← Back
Two stories - detached, small or mid-size
86-66 109 STREET
QUEENS · Richmond Hill · BIN 4192169
💬 Discuss this project
1915Year Built
2.5Stories
A1Building Class
R3XZoning
1,380 sfGross Floor Area
1Units
10 Open Violations 8 unresolved · 2 paperwork only ▸FDNY Report ↗
Two stories - detached, small or mid-size · 2,625 sf lot · 0.53 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralPlumbing
Permit Issued — active, not yet Signed-off
Floor 2Under Construction7p · 2 filings · 20 docs
Floor 1Under Construction7p · 2 filings · 20 docs
CellarUnder Construction8p · 2 filings · 20 docs
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
A&A CONSULTING ENGINEERS PC505/12/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
NEW LEONARD CONSTRUCTIONGeneral Contractor404/09/2026
BT'S PLUMBING AND HEATINGPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
HRF SERVICES CORP5616305/12/2026
Building Lifecycle
All (64)Filed (5)Permit Issued (3)Violation (12)Inspection (1)Objection (24)Special Inspection (19)
08/10/2026
Violation issued (ECB, open)
Construction
08/10/2026
Violation issued (ECB, open)
Construction
08/10/2026
Violation issued (ECB, open)
Construction
08/10/2026
Violation issued (ECB, open)
Unknown
05/12/2026
Filed — Alteration CO
PROPOSE HORIZONTAL EXTENSION AT THE REAR OF THE BUILDING W/ INTERIOR RENOVATIONS AS NOTED ON PLANS. WORK IN RESPONSE TO RESOLVE VIOLATION# 34208408H, 35020773H, & COMPLAINT# 4978732 & 4984837
Q01164547-P1
05/12/2026
Filed — Alteration
PROPOSE HORIZONTAL EXTENSION AT THE REAR OF THE BUILDING W/ INTERIOR RENOVATIONS AS NOTED ON PLANS. WORK IN RESPONSE TO RESOLVE VIOLATION# 34208408H, 35020773H, & COMPLAINT# 4978732 & 4984837
Q01334942-P1
05/11/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
SHAHRIAR QUAYYUM
04/30/2026
Violation issued (ECB, open)
Construction
04/16/2026
Inspection — Certified Storm Drainage-ST-Piping-Roughing
Certified
View inspection ↗
01/21/2026
Permit issued — Plumbing
Q01334942-I1-PL
01/15/2026
Objection resolved — Addressed
01/07/2026
Objection resolved — Addressed
01/06/2026
Objection raised — Cost
01/05/2026
Objection resolved — Addressed
01/03/2026
Objection raised — Zoning
01/03/2026
Objection raised — Plumbing
12/19/2025
Filed — Alteration
PROPOSE HORIZONTAL EXTENSION AT THE REAR OF THE BUILDING W/ INTERIOR RENOVATIONS AS NOTED ON PLANS. WORK IN RESPONSE TO RESOLVE VIOLATION# 34208408H, 35020773H, & COMPLAINT# 4978732 & 4984837
Q01334942-I1
12/15/2025
Permit issued — General Construction
Q01164547-S1-GC
12/10/2025
Permit issued — Structural
Q01164547-I1-GC-CX
11/19/2025
Objection resolved — Addressed
11/17/2025
Objection resolved — Addressed
10/21/2025
Objection resolved — Addressed
10/20/2025
Objection resolved — Addressed
10/15/2025
Objection raised — Zoning
10/15/2025
Objection raised — Other
10/15/2025
Objection raised — Other
10/15/2025
Objection raised — Cost
10/09/2025
Filed — Alteration CO
PROPOSE HORIZONTAL EXTENSION AT THE REAR OF THE BUILDING W/ INTERIOR RENOVATIONS AS NOTED ON PLANS. WORK IN RESPONSE TO RESOLVE VIOLATION# 34208408H, 35020773H, & COMPLAINT# 4978732 & 4984837
Q01164547-S1
08/27/2025
Objection resolved — Addressed
08/22/2025
Objection resolved — Addressed
07/28/2025
Special inspection requirement — Maintenance information
SHAHRIAR QUAYYUM
07/28/2025
Special inspection requirement — Metering
SHAHRIAR QUAYYUM
05/28/2025
Objection raised — Energy
05/15/2025
Objection resolved — Addressed
05/15/2025
Objection resolved — Addressed
04/15/2025
Objection raised — Plumbing
04/11/2025
Objection resolved — Addressed
04/11/2025
Special inspection requirement — Fenestration air leakage
SHAHRIAR QUAYYUM
04/11/2025
Special inspection requirement — Air barrier - visual inspection
SHAHRIAR QUAYYUM
04/11/2025
Special inspection requirement — Fenestration and door U-factor and product ratings
SHAHRIAR QUAYYUM
04/11/2025
Special inspection requirement — Fenestration areas
SHAHRIAR QUAYYUM
04/11/2025
Special inspection requirement — Insulation placement and R values
SHAHRIAR QUAYYUM
04/07/2025
Special inspection requirement — Structural Wood Frame
SHAHRIAR QUAYYUM
04/07/2025
Special inspection requirement — Concrete - Cast-In-Place
SHAHRIAR QUAYYUM
04/07/2025
Special inspection requirement — Excavations - Sheeting, Shoring, and Bracing
SHAHRIAR QUAYYUM
04/07/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
SHAHRIAR QUAYYUM
04/07/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
SHAHRIAR QUAYYUM
04/07/2025
Special inspection requirement — Subgrade Inspections
SHAHRIAR QUAYYUM
04/07/2025
Special inspection requirement — Underpinning
SHAHRIAR QUAYYUM
04/07/2025
Special inspection requirement — Energy Code Compliance Inspections
SHAHRIAR QUAYYUM
04/07/2025
Special inspection requirement — Fire-Resistance Rated Construction
SHAHRIAR QUAYYUM
02/05/2025
Objection raised — Cost
02/05/2025
Objection raised — Admin
02/05/2025
Objection raised — Other
01/23/2025
Filed — Alteration CO
PROPOSE HORIZONTAL EXTENSION AT THE REAR OF THE BUILDING W/ INTERIOR RENOVATIONS AS NOTED ON PLANS. WORK IN RESPONSE TO RESOLVE VIOLATION# 34208408H, 35020773H, & COMPLAINT# 4978732 & 4984837
Q01164547-I1
01/08/2025
Special inspection requirement — Footing and Foundation
SHAHRIAR QUAYYUM
01/08/2025
Special inspection requirement — Final
SHAHRIAR QUAYYUM
11/12/2024
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
11/12/2024
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
11/12/2024
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
Latest 60 of 64 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingPermit IssuedBT'S PLUMBING AND HEATING01/21/2026
DOB NOWGeneral ConstructionPermit IssuedNEW LEONARD CONSTRUCTION12/15/2025
DOB NOWStructuralPermit IssuedNEW LEONARD CONSTRUCTION12/10/2025
BISPLISSUEDJOSEPH O FERRARA &SONS INC03/20/2001
BIS—ISSUEDN.A01/10/2000
1 project · most recent 05/12/2026
Gas Water/Sanitary
FiledStatusContractorScope
05/12/2026Permit IssuedBT'S PLUMBING AND HEATINGGas, Water/Sanitary
2 projects · most recent 01/26/2026
General Wiring
FiledStatusContractorScope
01/26/2026Permit IssuedJOSEPH WEINSTEIN ELECTRICGeneral Wiring
01/26/2026Permit IssuedJOSEPH WEINSTEIN ELECTRICGeneral Wiring
1 project · most recent 05/12/2026
Wood
FiledStatusContractorScope
05/12/2026Permit IssuedNEW LEONARD CONSTRUCTIONWood
1 project · most recent 05/12/2026
Earthwork
FiledStatusContractorScope
05/12/2026Permit IssuedNEW LEONARD CONSTRUCTIONEarthwork
▾Field Inspections (DOB CAP) — 1
DateTypeResultReport
04/16/2026Certified Storm Drainage-ST-Piping-RoughingCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 19
DateRequirementInspectorRole
05/11/2026Fire-Resistant Penetrations and JointsSHAHRIAR QUAYYUMspecial
07/28/2025Maintenance informationSHAHRIAR QUAYYUMenergy_progress
07/28/2025MeteringSHAHRIAR QUAYYUMenergy_progress
04/11/2025Fenestration air leakageSHAHRIAR QUAYYUMenergy_progress
04/11/2025Air barrier - visual inspectionSHAHRIAR QUAYYUMenergy_progress
04/11/2025Fenestration and door U-factor and product ratingsSHAHRIAR QUAYYUMenergy_progress
04/11/2025Fenestration areasSHAHRIAR QUAYYUMenergy_progress
04/11/2025Insulation placement and R valuesSHAHRIAR QUAYYUMenergy_progress
04/07/2025Structural Wood FrameSHAHRIAR QUAYYUMprogress
04/07/2025Concrete - Cast-In-PlaceSHAHRIAR QUAYYUMspecial
04/07/2025Excavations - Sheeting, Shoring, and BracingSHAHRIAR QUAYYUMspecial
04/07/2025Fire-Resistant Penetrations and JointsSHAHRIAR QUAYYUMspecial
04/07/2025Structural Stability – Alterations of existing buildingsSHAHRIAR QUAYYUMspecial
04/07/2025Subgrade InspectionsSHAHRIAR QUAYYUMspecial
04/07/2025UnderpinningSHAHRIAR QUAYYUMspecial
04/07/2025Energy Code Compliance InspectionsSHAHRIAR QUAYYUMprogress
04/07/2025Fire-Resistance Rated ConstructionSHAHRIAR QUAYYUMprogress
01/08/2025Footing and FoundationSHAHRIAR QUAYYUMprogress
01/08/2025FinalSHAHRIAR QUAYYUMprogress
▾Documents — 30 on file (BIS + DOB NOW)
▸Plans & Drawings5
▸DOB NOWPlans/Sketch5
08/16/2026Q01164547-S1Request digital key ↗
08/16/2026Q01164547-I1Request digital key ↗
08/16/2026Q01164547-P1Request digital key ↗
Showing 3 of 5 on file for this type
▸Zoning, Tax Lot & Property Records2
▸DOB NOWZD1: DOB Zoning Diagram1
08/13/2026Q01164547-I1Open ↗
▸DOB NOWHouse Number Verification: TOPO Stamp1
08/13/2026Q01164547-I1Open ↗
▸Seals & Professional Certifications9
▸DOB NOWDPL-1: Design Professional Seal & Signature5
08/16/2026Q01164547-I1Open ↗
08/16/2026Q01164547-P1Open ↗
08/16/2026Q01164547-S1Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWProgress Inspector Seal & Signature2
08/31/2026Q01164547-I1Open ↗
08/31/2026Q01164547-I1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature2
08/31/2026Q01164547-I1Open ↗
08/23/2026Q01334942-P1Open ↗
▸Safety & Tenant Protection3
▸DOB NOWStreet Tree Checklist3
08/16/2026Q01164547-P1Open ↗
08/13/2026Q01164547-S1Open ↗
08/13/2026Q01164547-I1Open ↗
▸Inspections & Test Reports1
▸DOB NOWGeotechnical Report (BC 1803.6)1
08/13/2026Q01164547-I1Open ↗
▸Other Documents10
▸DOB NOWPlot Diagram3
08/16/2026Q01164547-P1Open ↗
08/13/2026Q01164547-I1Open ↗
08/13/2026Q01164547-S1Open ↗
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone3
08/16/2026Q01164547-P1Open ↗
08/13/2026Q01164547-I1Open ↗
08/13/2026Q01164547-S1Open ↗
▸DOB NOWSite Survey: Initial2
08/16/2026Q01164547-P1Open ↗
08/13/2026Q01164547-S1Open ↗
▸DOB NOWProperty Ownership Certification1
08/16/2026Q01164547-I1Open ↗
▸DOB NOWAdjoining Owners Notification1
08/13/2026Q01164547-I1Open ↗