← Back
Large suburban residence
86-29 PALERMO STREET
QUEENS · BIN 4224059
💬 Discuss this project
1955Year Built
2.5Stories
A3Building Class
R1-2Zoning
3,370 sfGross Floor Area
1Units
0 Open ViolationsFDNY Report ↗
Large suburban residence · Owner of record: PALERMO HOLDINGS LLC · 6,754 sf lot · 0.5 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralPlumbing
Floor 213p · 1 filing · 20 docs
Floor 113p · 1 filing · 20 docs
Cellar13p · 1 filing · 20 docs
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
08/31/2015$850K—Private party → PALERMO HOLDINGS LLC$252/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
GERALD CALIENDO ARCHITECTS707/29/2026
RAS PE CONSULTING ENGINEERS405/22/2026
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
GERALD J. CALIENDO R.A., P.C.903/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
NEW MILE STONE CONST CORPGeneral Contractor506/27/2026
AJIT ONE MECH&GEN'L CONTRPlumbing207/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
AA BUILDING & INSPECTION15191007/29/2026
Building Lifecycle
All (87)Filed (11)Permit Issued (7)Signed Off (5)Violation (1)Inspection (7)Objection (26)Special Inspection (30)
08/06/2026
Signed off — Alteration CO
Horizontal Extension of existing house. Change CO from 2 Family to 1 Family house.
Q00968468-S2
07/29/2026
Filed — Alteration CO
Horizontal Extension of existing house. Change CO from 2 Family to 1 Family house.
Q00968468-P8
07/24/2026
Special inspection requirement — Fenestration areas
Younes Abouyaala
07/24/2026
Special inspection requirement — Fenestration air leakage
Younes Abouyaala
07/24/2026
Special inspection requirement — Permanent certificate
Younes Abouyaala
07/24/2026
Special inspection requirement — Fenestration and door U-factor and product ratings
Younes Abouyaala
07/24/2026
Special inspection requirement — Insulation placement and R values
Younes Abouyaala
07/24/2026
Special inspection requirement — Interior lighting power
Younes Abouyaala
07/24/2026
Special inspection requirement — Electric vehicle service equipment requirements
Younes Abouyaala
07/24/2026
Special inspection requirement — Air barrier - visual inspection
Younes Abouyaala
07/24/2026
Special inspection requirement — Concrete - Cast-In-Place
Younes Abouyaala
07/24/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
Younes Abouyaala
07/24/2026
Special inspection requirement — Masonry
Younes Abouyaala
07/24/2026
Special inspection requirement — Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation
Younes Abouyaala
07/24/2026
Special inspection requirement — Structural Stability – Alterations of existing buildings
Younes Abouyaala
07/24/2026
Special inspection requirement — Structural Steel - Details
Younes Abouyaala
07/24/2026
Special inspection requirement — Structural Steel - High Strength Bolting
Younes Abouyaala
07/24/2026
Special inspection requirement — Structural Steel - Welding
Younes Abouyaala
07/24/2026
Special inspection requirement — Subgrade Inspections
Younes Abouyaala
07/24/2026
Special inspection requirement — Subsurface Conditions – Fill Placement & In-Place Density
Younes Abouyaala
07/24/2026
Special inspection requirement — Energy Code Compliance Inspections
Younes Abouyaala
07/24/2026
Special inspection requirement — Final
NAVEEN KUMAR
07/24/2026
Special inspection requirement — Fire-Resistance Rated Construction
Younes Abouyaala
07/24/2026
Special inspection requirement — Footing and Foundation
Younes Abouyaala
07/24/2026
Special inspection requirement — Structural Wood Frame
Younes Abouyaala
07/24/2026
Special inspection requirement — Protection of exposed foundation insulation
Younes Abouyaala
07/08/2026
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
06/25/2026
Signed off — Alteration CO
Horizontal Extension of existing house. Change CO from 2 Family to 1 Family house.
Q00968468-S3
06/24/2026
Signed off — Alteration CO
Horizontal Extension of existing house. Change CO from 2 Family to 1 Family house.
Q00968468-S5
06/24/2026
Signed off — Alteration CO
Horizontal Extension of existing house. Change CO from 2 Family to 1 Family house.
Q00968468-S4
06/10/2026
Special inspection requirement — Concrete - Cast-In-Place
Younes Abouyaala
06/10/2026
Special inspection requirement — Subsurface Investigations (Borings/Test Pits)
FAHAD FATEH
06/10/2026
Special inspection requirement — Underpinning
Younes Abouyaala
06/10/2026
Special inspection requirement — Subgrade Inspections
Younes Abouyaala
06/10/2026
Special inspection requirement — Footing and Foundation
Younes Abouyaala
06/10/2026
Special inspection requirement — Final
NAVEEN KUMAR
05/22/2026
Filed — Alteration CO
Horizontal Extension of existing house. Change CO from 2 Family to 1 Family house.
Q00968468-P7
05/06/2026
Permit issued — Plumbing
Q00968468-S2-PL
04/23/2026
Signed off — Alteration CO
Horizontal Extension of existing house. Change CO from 2 Family to 1 Family house.
Q00968468-S1
03/26/2026
Filed — Alteration CO
Horizontal Extension of existing house. Change CO from 2 Family to 1 Family house.
Q00968468-P6
12/01/2025
Objection resolved — Addressed
11/26/2025
Objection resolved — Addressed
11/25/2025
Objection raised — Plumbing
11/25/2025
Objection raised — Cost
11/07/2025
Filed — Alteration CO
Horizontal Extension of existing house. Change CO from 2 Family to 1 Family house.
Q00968468-P5
06/13/2025
Inspection — Certified Gas-Gas-Piping-Roughing
Certified
View inspection ↗
06/13/2025
Inspection — Certified Storm Drainage-ST-Piping-Underground
Certified
View inspection ↗
06/13/2025
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
04/09/2025
Permit issued — Plumbing
Q00968468-S2-PL
03/15/2025
Violation issued (ECB, closed)
Construction
01/29/2025
Permit issued — Structural
Q00968468-I1-GC-CX
01/10/2025
Filed — Alteration CO
Horizontal Extension of existing house. Change CO from 2 Family to 1 Family house.
Q00968468-P4
01/09/2025
Permit issued — Support of Excavation
Q00968468-S4-SE
01/09/2025
Permit issued — Foundation
Q00968468-S3-FO-EA
01/09/2025
Permit issued — Structural
Q00968468-S5-ST
01/07/2025
Permit issued — Construction Fence
Q00968468-S1-FN
10/29/2024
Inspection — Certified Gas-Gas-Piping-Roughing
Certified
View inspection ↗
10/29/2024
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
10/29/2024
Objection resolved — Addressed
10/24/2024
Objection raised — Structural
Latest 60 of 87 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingSigned-offAJIT ONE MECH&GEN'L CONTR05/06/2026
DOB NOWPlumbingSigned-offHAR JI PLUMBING& HEAT COR04/09/2025
DOB NOWStructuralPermit IssuedNEW MILE STONE CONST CORP01/29/2025
DOB NOWSupport of ExcavationSigned-offNEW MILE STONE CONST CORP01/09/2025
DOB NOWFoundationSigned-offNEW MILE STONE CONST CORP01/09/2025
DOB NOWStructuralSigned-offNEW MILE STONE CONST CORP01/09/2025
DOB NOWConstruction FenceSigned-offNEW MILE STONE CONST CORP01/07/2025
1 project · most recent 07/29/2026
Gas Storm Water/Sanitary
FiledStatusContractorScope
07/29/2026Signed-offAJIT ONE MECH&GEN'L CONTRGas, Storm, Water/Sanitary
1 project · most recent 02/18/2025
General Wiring
FiledStatusContractorScope
02/18/2025CompleteJOSEPH WEINSTEIN ELECTRICGeneral Wiring
1 project · most recent 07/29/2026
Steel Concrete Wood
FiledStatusContractorScope
07/29/2026Signed-offAJIT ONE MECH&GEN'L CONTRSteel, Concrete, Wood
▾Field Inspections (DOB CAP) — 7
DateTypeResultReport
07/08/2026Pass-Final CND-Occupancy InspectionPassView ↗
06/13/2025Certified Gas-Gas-Piping-RoughingCertifiedView ↗
06/13/2025Certified Storm Drainage-ST-Piping-UndergroundCertifiedView ↗
06/13/2025Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
10/29/2024Certified Gas-Gas-Piping-RoughingCertifiedView ↗
10/29/2024Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
10/01/2024Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 59
DateRequirementInspectorRole
07/24/2026Fenestration areasYounes Abouyaalaenergy_progress
07/24/2026Fenestration air leakageYounes Abouyaalaenergy_progress
07/24/2026Permanent certificateYounes Abouyaalaenergy_progress
07/24/2026Fenestration and door U-factor and product ratingsYounes Abouyaalaenergy_progress
07/24/2026Insulation placement and R valuesYounes Abouyaalaenergy_progress
07/24/2026Interior lighting powerYounes Abouyaalaenergy_progress
07/24/2026Electric vehicle service equipment requirementsYounes Abouyaalaenergy_progress
07/24/2026Air barrier - visual inspectionYounes Abouyaalaenergy_progress
07/24/2026Concrete - Cast-In-PlaceYounes Abouyaalaspecial
07/24/2026Fire-Resistant Penetrations and JointsYounes Abouyaalaspecial
07/24/2026MasonryYounes Abouyaalaspecial
07/24/2026Private On-Site Storm Water Disposal Systems-, and Detention Facilities, InstallationYounes Abouyaalaspecial
07/24/2026Structural Stability – Alterations of existing buildingsYounes Abouyaalaspecial
07/24/2026Structural Steel - DetailsYounes Abouyaalaspecial
07/24/2026Structural Steel - High Strength BoltingYounes Abouyaalaspecial
07/24/2026Structural Steel - WeldingYounes Abouyaalaspecial
07/24/2026Subgrade InspectionsYounes Abouyaalaspecial
07/24/2026Subsurface Conditions – Fill Placement & In-Place DensityYounes Abouyaalaspecial
07/24/2026Energy Code Compliance InspectionsYounes Abouyaalaprogress
07/24/2026FinalNAVEEN KUMARprogress
07/24/2026Fire-Resistance Rated ConstructionYounes Abouyaalaprogress
07/24/2026Footing and FoundationYounes Abouyaalaprogress
07/24/2026Structural Wood FrameYounes Abouyaalaprogress
07/24/2026Protection of exposed foundation insulationYounes Abouyaalaenergy_progress
06/10/2026Concrete - Cast-In-PlaceYounes Abouyaalaspecial
Latest 25 of 59.
▾Documents — 102 on file (BIS + DOB NOW)
▸Plans & Drawings11
▸DOB NOWPlans/Sketch11
08/16/2026Q00968468-P8Request digital key ↗
08/16/2026Q00968468-P4Request digital key ↗
08/16/2026Q00968468-S5Request digital key ↗
Showing 3 of 11 on file for this type
▸Applications & Permits3
▸BISPLAN / WORK APPROVAL APPLICATION3
02/09/2018421321858Open ↗
08/18/2016421321858Open ↗
06/09/2016421321858Open ↗
▸Zoning, Tax Lot & Property Records6
▸DOB NOWZD1: DOB Zoning Diagram4
08/16/2026Q00968468-P8Open ↗
08/13/2026Q00968468-I1Open ↗
08/13/2026Q00968468-P4Open ↗
Showing 3 of 4 on file for this type
▸BISZONING DIAGRAM1
08/19/2016421321858Open ↗
▸DOB NOWHouse Number Verification: TOPO Stamp1
08/13/2026Q00968468-I1Open ↗
▸Seals & Professional Certifications28
▸DOB NOWDPL-1: Design Professional Seal & Signature12
08/16/2026Q00968468-P8Open ↗
08/16/2026Q00968468-P6Open ↗
08/16/2026Q00968468-S3Open ↗
Showing 3 of 12 on file for this type
▸DOB NOWProgress Inspector Seal & Signature8
09/29/2026Q00968468-I1Open ↗
09/29/2026Q00968468-I1Open ↗
09/29/2026Q00968468-I1Open ↗
Showing 3 of 8 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature7
09/29/2026Q00968468-I1Open ↗
08/28/2026Q00968468-S3Open ↗
08/28/2026Q00968468-S3Open ↗
Showing 3 of 7 on file for this type
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION1
06/06/2018421321858Open ↗
▸Trade Schedules & Equipment1
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE1
06/09/2016421321858Open ↗
▸Safety & Tenant Protection6
▸DOB NOWStreet Tree Checklist4
08/16/2026Q00968468-P8Open ↗
08/13/2026Q00968468-P6Open ↗
08/13/2026Q00968468-P4Open ↗
Showing 3 of 4 on file for this type
▸BISDEMOLITION SUBMITTAL CERTIFICATION FORM1
06/06/2018421321858Open ↗
▸BISSTREET TREE CHECKLIST1
06/09/2016421321858Open ↗
▸Environmental & Asbestos12
▸DOB NOWDEP ACP-5: Asbestos Assessment Report11
08/16/2026Q00968468-P8Open ↗
08/16/2026Q00968468-P7Open ↗
08/16/2026Q00968468-P6Open ↗
Showing 3 of 11 on file for this type
▸BISASBESTOS: CERTIFICATION (DEP ACP5)1
06/09/2016421321858Open ↗
▸Energy Compliance1
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS1
06/06/2018421321858Open ↗
▸Inspections & Test Reports5
▸DOB NOWSOIL REPORT3
08/16/2026Q00968468-P7Open ↗
08/13/2026Q00968468-S4Open ↗
08/13/2026Q00968468-S3Open ↗
▸DOB NOWTR4 Test Report and Plot Diagram2
08/13/2026Q00968468-S4Open ↗
08/13/2026Q00968468-S3Open ↗
▸Approvals, Objections & Sign-offs2
▸BISLETTERS - SUPPORTING DOCUMENTATION1
06/06/2018421321858Open ↗
▸BISSCHEDULE A - OCCUPANCY / USE1
06/09/2016421321858Open ↗
▸Cost, Insurance & Ownership1
▸BISCOST AFFIDAVIT1
06/09/2016421321858Open ↗
▸Filing & Intake Forms2
▸BISADDITIONAL INFORMATION1
08/19/2016421321858Open ↗
▸BISEFILING COVER SHEET1
06/09/2016421321858Open ↗
▸Other Documents24
▸DOB NOWPlot Diagram7
08/16/2026Q00968468-P7Open ↗
08/16/2026Q00968468-P8Open ↗
08/13/2026Q00968468-S4Open ↗
Showing 3 of 7 on file for this type
▸DOB NOWSite Survey: Initial4
08/16/2026Q00968468-P8Open ↗
08/13/2026Q00968468-P6Open ↗
08/13/2026Q00968468-I1Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone4
08/16/2026Q00968468-P8Open ↗
08/13/2026Q00968468-P4Open ↗
08/13/2026Q00968468-I1Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWProperty Ownership Certification4
08/16/2026Q00968468-P6Open ↗
08/16/2026Q00968468-P8Open ↗
08/13/2026Q00968468-I1Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWAdjoining Owners Notification3
08/13/2026Q00968468-S4Open ↗
08/13/2026Q00968468-I1Open ↗
08/13/2026Q00968468-S3Open ↗
▸BISPLOT DIAGRAM1
08/18/2016421321858Open ↗
▸DOB NOWFinal Survey1
08/16/2026Q00968468-I1Open ↗