86-87 PALERMO STREET
QUEENS · BIN 4223974
💬 Discuss this project
1935Year Built
2.5Stories
A1Building Class
R1-2Zoning
2,320 sfGross Floor Area
1Units
Two stories - detached, small or mid-size · 6,450 sf lot · 0.36 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralPlumbingGeneral
Permit Issued — active, not yet Signed-off
Floor 2Under Construction42p · 1 filing · 20 docs
Floor 1Under Construction42p · 1 filing · 20 docs
CellarUnder Construction43p · 1 filing · 20 docs
1 job · most recent 08/07/2026
Air Conditioning Systems Ventilation Systems
FiledStatusContractorScopeMake / Model / Capacity
08/07/2026Permit IssuedTJAR GROUP CORPAir Conditioning Systems, Ventilation Systems
Cooling
Mitsubishi Electric M4H36W06060615-B 400,000 BTU ×6
Heating
Mitsubishi Electric M4H36W06060615-B 400,000 BTU ×6
Ventilation
Mitsubishi Electric M4H36W06060615-B 38,000 BTU ×3
1 job · most recent 08/07/2026
Gas Storm Water/Sanitary
FiledStatusContractorScope
08/07/2026Permit IssuedRAYMOND'S PLBG & HTG LLCGas, Storm, Water/Sanitary
1 job · most recent 06/23/2026
General Wiring
FiledStatusContractorScope
06/23/2026Permit IssuedKINGS ELECTRIC CO., INC.General Wiring
1 job · most recent 08/07/2026
Steel Concrete Wood
FiledStatusContractorScope
08/07/2026Permit IssuedTJAR GROUP CORPSteel, Concrete, Wood
1 job · most recent 08/07/2026
Fence
FiledStatusContractorScope
08/07/2026Permit IssuedTJAR GROUP CORPFence
1 job · most recent 08/07/2026
Earthwork
FiledStatusContractorScope
08/07/2026Permit IssuedTJAR GROUP CORPEarthwork
Building Lifecycle
All (67)Filed (8)Permit Issued (9)Signed Off (3)Inspection (5)Objection (12)Special Inspection (30)
08/19/2026
Signed off — ALT-CO - New Building with Existing Elements to Remain
HEREWITH FILE ALTERATION IN ORDER TO ERECT TEMPORARY CONSTRUCTION PLYWOOD FENCCE.
Q01266827-S5
08/07/2026
Filed — ALT-CO - New Building with Existing Elements to Remain
HEREWITH FILE ALTERATION IN ORDER TO ERECT TEMPORARY CONSTRUCTION PLYWOOD FENCCE.
Q01266827-P2
08/07/2026
Signed off — ALT-CO - New Building with Existing Elements to Remain
HEREWITH FILE ALTERATION IN ORDER TO ERECT TEMPORARY CONSTRUCTION PLYWOOD FENCCE.
Q01266827-S4
07/27/2026
Special inspection requirement — HVAC-R and service water heating equipment
Younes Abouyaala
07/27/2026
Special inspection requirement — HVAC-R and service water heating system controls
Younes Abouyaala
07/27/2026
Special inspection requirement — Maintenance information
Younes Abouyaala
07/27/2026
Special inspection requirement — Permanent certificate
Younes Abouyaala
07/27/2026
Special inspection requirement — HVAC-R and service water piping design and insulation
Younes Abouyaala
07/27/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
Younes Abouyaala
07/27/2026
Special inspection requirement — Soil Percolation Test - Private On-Site Storm Water Drainage Disposal Systems, and Detention Facilities
Younes Abouyaala
07/27/2026
Special inspection requirement — Subsurface Investigations (Borings/Test Pits)
FAHAD FATEH
07/27/2026
Special inspection requirement — Energy Code Compliance Inspections
Younes Abouyaala
06/24/2026
Inspection — Certified Gas-Gas-Piping-Roughing
Certified
View inspection ↗
06/24/2026
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
06/24/2026
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Underground
Certified
View inspection ↗
06/10/2026
Permit issued — General Construction
Q01266827-I1-GC
06/03/2026
Inspection — Certified Storm Drainage-ST-Piping-Underground
Certified
View inspection ↗
06/03/2026
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Underground
Certified
View inspection ↗
05/06/2026
Permit issued — Plumbing
Q01266827-S6-PL
04/28/2026
Signed off — ALT-CO - New Building with Existing Elements to Remain
HEREWITH FILE ALTERATION IN ORDER TO ERECT TEMPORARY CONSTRUCTION PLYWOOD FENCCE.
Q01266827-S3
04/09/2026
Filed — ALT-CO - New Building with Existing Elements to Remain
HEREWITH FILE ALTERATION IN ORDER TO ERECT TEMPORARY CONSTRUCTION PLYWOOD FENCCE.
Q01266827-P1
03/06/2026
Special inspection requirement — Insulation placement and R values
Younes Abouyaala
03/06/2026
Special inspection requirement — Energy Code Compliance Inspections
Younes Abouyaala
03/06/2026
Special inspection requirement — Final
NAVEEN KUMAR
03/06/2026
Special inspection requirement — Fire-Resistance Rated Construction
Younes Abouyaala
03/06/2026
Special inspection requirement — Permanent certificate
Younes Abouyaala
03/06/2026
Special inspection requirement — Fenestration and door U-factor and product ratings
Younes Abouyaala
03/06/2026
Special inspection requirement — HVAC-R and service water heating system controls
Younes Abouyaala
03/06/2026
Special inspection requirement — Air barrier — testing
Younes Abouyaala
03/06/2026
Special inspection requirement — Protection of exposed foundation insulation
Younes Abouyaala
03/06/2026
Special inspection requirement — Ventilation and air distribution system
Younes Abouyaala
03/06/2026
Special inspection requirement — Maintenance information
Younes Abouyaala
03/06/2026
Special inspection requirement — Fenestration air leakage
Younes Abouyaala
03/06/2026
Special inspection requirement — HVAC-R and service water piping design and insulation
Younes Abouyaala
03/06/2026
Special inspection requirement — Fenestration areas
Younes Abouyaala
03/06/2026
Special inspection requirement — Duct leakage testing, insulation and design
Younes Abouyaala
03/06/2026
Special inspection requirement — HVAC-R and service water heating equipment
Younes Abouyaala
03/06/2026
Special inspection requirement — Fireplaces
Younes Abouyaala
03/06/2026
Special inspection requirement — Interior lighting power
Younes Abouyaala
03/06/2026
Special inspection requirement — Air barrier - visual inspection
Younes Abouyaala
03/06/2026
Special inspection requirement — Exterior lighting power
Younes Abouyaala
03/06/2026
Special inspection requirement — Concrete - Cast-In-Place
Younes Abouyaala
02/26/2026
Objection resolved — Addressed
01/27/2026
Permit issued — Foundation
Q01266827-S4-FO
12/26/2025
Permit issued — Support of Excavation
Q01266827-S3-SE
12/19/2025
Objection raised — Energy
12/16/2025
Filed — ALT-CO - New Building with Existing Elements to Remain
HEREWITH FILE ALTERATION IN ORDER TO ERECT TEMPORARY CONSTRUCTION PLYWOOD FENCCE.
Q01266827-S6
12/03/2025
Permit issued — General Construction
Q01266827-I1-MS
12/03/2025
Permit issued — General Construction
Q01266827-I1-GC
11/17/2025
Objection resolved — Addressed
11/14/2025
Permit issued — Structural
Q01266827-S5-ST
11/13/2025
Permit issued — Construction Fence
Q01266827-S2-FN
11/05/2025
Objection raised — Cost
10/27/2025
Permit issued — Construction Fence
Q01266827-S2-FN
10/25/2025
Filed — ALT-CO - New Building with Existing Elements to Remain
HEREWITH FILE ALTERATION IN ORDER TO ERECT TEMPORARY CONSTRUCTION PLYWOOD FENCCE.
Q01266827-S5
10/25/2025
Filed — ALT-CO - New Building with Existing Elements to Remain
HEREWITH FILE ALTERATION IN ORDER TO ERECT TEMPORARY CONSTRUCTION PLYWOOD FENCCE.
Q01266827-S3
10/24/2025
Filed — ALT-CO - New Building with Existing Elements to Remain
HEREWITH FILE ALTERATION IN ORDER TO ERECT TEMPORARY CONSTRUCTION PLYWOOD FENCCE.
Q01266827-S4
10/14/2025
Objection resolved — Addressed
10/14/2025
Objection resolved — Addressed
09/29/2025
Objection resolved — Addressed
Latest 60 of 67 events.
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
06/27/2025$1.6M—Private party → Private party$690/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
GERALD CALIENDO ARCHITECTS508/07/2026
NYC SPECIAL CONTRACTORS310/25/2025
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
DMCONSULTING68601203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
TJAR GROUP CORPGeneral Contractor707/08/2026
GOLDEN TIME CONTRACTING IGeneral Contractor104/09/2026
RAYMOND'S PLBG & HTG LLCPlumbing106/28/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
AA BUILDING & INSPECTION1519708/07/2026
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWGeneral ConstructionPermit IssuedTJAR GROUP CORP06/10/2026
DOB NOWPlumbingPermit IssuedRAYMOND'S PLBG & HTG LLC05/06/2026
DOB NOWFoundationSigned-offTJAR GROUP CORP01/27/2026
DOB NOWSupport of ExcavationSigned-offTJAR GROUP CORP12/26/2025
DOB NOWGeneral ConstructionPermit IssuedTJAR GROUP CORP12/03/2025
DOB NOWGeneral ConstructionPermit IssuedTJAR GROUP CORP12/03/2025
DOB NOWStructuralSigned-offTJAR GROUP CORP11/14/2025
DOB NOWConstruction FencePermit IssuedTJAR GROUP CORP11/13/2025
DOB NOWConstruction FencePermit IssuedGOLDEN TIME CONTRACTING I10/27/2025
▾Field Inspections (DOB CAP) — 5
DateTypeResultReport
06/24/2026Certified Gas-Gas-Piping-RoughingCertifiedView ↗
06/24/2026Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
06/24/2026Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
06/03/2026Certified Storm Drainage-ST-Piping-UndergroundCertifiedView ↗
06/03/2026Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 57
DateRequirementInspectorRole
07/27/2026HVAC-R and service water heating equipmentYounes Abouyaalaenergy_progress
07/27/2026HVAC-R and service water heating system controlsYounes Abouyaalaenergy_progress
07/27/2026Maintenance informationYounes Abouyaalaenergy_progress
07/27/2026Permanent certificateYounes Abouyaalaenergy_progress
07/27/2026HVAC-R and service water piping design and insulationYounes Abouyaalaenergy_progress
07/27/2026Fire-Resistant Penetrations and JointsYounes Abouyaalaspecial
07/27/2026Soil Percolation Test - Private On-Site Storm Water Drainage Disposal Systems, and Detention FacilitiesYounes Abouyaalaspecial
07/27/2026Subsurface Investigations (Borings/Test Pits)FAHAD FATEHspecial
07/27/2026Energy Code Compliance InspectionsYounes Abouyaalaprogress
03/06/2026Insulation placement and R valuesYounes Abouyaalaenergy_progress
03/06/2026Energy Code Compliance InspectionsYounes Abouyaalaprogress
03/06/2026FinalNAVEEN KUMARprogress
03/06/2026Fire-Resistance Rated ConstructionYounes Abouyaalaprogress
03/06/2026Permanent certificateYounes Abouyaalaenergy_progress
03/06/2026Fenestration and door U-factor and product ratingsYounes Abouyaalaenergy_progress
03/06/2026HVAC-R and service water heating system controlsYounes Abouyaalaenergy_progress
03/06/2026Air barrier — testing Younes Abouyaalaenergy_progress
03/06/2026Protection of exposed foundation insulationYounes Abouyaalaenergy_progress
03/06/2026Ventilation and air distribution systemYounes Abouyaalaenergy_progress
03/06/2026Maintenance informationYounes Abouyaalaenergy_progress
03/06/2026Fenestration air leakageYounes Abouyaalaenergy_progress
03/06/2026HVAC-R and service water piping design and insulationYounes Abouyaalaenergy_progress
03/06/2026Fenestration areasYounes Abouyaalaenergy_progress
03/06/2026Duct leakage testing, insulation and designYounes Abouyaalaenergy_progress
03/06/2026HVAC-R and service water heating equipmentYounes Abouyaalaenergy_progress
Latest 25 of 57.
▾Documents — 77 on file (BIS + DOB NOW)
▸Plans & Drawings8
▸DOB NOWPlans/Sketch8
08/18/2026Q01266827-S6Request digital key ↗
08/18/2026Q01266827-P1Request digital key ↗
08/18/2026Q01266827-I1Request digital key ↗
Showing 3 of 8 on file for this type
▸Zoning, Tax Lot & Property Records6
▸DOB NOWZD1: DOB Zoning Diagram2
08/13/2026Q01266827-P1Open ↗
08/13/2026Q01266827-I1Open ↗
▸DOB NOWHouse Number Verification: TOPO Stamp2
08/13/2026Q01266827-I1Open ↗
08/13/2026Q01266827-P1Open ↗
▸DOB NOWZoning Exhibit form (1-5)2
08/13/2026Q01266827-P1Open ↗
08/13/2026Q01266827-I1Open ↗
▸Seals & Professional Certifications39
▸DOB NOWProgress Inspector Seal & Signature19
08/24/2026Q01266827-P1Open ↗
08/24/2026Q01266827-P1Open ↗
08/24/2026Q01266827-P1Open ↗
Showing 3 of 19 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature12
09/24/2026Q01266827-S3Open ↗
08/24/2026Q01266827-P1Open ↗
08/24/2026Q01266827-P1Open ↗
Showing 3 of 12 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature8
08/18/2026Q01266827-P2Open ↗
08/13/2026Q01266827-P1Open ↗
08/13/2026Q01266827-S6Open ↗
Showing 3 of 8 on file for this type
▸Safety & Tenant Protection1
▸DOB NOWParks Department Acknowledgment Letter for Street Trees Plan1
08/13/2026Q01266827-I1Open ↗
▸Environmental & Asbestos7
▸DOB NOWDEP ACP-5: Asbestos Assessment Report7
08/18/2026Q01266827-P2Open ↗
08/13/2026Q01266827-S5Open ↗
08/13/2026Q01266827-S6Open ↗
Showing 3 of 7 on file for this type
▸Inspections & Test Reports8
▸DOB NOWSOIL REPORT4
08/18/2026Q01266827-P2Open ↗
08/13/2026Q01266827-P1Open ↗
08/13/2026Q01266827-S6Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWGeotechnical Report (BC 1803.6)2
08/13/2026Q01266827-S4Open ↗
08/13/2026Q01266827-S3Open ↗
▸DOB NOWTR4 Test Report and Plot Diagram2
08/13/2026Q01266827-S6Open ↗
08/13/2026Q01266827-I1Open ↗
▸Other Documents8
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone2
08/13/2026Q01266827-P1Open ↗
08/13/2026Q01266827-I1Open ↗
▸DOB NOWProperty Ownership Certification2
08/13/2026Q01266827-P1Open ↗
08/13/2026Q01266827-I1Open ↗
▸DOB NOWSite Survey: Initial2
08/13/2026Q01266827-I1Open ↗
08/13/2026Q01266827-P1Open ↗
▸DOB NOWAdjoining Owners Notification1
08/13/2026Q01266827-S3Open ↗
▸DOB NOWPARTIAL DEMO: 10-DAY Notice1
08/13/2026Q01266827-S5Open ↗