1958Year Built
17Stories
D3Building Class
R7-2Zoning
700,175 sfGross Floor Area
1,162Units
LL97 Covered11 Open Violations 10 unresolved · 1 paperwork only ▸FISP: SAFE
Elevator apt, fireproof without stores · Owner of record: NYC HOUSING AUTHORITY · 628,400 sf lot · 1.11 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralMechanicalPlumbing
Permit Issued — active, not yet Signed-off
RoofUnder Construction31p · 3 filings · 20 docs
Bulkhead1p · 1 filing · 16 docs
Cellar3p · 2 filings · 14 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
NYCHA5109/18/2026
NYC HOUSING AUTHORITY703/22/2026
J N CONSTRUCTION GROUP203/22/2026
NYC HOUSING AUTH103/22/2026
NEW YOUR CITY HOUSING AUT103/22/2026
NYCHA 99103/22/2026
▾Design Consultants (Architect / Engineer of Record)
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
AK CONSULTING SERVICES803/21/2026
JOEL PHAGOO P.E. PLLC103/21/2026
MK ARCHITECTURE PC203/21/2026
SHENOY ENGINEERING, P.C.203/21/2026
JM ZONING, LLC.403/21/2026
JOEL PHAGOO P E103/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
ROMA SCAFFOLDING INCGeneral Contractor1707/08/2026
J & N CONSTRUCTION GROUPGeneral Contractor1409/18/2026
ZORIA HOUSING, LLCGeneral Contractor603/21/2026
MNK ENTERPRISES LLCGeneral Contractor603/21/2026
STEPHENS, KENNETHElectrical103/21/2026
THOMPSON, NElectrical103/21/2026
WHEELER, RElectrical103/21/2026
D.D.S. MECH PBG&HTG CORPPlumbing107/08/2026
CHARNJIT SINGHElectrical103/21/2026
SKYLINE P & H INCPlumbing103/22/2026
FORD, GUYElectrical103/21/2026
GUY FORDElectrical103/21/2026
OMAR MAHMOUDElectrical103/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
SOCOTEC ENGINEERING4983211/01/2024
JOEL PHAGOO ,PE, PLLC2416102/20/2024
MT GROUP798202/16/2024
MP ENGINEERS & ARCHITECTS1438212/20/2022
Building Lifecycle
All (135)Filed (23)Permit Issued (25)Signed Off (10)Facade (FISP) (15)Violation (28)Inspection (1)Objection (3)Special Inspection (30)
09/17/2026
Permit issued — Structural
M08014787-I1-ST
03/02/2026
Permit issued — General Construction
M08014780-I1-GC
02/27/2026
Permit issued — Structural
M08014787-I1-ST
08/05/2025
Signed off — Alteration
REMOVE AND REPLACE ALL GAS PIPING THROUGHOUT BUILDING INCLUDING RISER AND METERS. EXISTING GAS SERVICE TO REMAIN.
M00623922-I1
07/31/2025
Signed off — Alteration
INSTALLATION OF SUPPORTED PIPE SCAFFOLD AT 852 COLUMBUS AVENUE, MANHATTAN AS INDICATED ON PLANS. THERE WILL BE NO CHANGE IN THE USE, EGRESS, OR OCCUPANCY UNDER THIS APPLICATION.
M01055837-I1
07/29/2025
Signed off — Alteration
INSTALLATION OF TEMPORARY CONSTRUCTION FENCE AT 852 COLUMBUS AVENUE MANHATTAN AS INDICATED ON PLANS. THERE WILL BE NO CHANGE IN THE USE, EGRESS, OR OCCUPANCY UNDER THIS APPLICATION.
M01051457-I1
05/06/2025
Signed off — Alteration
INSTALLATION OF NEW SIDEWALK SHED AT 852 COLUMBUS AVENUE, MANHATTAN AS INDICATED ON PLANS. THERE WILL BE NO CHANGE IN THE USE, EGRESS, OR OCCUPANCY UNDER THIS APPLICATION.
M01056245-I1
02/28/2025
Signed off — Alteration
Exterior wall and roof bulkhead repairs. no change to use, occupancy or egress.
M00995793-I1
02/24/2025
Inspection — Pass-Final PL - More than 10 Requested Floors
Pass
View inspection ↗
01/03/2025
Permit issued — Structural
M08014787-I1-ST
12/31/2024
Violation issued (ECB, closed)
Construction
12/31/2024
Violation issued (ECB, closed)
Construction
12/06/2024
Signed off — Alteration
M01006427-I1
12/06/2024
Signed off — Alteration
INSTALLATION OF TEMPORARY CHAIN LINK FENCE AS PER PLANS. CHAIN LINK FENCE SHALL COMPLY WITH CHAPTER 33 OF THE 2022 NYC BUILDING CODE. NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
M00885419-I1
12/06/2024
Signed off — Alteration
INSTALLATION OF TEMPORARY SIDEWALK SHED AS PER PLANS. SIDEWALK SHED SHALL COMPLY WITH CHAPTER 33 OF THE 2022 NYC BUILDING CODE. NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
M00885416-I1
11/29/2024
Permit issued — General Construction
M08014780-I1-GC
11/21/2024
Filed — Alteration
INSTALLATION OF NEW SIDEWALK SHED AT 852 COLUMBUS AVENUE, MANHATTAN AS INDICATED ON PLANS. THERE WILL BE NO CHANGE IN THE USE, EGRESS, OR OCCUPANCY UNDER THIS APPLICATION.
M01056245-P1
11/04/2024
Special inspection requirement — Structural Stability – Alterations of existing buildings
ALEXIS SCHLESSINGERMAN
11/04/2024
Special inspection requirement — Masonry
ALEXIS SCHLESSINGERMAN
11/04/2024
Special inspection requirement — Final
TIMOTHY WEBB
11/04/2024
Special inspection requirement — Tenant Protection Plan Compliance
ALEXIS SCHLESSINGERMAN
11/01/2024
Filed — Alteration
Exterior wall and roof bulkhead repairs. no change to use, occupancy or egress.
M00995793-P1
10/29/2024
Special inspection requirement — Masonry
ALEXIS SCHLESSINGERMAN
10/29/2024
Special inspection requirement — Tenant Protection Plan Compliance
10/29/2024
Special inspection requirement — Final
TIMOTHY WEBB
10/29/2024
Special inspection requirement — Structural Stability – Alterations of existing buildings
ALEXIS SCHLESSINGERMAN
10/25/2024
Cycle 9 facade report signed — SAFE
10/03/2024
Cycle 9 facade report submitted
09/27/2024
Cycle 9 facade inspection completed
09/11/2024
Permit issued — Suspended Scaffold
M01083593-I1-SC
09/11/2024
Permit issued — Plumbing
M00623922-I1-PL
09/02/2024
Filed — Alteration
M01083593-I1
08/12/2024
Permit issued — General Construction
M00995793-I1-GC
07/17/2024
Filed — Alteration
INSTALLATION OF TEMPORARY SIDEWALK SHED AS PER PLANS. SIDEWALK SHED SHALL COMPLY WITH CHAPTER 33 OF THE 2022 NYC BUILDING CODE. NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
M00885416-P1
07/17/2024
Filed — Alteration
INSTALLATION OF TEMPORARY CHAIN LINK FENCE AS PER PLANS. CHAIN LINK FENCE SHALL COMPLY WITH CHAPTER 33 OF THE 2022 NYC BUILDING CODE. NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
M00885419-P1
06/17/2024
Permit issued — Sidewalk Shed
M00885416-I1-SH
06/14/2024
Permit issued — Construction Fence
M00885419-I1-FN
05/28/2024
Permit issued — Sidewalk Shed
M01056245-I1-SH
05/28/2024
Permit issued — Supported Scaffold
M01055837-I1-SF
05/27/2024
Filed — Alteration
INSTALLATION OF SUPPORTED PIPE SCAFFOLD AT 852 COLUMBUS AVENUE, MANHATTAN AS INDICATED ON PLANS. THERE WILL BE NO CHANGE IN THE USE, EGRESS, OR OCCUPANCY UNDER THIS APPLICATION.
M01055837-I1
05/27/2024
Filed — Alteration
INSTALLATION OF NEW SIDEWALK SHED AT 852 COLUMBUS AVENUE, MANHATTAN AS INDICATED ON PLANS. THERE WILL BE NO CHANGE IN THE USE, EGRESS, OR OCCUPANCY UNDER THIS APPLICATION.
M01056245-I1
05/22/2024
Permit issued — Construction Fence
M01051457-I1-FN
05/21/2024
Filed — Alteration
INSTALLATION OF TEMPORARY CONSTRUCTION FENCE AT 852 COLUMBUS AVENUE MANHATTAN AS INDICATED ON PLANS. THERE WILL BE NO CHANGE IN THE USE, EGRESS, OR OCCUPANCY UNDER THIS APPLICATION.
M01051457-I1
05/01/2024
Special inspection requirement — Fenestration and door U-factor and product ratings
JAMES WILSON
05/01/2024
Special inspection requirement — Fenestration air leakage
JAMES WILSON
05/01/2024
Special inspection requirement — Insulation placement and R values
JAMES WILSON
05/01/2024
Special inspection requirement — Structural Stability – Alterations of existing buildings
JAMES WILSON
05/01/2024
Special inspection requirement — Tenant Protection Plan Compliance
JAMES WILSON
05/01/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
JAMES WILSON
05/01/2024
Special inspection requirement — Final
JAMES WILSON
05/01/2024
Special inspection requirement — Masonry
JAMES WILSON
05/01/2024
Special inspection requirement — Preliminary
JAMES WILSON
05/01/2024
Special inspection requirement — Post-installed Anchors
JAMES WILSON
05/01/2024
Special inspection requirement — Structural Stability – Alterations of existing buildings
JAMES WILSON
05/01/2024
Special inspection requirement — Masonry
JAMES WILSON
05/01/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
JAMES WILSON
05/01/2024
Special inspection requirement — Energy Code Compliance Inspections
JAMES WILSON
05/01/2024
Special inspection requirement — Final
JAMES WILSON
04/30/2024
Filed — Alteration
HEREWITH FILING STRUCTURAL WORK AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
M08014787-P1
04/23/2024
Filed — Alteration
HEREWITH FILING ROOFING REPLACEMENT LIMITED FACADE WORK AT BULKHEADS AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
M08014780-P1
Latest 60 of 135 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWStructuralPermit IssuedJ & N CONSTRUCTION GROUP09/17/2026
DOB NOWGeneral ConstructionPermit IssuedJ & N CONSTRUCTION GROUP03/02/2026
DOB NOWStructuralPermit IssuedJ & N CONSTRUCTION GROUP02/27/2026
DOB NOWStructuralPermit IssuedJ & N CONSTRUCTION GROUP01/03/2025
DOB NOWGeneral ConstructionPermit IssuedJ & N CONSTRUCTION GROUP11/29/2024
DOB NOWSuspended ScaffoldPermit IssuedJ&N CONSTRUCTION GRP CORP09/11/2024
DOB NOWPlumbingSigned-offD.D.S. MECH PBG&HTG CORP09/11/2024
DOB NOWGeneral ConstructionSigned-offZORIA HOUSING, LLC08/12/2024
DOB NOWSidewalk ShedSigned-offMNK ENTERPRISES LLC06/17/2024
DOB NOWConstruction FenceSigned-offZORIA HOUSING, LLC06/14/2024
DOB NOWSidewalk ShedSigned-offJ & N CONSTRUCTION GROUP05/28/2024
DOB NOWSupported ScaffoldSigned-offJ & N CONSTRUCTION GROUP05/28/2024
DOB NOWConstruction FenceSigned-offJ & N CONSTRUCTION GROUP05/22/2024
DOB NOWSuspended ScaffoldSigned-offZORIA HOUSING LLC02/27/2024
DOB NOWConstruction FenceSigned-offZORIA HOUSING, LLC06/09/2023
DOB NOWSidewalk ShedSigned-offMNK ENTERPRISES LLC06/09/2023
DOB NOWConstruction FenceSigned-offROMA SCAFFOLDING INC02/08/2023
DOB NOWSidewalk ShedSigned-offROMA SCAFFOLDING INC09/27/2022
DOB NOWConstruction FenceSigned-offROMA SCAFFOLDING INC02/03/2022
DOB NOWSidewalk ShedSigned-offROMA SCAFFOLDING INC09/29/2021
DOB NOWConstruction FenceSigned-offROMA SCAFFOLDING INC02/04/2021
DOB NOWConstruction FenceSigned-offROMA SCAFFOLDING INC10/28/2020
DOB NOWSidewalk ShedSigned-offROMA SCAFFOLDING INC09/30/2020
DOB NOWConstruction FenceSigned-offROMA SCAFFOLDING INC11/14/2019
DOB NOWSidewalk ShedSigned-offROMA SCAFFOLDING INC10/07/2019
BISPLISSUEDREYVIN PLBG & HTG CORP06/08/2004
BISOTISSUEDNAP CONSTRUCTION CO INC04/30/2002
BISOTISSUEDPHOENIX CONSTRUCION CORP05/14/1999
BISOTISSUEDPHOENIX CONST. CORP09/23/1998
BISPLISSUEDREYVIN PLBG & HTG CORP09/23/1998
BISOTISSUEDTRATAORS PLUMBING & HTG04/07/1997
BISPLISSUEDTRATAROS PBG/ACE CONSTRUCTION04/07/1997
BISPLISSUEDV. C. VITANZA SONS INC11/05/1993
1 project · most recent 02/16/2021
Gas
FiledStatusContractorScope
02/16/2021——Gas
6 projects · most recent 07/11/2025
General Wiring
FiledStatusContractorScope
07/11/2025CompleteTRI-STATE ELECL & MECHL IGeneral Wiring
11/12/2024CompleteLIT MODE ELECL CONTG INC—
11/12/2024CompleteLIT MODE ELECL CONTG INC—
03/21/2024CompleteQ.Y. ELECTRIC, INC—
03/15/2023CompleteQ.Y. ELECTRIC, INC—
09/06/2019Permit IssuedRAIDEN ELECTRIC LLC—
1 project · most recent 04/30/2024
Concrete
FiledStatusContractorScope
04/30/2024Permit IssuedJ & N CONSTRUCTION GROUPConcrete
▾Field Inspections (DOB CAP) — 1
DateTypeResultReport
02/24/2025Pass-Final PL - More than 10 Requested FloorsPassView ↗
▾Special Inspection Requirements (DOB NOW) — 43
DateRequirementInspectorRole
11/04/2024Structural Stability – Alterations of existing buildingsALEXIS SCHLESSINGERMANspecial
11/04/2024MasonryALEXIS SCHLESSINGERMANspecial
11/04/2024FinalTIMOTHY WEBBprogress
11/04/2024Tenant Protection Plan ComplianceALEXIS SCHLESSINGERMANspecial
10/29/2024MasonryALEXIS SCHLESSINGERMANspecial
10/29/2024Tenant Protection Plan Compliance—special
10/29/2024FinalTIMOTHY WEBBprogress
10/29/2024Structural Stability – Alterations of existing buildingsALEXIS SCHLESSINGERMANspecial
05/01/2024Fenestration and door U-factor and product ratingsJAMES WILSONenergy_progress
05/01/2024Fenestration air leakageJAMES WILSONenergy_progress
05/01/2024Insulation placement and R valuesJAMES WILSONenergy_progress
05/01/2024Structural Stability – Alterations of existing buildingsJAMES WILSONspecial
05/01/2024Tenant Protection Plan ComplianceJAMES WILSONspecial
05/01/2024Fire-Resistant Penetrations and JointsJAMES WILSONspecial
05/01/2024FinalJAMES WILSONprogress
05/01/2024MasonryJAMES WILSONspecial
05/01/2024PreliminaryJAMES WILSONprogress
05/01/2024Post-installed AnchorsJAMES WILSONspecial
05/01/2024Structural Stability – Alterations of existing buildingsJAMES WILSONspecial
05/01/2024MasonryJAMES WILSONspecial
05/01/2024Fire-Resistant Penetrations and JointsJAMES WILSONspecial
05/01/2024Energy Code Compliance InspectionsJAMES WILSONprogress
05/01/2024FinalJAMES WILSONprogress
04/12/2024Fenestration and door U-factor and product ratings—energy_progress
04/12/2024Fire-Resistant Penetrations and Joints—special
Latest 25 of 43.
▾Documents — 123 on file (BIS + DOB NOW)
▸Plans & Drawings24
▸DOB NOWPlans/Sketch19
09/03/2026M00623922-P1Request digital key ↗
09/03/2026M00623922-I1Request digital key ↗
09/01/2026M08014780-P1Request digital key ↗
Showing 3 of 19 on file for this type
▸DOB NOWPlans/Sketch - Construction Fence2
09/05/2026M00263830-I1Request digital key ↗
08/15/2026M00263830-P1Request digital key ↗
▸DOB NOWPlans/Sketch - Sidewalk Shed2
09/05/2026M00232518-I1Request digital key ↗
08/15/2026M00232518-P1Request digital key ↗
▸DOB NOWPlans/Sketch - Plumbing1
08/15/2026M00346302-I1Request digital key ↗
▸Seals & Professional Certifications45
▸DOB NOWDPL-1: Design Professional Seal & Signature22
09/04/2026M00346302-I1Open ↗
09/03/2026M00623922-P1Open ↗
09/03/2026M00623922-I1Open ↗
Showing 3 of 22 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature14
09/29/2026M01006427-I1Open ↗
09/18/2026M00995793-P1Open ↗
09/01/2026M08014787-I1Open ↗
Showing 3 of 14 on file for this type
▸DOB NOWProgress Inspector Seal & Signature9
09/18/2026M00995793-P1Open ↗
09/01/2026M08014787-I1Open ↗
09/01/2026M08014787-I1Open ↗
Showing 3 of 9 on file for this type
▸Safety & Tenant Protection4
▸DOB NOWTenant Protection Plan4
08/13/2026M00263830-I1Open ↗
08/13/2026M00263830-P1Open ↗
08/13/2026M00232518-I1Open ↗
Showing 3 of 4 on file for this type
▸Environmental & Asbestos2
▸DOB NOWDEP ACP-20/ACP-21: Asbestos Project Conditional Completion Form/Asbestos Project Completion Form2
09/03/2026M00623922-I1Open ↗
08/27/2026M00995793-I1Open ↗
▸Approvals, Objections & Sign-offs42
▸DOB NOWFee Exempt Supporting Document - DOF ACRIS report or BIB letter24
09/03/2026M00623922-P1Open ↗
09/03/2026M00623922-I1Open ↗
09/01/2026M08014780-I1Open ↗
Showing 3 of 24 on file for this type
▸DOB NOWDesign Commission Approval City Owned (Exterior Work)11
09/01/2026M08014780-I1Open ↗
09/01/2026M08014787-P2Open ↗
08/13/2026M00232518-I1Open ↗
Showing 3 of 11 on file for this type
▸DOB NOWDesign Commission Sign Off City Owned (Exterior Work)4
08/13/2026M00263830-I1Open ↗
08/13/2026M00995793-I1Open ↗
08/13/2026M00623922-I1Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWDEP Variance (V5) letter3
08/27/2026M00995793-I1Open ↗
08/13/2026M08014787-I1Open ↗
08/13/2026M08014780-I1Open ↗
▸Other Documents6
▸DOB NOWCalculations2
08/13/2026M01006427-I1Open ↗
08/13/2026M01083593-I1Open ↗
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone2
09/01/2026M08014780-I1Open ↗
08/13/2026M08014780-P1Open ↗
▸DOB NOWManufacturer's Specifications2
08/13/2026M01083593-I1Open ↗
08/13/2026M01006427-I1Open ↗