| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 12/16/2016 | $610K | — | — → — | $258/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| CHUN FENG, ARCHITECT | 4 | 08/11/2025 |
| Representative | Filings | Most Recent |
|---|---|---|
| HIGH QUALITY 338 | 8 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| EMPRISE CONSTRUCTION INC | General Contractor | 1 | 07/08/2026 |
| VMC PLUMBING & HEATING IN | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| NKM ENGINEERING PLLC | 6244 | 4 | 08/11/2025 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Signed-off | EMPRISE CONSTRUCTION INC | 06/25/2025 |
| DOB NOW | Plumbing | Signed-off | M. SPINELLI PLB & HTG INC | 06/25/2025 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/11/2025 | Signed-off | VMC PLUMBING & HEATING IN | Gas, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 03/13/2026 | Complete | I.P. ELECTRIC INC | 1 meters |
| Date | Type | Result | Report |
|---|---|---|---|
| 11/04/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 10/21/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 10/15/2025 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 08/29/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 08/29/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 08/13/2025 | Interior lighting power | NARESH MAHANGU | energy_progress |
| 08/13/2025 | Fenestration and door U-factor and product ratings | NARESH MAHANGU | energy_progress |
| 08/13/2025 | Fire-Resistant Penetrations and Joints | NARESH MAHANGU | special |
| 08/13/2025 | Fire-Resistance Rated Construction | NARESH MAHANGU | progress |
| 08/13/2025 | Final | Chun Feng | progress |
| 08/13/2025 | Energy Code Compliance Inspections | NARESH MAHANGU | progress |
| 08/13/2025 | Air barrier - visual inspection | NARESH MAHANGU | energy_progress |
| 08/13/2025 | Fenestration air leakage | NARESH MAHANGU | energy_progress |
| 08/13/2025 | Fenestration areas | NARESH MAHANGU | energy_progress |
| 08/13/2025 | Insulation placement and R values | NARESH MAHANGU | energy_progress |
| 08/11/2025 | Fire-Resistant Penetrations and Joints | NARESH MAHANGU | special |
| 08/11/2025 | Energy Code Compliance Inspections | NARESH MAHANGU | progress |
| 08/11/2025 | Final | Chun Feng | progress |
| 08/11/2025 | Fire-Resistance Rated Construction | NARESH MAHANGU | progress |
| 08/11/2025 | Fenestration areas | NARESH MAHANGU | energy_progress |
| 08/11/2025 | Insulation placement and R values | NARESH MAHANGU | energy_progress |
| 08/11/2025 | Air barrier - visual inspection | NARESH MAHANGU | energy_progress |
| 08/11/2025 | Fenestration and door U-factor and product ratings | NARESH MAHANGU | energy_progress |
| 08/11/2025 | Interior lighting power | NARESH MAHANGU | energy_progress |
| 08/11/2025 | Fenestration air leakage | NARESH MAHANGU | energy_progress |
| 05/30/2025 | Energy Code Compliance Inspections | Chun Feng | progress |
| 05/30/2025 | Fire-Resistant Penetrations and Joints | NARESH MAHANGU | special |