← Back
BuildNYC
Office only, 2-6 stories
860 PACIFIC STREET
BROOKLYN · Prospect Heights · BIN 3424141
💬 Discuss this project
2019Year Built
4Stories
O2Building Class
R6BZoning
43,292 sfGross Floor Area
1Units
0 Active ViolationsFDNY Report ↗
Office only, 2-6 stories · 13,825 sf lot · 3.13 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralMechanicalPlumbingFire ProtectionEquipmentGeneral
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
Permit Issued — active, not yet Signed-off
Whole building & multi-floor projectsDiocese of BrooklynUnder Construction1 filing
Floor 4Pipe scaffold for facade repair2 filings
Floor 3Pipe scaffold for facade repair2 filings
Floor 2Pipe scaffold for facade repair2 filings
Floor 1Pipe scaffold for facade repair2 filings
Cellar1 filing
Site & exteriorDesales Media Group4 filings · 7 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
Co-Cathedral of St Joseph3403/22/2026
Rocklyn Asset810/13/2026
Desales Media Group607/08/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
AKF Engineers303/27/2026
PBDW Architects203/26/2026
Paul Perdek, Prof. Engineering212/17/2020
Scalar Architecture101/07/2020
Permanen Engineering International101/30/2018
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
AE Design Solution603/21/2026
KAS103/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
Core Scaffold SystemsScaffold2407/08/2026
Fazio Construction GroupGeneral Contractor507/08/2026
J.A. JenningsScaffold407/08/2026
CKC Contracting Corp DbaElectrical203/21/2026
CKC Contracting Corp DbaGeneral Contractor203/22/2026
Stasi/Dallas Electrical ContElectrical103/22/2026
James SegerElectrical103/21/2026
CKC Contracting Corp DbaElectrical103/22/2026
Magic MechanicalPlumbing108/30/2026
Magic MechanicalFire Protection109/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
C.M. Testing Laboratory1352303/27/2026
Building Lifecycle
All (101)Filed (9)Permit Issued (17)Signed Off (4)Violation (47)Objection (4)Special Inspection (20)
09/03/2026
Permit issued — Sprinklers
B01378819-S3-EW-SP
08/28/2026
Permit issued — Plumbing
B01378819-S2-PL
04/27/2026
Permit issued — General Construction
B01378819-I1-GC
04/27/2026
Permit issued — Mechanical Systems
B01378819-S1-MS
03/27/2026
Filed — Alteration
Modification to sprinkler system as per plans
B01378819-S1
03/27/2026
Filed — Alteration
Modification to sprinkler system as per plans
B01378819-S3
03/27/2026
Filed — Alteration
Modification to sprinkler system as per plans
B01378819-S2
03/26/2026
Filed — Alteration
Modification to sprinkler system as per plans
B01378819-I1
03/26/2026
Special inspection requirement — Maintenance information
JOHN SEMIOLI
03/26/2026
Special inspection requirement — Energy Code Compliance Inspections
JOHN SEMIOLI
03/26/2026
Special inspection requirement — Fire-Resistance Rated Construction
JOHN SEMIOLI
03/26/2026
Special inspection requirement — Final
JOHN SEMIOLI
03/26/2026
Special inspection requirement — Sprinkler Systems
03/26/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
03/26/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
JOHN SEMIOLI
03/26/2026
Special inspection requirement — Mechanical Systems
JOHN SEMIOLI
03/26/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
JOHN SEMIOLI
03/26/2026
Special inspection requirement — Post-installed Anchors
JOHN SEMIOLI
03/26/2026
Special inspection requirement — Final
JOHN SEMIOLI
03/26/2026
Special inspection requirement — Energy Code Compliance Inspections
JOHN SEMIOLI
03/26/2026
Special inspection requirement — Metering
JOHN SEMIOLI
03/26/2026
Special inspection requirement — HVAC-R and service water heating equipment
JOHN SEMIOLI
03/26/2026
Special inspection requirement — Shutoff dampers
JOHN SEMIOLI
03/26/2026
Special inspection requirement — HVAC-R and service water piping design and insulation
JOHN SEMIOLI
03/26/2026
Special inspection requirement — Lighting controls
JOHN SEMIOLI
03/26/2026
Special inspection requirement — HVAC-R and service water heating system controls
JOHN SEMIOLI
03/26/2026
Special inspection requirement — Interior lighting power
JOHN SEMIOLI
10/10/2024
Signed off — Alteration
B00014274-I1
05/15/2024
Signed off — Alteration
B00441869-I1
04/17/2024
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
02/21/2024
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
01/09/2024
Signed off — Alteration
B00072926-I1
12/13/2023
Violation issued (ECB, closed)
Construction
12/13/2023
Violation issued (ECB, closed)
Construction
12/13/2023
Violation issued (ECB, closed)
Unknown
12/07/2023
Objection resolved — Addressed
11/14/2023
Objection raised — Other
10/24/2023
Objection resolved — Addressed
10/19/2023
Objection raised — Fire_Protection
10/06/2023
Violation issued (ECB, closed)
Site Safety
09/28/2023
Filed — No Work
B00897314-I1
06/28/2023
Special inspection requirement — Public Assembly Emergency Lighting
RICHARD GREENWALD
11/15/2022
Permit issued — Sidewalk Shed
B00072926-I1-SH
11/03/2022
Violation issued (ECB, closed)
Construction
11/03/2022
Violation issued (ECB, closed)
Construction
09/21/2022
Violation issued (ECB, closed)
Construction
04/13/2022
Signed off — Alteration
B00290912-I1
12/15/2021
Permit issued — Supported Scaffold
B00441869-I1-SF
11/16/2021
Permit issued — Sidewalk Shed
B00072926-I1-SH
03/01/2021
Violation issued (ECB, closed)
Cranes and Derricks
01/07/2021
Permit issued — Supported Scaffold
B00290912-I1-SF
12/23/2020
Violation issued (ECB, closed)
Construction
12/21/2020
Permit issued — Supported Scaffold
B00441869-I1-SF
12/17/2020
Filed — Alteration
B00441869-I1
11/09/2020
Permit issued — Sidewalk Shed
B00072926-I1-SH
04/22/2020
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
04/22/2020
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
01/07/2020
Filed — Alteration
B00290912-I1
01/07/2020
Permit issued — Supported Scaffold
B00290912-I1-SF
12/09/2019
Violation issued (ECB, closed)
Construction
Latest 60 of 101 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSprinklersPermit IssuedMagic Mechanical09/03/2026
DOB NOWPlumbingPermit IssuedMagic Mechanical08/28/2026
DOB NOWGeneral ConstructionPermit IssuedFazio Construction Group04/27/2026
DOB NOWMechanical SystemsPermit IssuedFazio Construction Group04/27/2026
DOB NOWSidewalk ShedSigned-offCore Scaffold Systems11/15/2022
DOB NOWSupported ScaffoldSigned-offCore Scaffold Systems12/15/2021
DOB NOWSidewalk ShedSigned-offCore Scaffold Systems11/16/2021
DOB NOWSupported ScaffoldSigned-offCore Scaffold Systems01/07/2021
DOB NOWSupported ScaffoldSigned-offCore Scaffold Systems12/21/2020
DOB NOWSidewalk ShedSigned-offCore Scaffold Systems11/09/2020
DOB NOWSupported ScaffoldSigned-offCore Scaffold Systems01/07/2020
DOB NOWSidewalk ShedSigned-offCore Scaffold Systems11/08/2019
DOB NOWConstruction FenceSigned-offJ.A. Jennings06/05/2019
DOB NOWConstruction FenceSigned-offJ.A. Jennings01/03/2019
DOB NOWSidewalk ShedSigned-offCore Scaffold Systems11/07/2018
DOB NOWSidewalk ShedSigned-offCore Scaffold Systems08/24/2018
DOB NOWConstruction FenceSigned-offJ.A. Jennings02/07/2018
BIS—ISSUEDFazio Construction Group12/06/2024
BISPLISSUEDUniversal Plumbing07/22/2024
BIS—ISSUEDFazio Construction Group11/29/2023
BISEQISSUEDFazio Construction Group06/29/2023
BISSDISSUEDShamrock Mechanical05/09/2023
BISPLISSUEDUniversal Plumbing05/09/2023
BISPLISSUEDUniversal Plumbing05/09/2023
BISMHISSUEDSav-Mor Mechanical03/02/2023
BIS—ISSUEDFazio Construction Group11/25/2022
BISMHISSUEDSav-Mor Mechanical07/07/2022
BISFSISSUEDNew York Heating07/05/2022
BISEQISSUEDFazio Construction Group07/01/2022
BISPLISSUEDUniversal Plumbing03/02/2022
BISPLISSUEDUniversal Plumbing03/02/2022
BISSPISSUEDShamrock Mechanical03/01/2022
BIS—ISSUEDFazio Construction Group12/02/2021
BIS—ISSUEDFazio Construction Group12/02/2021
BIS—ISSUEDFazio Construction Group07/09/2021
BIS—ISSUEDFazio Construction Group07/09/2021
BISEQISSUEDFazio Construction Group07/09/2021
BIS—ISSUEDFazio Construction Group07/09/2021
BISPLISSUEDPlumbing NYC02/12/2021
BISPLISSUEDPlumbing NYC02/12/2021
+ 20 more permits on file
1 project · most recent 03/27/2026
Heating and Air Conditioning Systems
FiledStatusContractorScopeMake / Model / Capacity
03/27/2026Permit IssuedFazio Construction GroupHeating and Air Conditioning Systems
Heat / Cool
Indeeco OCAPU1502 160 CFM · Electric Heater ×12
Anemostat ESTE 3309 1,000 CFM ×4
ESTE 3308 700 CFM ×2
1 project · most recent 03/27/2026
FiledStatusContractorScope
03/27/2026Permit IssuedMagic Mechanical493 heads
1 project · most recent 03/27/2026
Water/Sanitary
FiledStatusContractorScope
03/27/2026Permit IssuedMagic MechanicalWater/Sanitary
12 projects · most recent 12/19/2024
General Wiring
FiledStatusContractorScope
12/19/2024CompleteCKC Contracting Corp Dba—
10/10/2024CompleteCKC Contracting Corp DbaGeneral Wiring
04/15/2022CancelledStasi/Dallas Electrical ContGeneral Wiring
04/15/2022CompleteStasi/Dallas Electrical Cont—
04/15/2022CancelledStasi/Dallas Electrical ContGeneral Wiring
04/15/2022CancelledStasi/Dallas Electrical Cont—
12/13/2021CompleteM F Electrical Service CoGeneral Wiring
11/25/2019CompleteStar Electrical Contractors—
11/19/2019CancelledA.S.K. ElectricalGeneral Wiring
08/08/2019CancelledA.S.K. ElectricalGeneral Wiring
07/22/2019CancelledA.S.K. Electrical—
08/23/2018CompleteV. Vass Electric—
▾Special Inspection Requirements (DOB NOW) — 20
DateRequirementInspectorRole
03/26/2026Maintenance informationJOHN SEMIOLIenergy_progress
03/26/2026Energy Code Compliance InspectionsJOHN SEMIOLIprogress
03/26/2026Fire-Resistance Rated ConstructionJOHN SEMIOLIprogress
03/26/2026FinalJOHN SEMIOLIprogress
03/26/2026Sprinkler Systems—special
03/26/2026Fire-Resistant Penetrations and Joints—special
03/26/2026Fire-Resistant Penetrations and JointsJOHN SEMIOLIspecial
03/26/2026Mechanical SystemsJOHN SEMIOLIspecial
03/26/2026Fire-Resistant Penetrations and JointsJOHN SEMIOLIspecial
03/26/2026Post-installed AnchorsJOHN SEMIOLIspecial
03/26/2026FinalJOHN SEMIOLIprogress
03/26/2026Energy Code Compliance InspectionsJOHN SEMIOLIprogress
03/26/2026MeteringJOHN SEMIOLIenergy_progress
03/26/2026HVAC-R and service water heating equipmentJOHN SEMIOLIenergy_progress
03/26/2026Shutoff dampersJOHN SEMIOLIenergy_progress
03/26/2026HVAC-R and service water piping design and insulationJOHN SEMIOLIenergy_progress
03/26/2026Lighting controlsJOHN SEMIOLIenergy_progress
03/26/2026HVAC-R and service water heating system controlsJOHN SEMIOLIenergy_progress
03/26/2026Interior lighting powerJOHN SEMIOLIenergy_progress
06/28/2023Public Assembly Emergency LightingRICHARD GREENWALDprogress
▾Tenants in the building
TenantSpaceFloorsRenovation projects
Diocese of BrooklynReligious—
Project B01378819 Alteration · Permit Entire · 03/26/2026
Desales Media GroupArts / Culture / Entertainment—
Project B00014274 Alteration · LOC Issued · 01/30/2018
Names are taken automatically from the text of each project’s filed documents (title blocks and cover sheets) and screened to exclude owners, landlords and designers. They may be incomplete or wrong; check the filing.
▾Documents — 371 on file (BIS + DOB NOW)
▸Plans & Drawings9
▸DOB NOWPlans/Sketch6
09/03/2026B00014274-I1Request digital key ↗
09/03/2026B00072926-I1Request digital key ↗
08/17/2026B01378819-I1Request digital key ↗
Showing 3 of 6 on file for this type
▸DOB NOWPlans/Sketch - Supported Scaffold2
09/02/2026B00290912-I1Request digital key ↗
09/02/2026B00441869-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Place of Assembly1
08/14/2026B00897314-I1Request digital key ↗
▸Applications & Permits91
▸BISPLAN / WORK APPROVAL APPLICATION45
07/15/2025321192598Open ↗
07/02/2025321192598Open ↗
04/23/2025321192598Open ↗
Showing 3 of 45 on file for this type
▸BISWORK PERMIT APPLICATION42
12/10/2024321192598Open ↗
12/04/2023321192598Open ↗
11/25/2022321192598Open ↗
Showing 3 of 42 on file for this type
▸BISBPP-5 - Authorization to the Department of Transportation3
08/31/2023340442453Open ↗
Showing 1 of 3 on file for this type
▸BISPLAN - WORK & PERMITS - SUPPPORTING DOCUMENTATION1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Zoning, Tax Lot & Property Records8
▸BISZONING DIAGRAM3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸BISTAX LOT: FINAL LOT NUMBER ISSUED1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISZONING EXHIBIT III:DESC. & OWNRSHP.STMNT1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISVERIFY TAX LOT1
08/29/2024321192598Open ↗
▸BISCO OBJ: VERIFY ADDRESS-TOPO STAMP1
06/27/2024321192598Open ↗
▸BISZONING EXHIBIT I: CERTIFICATION1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Seals & Professional Certifications35
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION10
12/13/2019321817548Open ↗
12/13/2019321817548Open ↗
11/18/2019340424053Open ↗
Showing 3 of 10 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature9
09/03/2026B00014274-I1Open ↗
09/03/2026B00072926-I1Open ↗
09/02/2026B00441869-I1Open ↗
Showing 3 of 9 on file for this type
▸DOB NOWProgress Inspector Seal & Signature7
09/01/2026B01378819-S1Open ↗
09/01/2026B01378819-S1Open ↗
09/01/2026B01378819-S1Open ↗
Showing 3 of 7 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature4
09/01/2026B01378819-S1Open ↗
09/01/2026B01378819-S1Open ↗
09/01/2026B01378819-S1Open ↗
Showing 3 of 4 on file for this type
▸BISAPPLICANT OWNER SIGNATURE3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Trade Schedules & Equipment24
▸BISSCHEDULE B - PLUMBING9
07/02/2025321192598Open ↗
03/01/2024340424053Open ↗
02/09/2024321192598Open ↗
Showing 3 of 9 on file for this type
▸BISEQUIPMENT USE PERMITS7
08/19/2024321192598Open ↗
08/07/2024321192598Open ↗
08/07/2024321192598Open ↗
Showing 3 of 7 on file for this type
▸BISEQUIPMENT USE APPLICATION/PERMIT3
08/07/2024321192598Open ↗
08/07/2024321192598Open ↗
08/07/2024321192598Open ↗
▸BISSCHEDULE C - HEATING & COMBUSTION EQUIPMENT2
08/30/2024340675371Open ↗
Showing 1 of 2 on file for this type
▸BISHVAC & SERVICE WATER HEATING SYSTEM CONTROLS1
03/29/2024321192598Open ↗
▸BISSPRINKLER SYSTEMS1
03/29/2024340424053Open ↗
▸BISSTANDPIPE SYSTEMS1
03/29/2024340424053Open ↗
▸Safety & Tenant Protection5
▸BISSTREET TREE CHECKLIST3
08/21/2023321192598Open ↗
Showing 1 of 3 on file for this type
▸BISSTREET TREES: RECEIPT OF STREET TREES SITE PLAN1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISSTREET TREE SIGNOFF1
04/29/2024321192598Open ↗
▸Energy Compliance12
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS (EN2)2
08/15/2024340675371Open ↗
05/06/2024321192598Open ↗
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISINSULATION PLACEMENT & R VALUES1
08/26/2024321192598Open ↗
▸BISENERGY CODE COMPLIANCE INSPECTIONS1
03/29/2024321192598Open ↗
▸BISELECTRIC MOTORS1
05/06/2024321192598Open ↗
▸BISLIGHTING CONTROLS1
05/06/2024321192598Open ↗
▸BIS* HVAC INSULATION AND SEALING1
08/26/2024321192598Open ↗
▸Inspections & Test Reports43
▸BISTECHNICAL REPORT: RESPONSIBILITY27
08/29/2024340675371Open ↗
08/26/2024321192598Open ↗
02/28/2024340424053Open ↗
Showing 3 of 27 on file for this type
▸BISTECHNICAL REPORT: CONCRETE/TEST CYLINDER7
04/06/2023321192598Open ↗
04/06/2023321192598Open ↗
04/06/2023321192598Open ↗
Showing 3 of 7 on file for this type
▸BISFIRE-RESISTANT PENETRATIONS AND JOINTS (FIRESTOP)2
03/29/2024340424053Open ↗
03/29/2024321192598Open ↗
▸BISMECHANICAL SYSTEMS2
06/27/2024340675371Open ↗
06/27/2024321192598Open ↗
▸BISSTRUCTURAL STEEL - HIGH STRENGTH BOLTING1
01/18/2024321192598Open ↗
▸BISSTRUCTURAL STEEL - WELDING1
01/18/2024321192598Open ↗
▸BISSUBGRADE INSP / SOILS-SITE PREP1
03/23/2023321192598Open ↗
▸BISHYDRO FLOW TEST LETTER1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISSOIL REPORT1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Approvals, Objections & Sign-offs26
▸BISSCHEDULE A - OCCUPANCY / USE9
07/15/2025321192598Open ↗
04/23/2025321192598Open ↗
12/21/2023321192598Open ↗
Showing 3 of 9 on file for this type
▸DOB NOWFee Exempt Supporting Document - DOF ACRIS report or BIB letter7
09/03/2026B00014274-I1Open ↗
08/17/2026B01378819-S3Open ↗
08/17/2026B01378819-S2Open ↗
Showing 3 of 7 on file for this type
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST5
09/12/2024321817548Open ↗
08/30/2024340675371Open ↗
08/16/2024321448698Open ↗
Showing 3 of 5 on file for this type
▸BISLETTERS - SUPPORTING DOCUMENTATION3
09/26/2019340675371Open ↗
Showing 1 of 3 on file for this type
▸BISFINAL2
08/15/2024340675371Open ↗
03/29/2024340424053Open ↗
▸Cost, Insurance & Ownership17
▸BISPROJECT-SPECIFIC GL INSURANCE7
12/04/2023321192598Open ↗
11/25/2022321192598Open ↗
12/03/2021321192598Open ↗
Showing 3 of 7 on file for this type
▸BISCOST AFFIDAVIT5
12/13/2019321817548Open ↗
Showing 1 of 5 on file for this type
▸BISCOST AFFIDAVIT (FINAL): PW33
08/15/2024321448698Open ↗
05/20/2024340424053Open ↗
03/14/2024340675371Open ↗
▸BISAcord 25 (Acord Certificate of Liability Insurance)2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸Filing & Intake Forms52
▸BISADDITIONAL INFORMATION37
10/25/2024321192598Open ↗
08/29/2024321192598Open ↗
08/29/2024321192598Open ↗
Showing 3 of 37 on file for this type
▸BISEFILING COVER SHEET7
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 7 on file for this type
▸BISBOROUGH INTAKE FORM5
12/10/2024321192598Open ↗
03/10/2022321192598Open ↗
03/10/2022321192598Open ↗
Showing 3 of 5 on file for this type
▸BISEFILING JOB APPLICATION COVER SHEET3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸Other Documents16
▸BISCONSTRUCTION - SUPPORTING DOCUMENTATION5
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 5 on file for this type
▸BISBPP - SUPPORTING DOCUMENTATION4
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 4 on file for this type
▸BISFUEL-OIL STORAGE AND FUEL-OIL PIPING SYSTEMS2
06/27/2024340675371Open ↗
03/29/2024321192598Open ↗
▸BISEMERGENCY & STANDBY POWER SYSTEMS (GENERATORS)2
06/27/2024340675371Open ↗
02/12/2024321192598Open ↗
▸BISPRIOR TO FCO AMEND SCH A AND PW1 SECTION 12 TO INDICATE NUMBER OF ENCLOSED PARKING SPACES.1
08/25/2025321192598Open ↗
▸BISMAINTENANCE INFORMATION1
05/06/2024321192598Open ↗
▸BISPROTECTION OF EXPOSED FOUNDATION INSULATION1
08/26/2024321192598Open ↗