← Back
BuildNYC
One story - permanent living quarter
86-41 MARENGO STREET
QUEENS · BIN 4224297
💬 Discuss this project
1960Year Built
1Stories
A2Building Class
R1-2Zoning
2,349 sfGross Floor Area
1Units
4 Active Violations ▸FDNY Report ↗
One story - permanent living quarter · Owner of record: 8641 Marengo · 9,672 sf lot · 0.24 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralElectricalPlumbingEquipment
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
Permit Issued — active, not yet Signed-off
RoofUnder Construction2p · 1 filing · 20 docs
Floor 2Under Construction1p · 1 filing · 20 docs
Floor 1Under Construction1p · 1 filing · 20 docs
Sub-BasementUnder Construction1p · 1 filing · 20 docs
Filed — no permit issuedExcavation and soil monitoring13p · 1 filing · 9 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
8641 Marengo303/22/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
08/28/2025$1.8M—Private party → 8641 MARENGO LLC$745/sf building
09/19/2016$999K—Private party → Private party$425/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
Rizwan Salam511/16/2026
JBA204/07/2026
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
KC Expediting203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
FRSS GroupGeneral Contractor107/04/2026
All Pro Plumbing & HeatingPlumbing107/30/2026
Jarro Building IndustriesGeneral Contractor109/12/2003
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
AA Building & Inspection1519204/07/2026
Building Lifecycle
11/16/2026
Filed — Alteration
SOE FOR SITE RETAINING WALL
Q01440759-P3
11/03/2026
Filed — Alteration
SOE FOR SITE RETAINING WALL
Q01440759-P2
10/29/2026
Special inspection requirement — Concrete - Cast-In-Place
10/29/2026
Special inspection requirement — Footing and Foundation
10/29/2026
Special inspection requirement — Final
51 history events on file for this building. Sign in free to see the full history. Sign in · Create account
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingPermit IssuedAll Pro Plumbing & Heating07/29/2026
DOB NOWFoundationPermit IssuedFRSS Group07/02/2026
BISOTISSUEDJarro Building Industries09/12/2003
1 project · most recent 05/18/2026
General Wiring
FiledStatusContractorScope
05/18/2026Permit IssuedNas ElectricGeneral Wiring
1 project · most recent 11/16/2026
FiledStatusContractorScope
11/16/2026———
▾Field Inspections (DOB CAP) — 3
DateTypeResultReport
08/19/2026Certified Gas-Gas-Piping-RoughingCertifiedView ↗
08/19/2026Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
08/19/2026Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 43
DateRequirementInspectorRole
10/29/2026Concrete - Cast-In-Place—special
10/29/2026Footing and Foundation—progress
10/29/2026Final—progress
10/29/2026Subsurface Conditions – Fill Placement & In-Place Density—special
10/29/2026Subgrade Inspections—special
10/29/2026Structural Stability – Alterations of existing buildings—special
10/26/2026Structural Stability – Alterations of existing buildings—special
10/26/2026Subsurface Investigations (Borings/Test Pits)—special
10/26/2026Subgrade Inspections—special
10/26/2026Excavations - Sheeting, Shoring, and Bracing—special
10/14/2026Structural Stability – Alterations of existing buildings—special
10/14/2026Footing and Foundation—progress
10/14/2026Final—progress
10/14/2026Subsurface Conditions – Fill Placement & In-Place Density—special
10/14/2026Subgrade Inspections—special
10/14/2026Concrete - Cast-In-Place—special
08/17/2026Concrete - Cast-In-Place—special
08/17/2026Structural Stability – Alterations of existing buildings—special
08/17/2026Subsurface Conditions – Fill Placement & In-Place Density—special
08/17/2026Structural Stability – Alterations of existing buildings—special
08/17/2026Subgrade Inspections—special
08/04/2026Footing and Foundation—progress
08/04/2026Final—progress
08/04/2026Subgrade Inspections—special
08/04/2026Excavations - Sheeting, Shoring, and Bracing—special
Latest 25 of 43.
33 filed documents on file for this building. Sign in free to see the full history. Sign in · Create account