Elevator cooperative
87-01 MIDLAND PARKWAY
QUEENS · BIN 4213038
💬 Discuss this project
1960Year Built
6Stories
D4Building Class
R5Zoning
34,200 sfGross Floor Area
53Units
LL97 CoveredRent Stabilized37 Open Violations ▸FISP: SAFEFDNY Report ↗
Elevator cooperative · Owner of record: 87-01 MIDLAND PARKWAY REALTY CORP · 20,728 sf lot · 1.65 FAR built · Flood zone X
Locations of Work
No floor-level scope or drawing coverage on file for this building.
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
METRO CONTRACTING NY407/08/2026
TRIERA CONTRACTING407/08/2026
925 UNION STREET TENANTS CORP.903/22/2026
87-01 MIDLAND PARKWAY1803/22/2026
B L MANAGEMENT103/22/2026
87-01 MIDLAND OWNERS CORP103/22/2026
87-01 MIDLAND PKY REAL ES103/22/2026
87-01 MIDLAND REALTY CO103/22/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
JANHA BUILDING IDEAS305/30/2024
ENTHINK ENGINEERS LLC108/18/2023
ROYAL ENGINEERING, P.C105/04/2019
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
JANHA BUILDING IDEAS INC303/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
BEST NY CONTRACTING INCGeneral Contractor303/21/2026
METRO CONTRACTING NY, INC.General Contractor107/08/2026
TRIERA CONTRACTING INCGeneral Contractor107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
JANHA BUILDING IDEAS INC6129205/30/2024
Building Lifecycle
All (87)Filed (5)Permit Issued (3)Signed Off (2)Facade (FISP) (8)Violation (60)Inspection (2)Special Inspection (7)
06/12/2025
Violation issued (HPD, closed)
A
02/04/2025
Violation issued (HPD, open)
B
02/04/2025
Violation issued (HPD, open)
B
02/04/2025
Violation issued (HPD, open)
C
02/04/2025
Violation issued (HPD, open)
B
02/04/2025
Violation issued (HPD, open)
C
02/04/2025
Violation issued (HPD, open)
B
02/04/2025
Violation issued (HPD, open)
A
02/04/2025
Violation issued (HPD, open)
B
02/04/2025
Violation issued (HPD, open)
B
12/03/2024
Violation issued (HPD, closed)
I
07/11/2024
Violation issued (HPD, open)
B
07/11/2024
Violation issued (HPD, open)
C
06/29/2024
Signed off — Alteration
INSTALLATION OF TEMPORARY HEAVY DUTY SIDEWALK SHED AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY. SIDEWALK SHED SHALL COMPLY WITH CHAPTER #33 OF 2022 THE NYC BUILDING CODE. LIVE LOAD 300PSF.
Q00921465-I1
06/27/2024
Cycle 9 facade report signed — SAFE
06/25/2024
Signed off — Alteration
Facade repair work at front elevations as shown in plan as per FISP cycle 8A report.
Q00933227-I1
06/25/2024
Cycle 9 facade inspection completed
06/24/2024
Inspection — Pass-Final General Construction Non-Directive 14
Pass
View inspection ↗
06/17/2024
Inspection — Pass-Final General Construction Non-Directive 14
Pass
View inspection ↗
06/06/2024
Special inspection requirement — Tenant Protection Plan Compliance
KAMRUZ ZAMAN
06/06/2024
Special inspection requirement — Structural Stability – Alterations of existing buildings
KAMRUZ ZAMAN
05/30/2024
Filed — Alteration
Facade repair work at front elevations as shown in plan as per FISP cycle 8A report.
Q00933227-P2
05/30/2024
Special inspection requirement — Tenant Protection Plan Compliance
05/28/2024
Special inspection requirement — Structural Stability – Alterations of existing buildings
KAMRUZ ZAMAN
02/20/2024
Cycle 9 facade report submitted
11/16/2023
Permit issued — General Construction
Q00933227-I1-GC
11/08/2023
Filed — Alteration
Facade repair work at front elevations as shown in plan as per FISP cycle 8A report.
Q00933227-P1
11/06/2023
Special inspection requirement — Masonry
11/06/2023
Special inspection requirement — Tenant Protection Plan Compliance
11/06/2023
Special inspection requirement — Structural Stability – Alterations of existing buildings
10/07/2023
Filed — Alteration
Facade repair work at front elevations as shown in plan as per FISP cycle 8A report.
Q00933227-I1
08/18/2023
Filed — Alteration
INSTALLATION OF TEMPORARY HEAVY DUTY SIDEWALK SHED AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY. SIDEWALK SHED SHALL COMPLY WITH CHAPTER #33 OF 2022 THE NYC BUILDING CODE. LIVE LOAD 300PSF.
Q00921465-I1
08/18/2023
Permit issued — Sidewalk Shed
Q00921465-I1-SH
08/03/2023
Violation issued (HPD, open)
B
08/03/2023
Violation issued (HPD, open)
A
08/03/2023
Violation issued (HPD, open)
B
08/03/2023
Violation issued (HPD, open)
B
08/03/2023
Violation issued (HPD, open)
C
08/03/2023
Violation issued (HPD, open)
B
05/17/2023
Violation issued (HPD, open)
A
05/17/2023
Violation issued (HPD, open)
B
05/17/2023
Violation issued (HPD, closed)
A
05/17/2023
Violation issued (HPD, open)
A
03/29/2023
Violation issued (HPD, closed)
A
02/22/2023
Violation issued (HPD, open)
C
02/22/2023
Violation issued (HPD, closed)
C
02/22/2023
Violation issued (HPD, open)
C
12/02/2022
Violation issued (ECB, closed)
Local Law
03/04/2022
Violation issued (HPD, closed)
A
02/22/2022
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
07/09/2021
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
04/15/2021
Violation issued (HPD, closed)
A
04/15/2021
Violation issued (HPD, closed)
I
03/31/2021
Violation issued (HPD, closed)
C
03/31/2021
Violation issued (HPD, open)
B
07/14/2020
Violation issued (DOB, closed)
V*-DOB VIOLATION - Resolved
11/01/2019
Violation issued (HPD, closed)
I
09/06/2019
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
08/21/2019
Cycle 8 facade report submitted
08/07/2019
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
Latest 60 of 87 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWGeneral ConstructionSigned-offBEST NY CONTRACTING INC11/16/2023
DOB NOWSidewalk ShedSigned-offMETRO CONTRACTING NY, INC.08/18/2023
DOB NOWSidewalk ShedPermit IssuedTRIERA CONTRACTING INC05/06/2019
BISOTISSUEDJAHANGIL H BHUIYAN10/28/2015
BISEQISSUEDGUL & G CONSTR. CORP09/21/2015
BISPLISSUEDMISA PLUMBING, LLC10/23/2002
BISBLISSUEDCOMMERCIAL COMBUSTION SER10/07/2002
BISPLISSUEDJOSEPH FERRIGNO P&H CO12/20/2000
BISPLISSUEDCROOM PLUMBING & HEATING CORP.01/25/1993
BISSPISSUEDCROOM PLUMBING & HEATING CORP.01/25/1993
BISOTISSUEDPHOENIX COMBUSTION CORP10/27/1992
2 projects · most recent 08/18/2023
FiledStatusContractorScope
08/18/2023CompleteRICHARD NEU—
05/04/2019CompleteMEO ELECTRIC CORP—
1 project · most recent 05/04/2019
Sidewalk Shed
FiledStatusContractorScope
05/04/2019Permit IssuedTRIERA CONTRACTING INCSidewalk Shed
▾Field Inspections (DOB CAP) — 2
DateTypeResultReport
06/24/2024Pass-Final General Construction Non-Directive 14PassView ↗
06/17/2024Pass-Final General Construction Non-Directive 14PassView ↗
▾Special Inspection Requirements (DOB NOW) — 7
DateRequirementInspectorRole
06/06/2024Tenant Protection Plan ComplianceKAMRUZ ZAMANspecial
06/06/2024Structural Stability – Alterations of existing buildingsKAMRUZ ZAMANspecial
05/30/2024Tenant Protection Plan Compliance—special
05/28/2024Structural Stability – Alterations of existing buildingsKAMRUZ ZAMANspecial
11/06/2023Masonry—special
11/06/2023Tenant Protection Plan Compliance—special
11/06/2023Structural Stability – Alterations of existing buildings—special
▾Documents — 31 on file (BIS + DOB NOW)
▸Plans & Drawings5
▸DOB NOWPlans/Sketch4
08/24/2026Q00921465-I1Request digital key ↗
08/24/2026Q00933227-P1Request digital key ↗
08/24/2026Q00933227-I1Request digital key ↗
Showing 3 of 4 on file for this type
▸DOB NOWPlans/Sketch - Sidewalk Shed1
08/28/2026Q00162935-I1Request digital key ↗
▸Applications & Permits4
▸BISWORK PERMIT APPLICATION2
11/02/2015421225613Open ↗
09/14/2015440251442Open ↗
▸BISPLAN / WORK APPROVAL APPLICATION2
10/19/2015421225613Open ↗
09/14/2015440251442Open ↗
▸Seals & Professional Certifications13
▸DOB NOWDPL-1: Design Professional Seal & Signature5
08/24/2026Q00933227-P1Open ↗
08/24/2026Q00933227-I1Open ↗
08/24/2026Q00933227-P2Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature3
09/01/2026Q00933227-I1Open ↗
09/01/2026Q00933227-I1Open ↗
08/26/2026Q00933227-P2Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT2
10/19/2015421225613Open ↗
09/14/2015440251442Open ↗
▸BISPROFESSIONAL CERTIFIED CHECKLIST1
10/19/2015421225613Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY1
09/14/2015440251442Open ↗
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION1
09/14/2015440251442Open ↗
▸Environmental & Asbestos3
▸DOB NOWDEP ACP-5: Asbestos Assessment Report3
08/24/2026Q00933227-I1Open ↗
08/24/2026Q00933227-P2Open ↗
08/24/2026Q00933227-P1Open ↗
▸Approvals, Objections & Sign-offs1
▸BISADMINISTRATIVE OBJECTIONS1
10/19/2015421225613Open ↗
▸Cost, Insurance & Ownership1
▸BISCOST AFFIDAVIT1
10/19/2015421225613Open ↗
▸Filing & Intake Forms2
▸BISEFILING COVER SHEET1
10/19/2015421225613Open ↗
▸BISEFILING JOB APPLICATION COVER SHEET1
09/14/2015440251442Open ↗
▸Other Documents2
▸BISCONSTRUCTION - SUPPORTING DOCUMENTATION1
09/14/2015440251442Open ↗
▸DOB NOWBSA Meeting Minutes/BSA Resolution1
08/13/2026Q00162935-I1Open ↗