Open ↗
08/23/2026Q00447542-I1Open ↗
Showing 3 of 17 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature3
08/13/2026Q00447542-P1Open ↗
08/13/2026Q00447542-S1Open ↗
08/13/2026Q00447542-I1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature2
08/23/2026Q00447542-I1Open ↗
08/23/2026Q00447542-P1Open ↗
▸Environmental & Asbestos3
▸DOB NOWDEP ACP-5: Asbestos Assessment Report3
08/13/2026Q00447542-S1Open ↗
08/13/2026Q00447542-P1Open ↗
08/13/2026Q00447542-I1Open ↗
▸Energy Compliance1
▸DOB NOWEN2: As Built Energy Analysis.1