← Back
Elevator apt, semi-fireproof with stores
87-40 165 STREET
QUEENS · BIN 4210407
💬 Discuss this project
1960Year Built
6Stories
D7Building Class
C4-4DZoning
121,138 sfGross Floor Area
119Units
LL97 CoveredRent Stabilized534 Open Violations 496 unresolved · 38 paperwork only ▸FISP: No Report FiledFDNY Report ↗
Elevator apt, semi-fireproof with stores · Owner of record: 87-40 165 STREET, LLC · 36,737 sf lot · 3.3 FAR built · Flood zone X
Locations of Work
Floor 61 filing · 4 docs
Floor 51 filing · 4 docs
Floor 41 filing · 4 docs
Floor 31 filing · 4 docs
Floor 21 filing · 4 docs
Floor 12 filings · 8 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
87-40 165 STREET LLC3003/22/2026
82-40 165 STREET, LLC103/22/2026
HILLSIDE HOUSING MANAGEME503/22/2026
HILSIDE HOUSE MANAGEMENT103/22/2026
HILLSIDE MANAGEMENT103/22/2026
HILLSINN HOUSE MAN LLC/HA103/22/2026
HILLSIDE HOUSE MGNT CO203/22/2026
HILLSIDE HOUSING MANAG203/22/2026
HILLSIDE HOUSE MANG LLC103/22/2026
KRCM REALTY403/21/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
04/19/2019$15.8M—— → —$130/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
STRUCTURAL DESIGN COLLABORATIVE112/08/2023
LEDER-LUIS ARCHITECTURAL DESIGN, PL112/22/2022
ASHRAF CORP403/04/2020
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
FRANK BUENO EXPEDITING203/21/2026
XPDITE GROUP LLC (104)103/21/2026
SHEIKH EXPEDITING803/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
ALL EMPIRE BUILDING CONGeneral Contractor1307/08/2026
JOSEPH ALOIAElectrical103/21/2026
SCHWARTZ, IRVINGElectrical103/21/2026
Building Lifecycle
All (89)Filed (6)Permit Issued (7)Facade (FISP) (3)Violation (60)Objection (12)Special Inspection (1)
08/18/2026
Violation issued (HPD, open)
B
08/18/2026
Violation issued (HPD, open)
B
08/18/2026
Violation issued (HPD, open)
B
08/18/2026
Violation issued (HPD, open)
B
08/18/2026
Violation issued (HPD, open)
B
08/18/2026
Violation issued (HPD, open)
B
08/18/2026
Violation issued (HPD, open)
B
08/18/2026
Violation issued (HPD, open)
B
08/18/2026
Violation issued (HPD, open)
B
08/18/2026
Violation issued (HPD, open)
B
08/18/2026
Violation issued (HPD, open)
B
08/18/2026
Violation issued (HPD, open)
B
08/18/2026
Violation issued (HPD, open)
B
08/18/2026
Violation issued (HPD, open)
C
08/18/2026
Violation issued (HPD, open)
B
08/07/2026
Violation issued (HPD, open)
B
08/07/2026
Violation issued (HPD, open)
B
08/07/2026
Violation issued (HPD, open)
B
08/07/2026
Violation issued (HPD, open)
B
07/15/2026
Violation issued (HPD, closed)
C
07/15/2026
Violation issued (HPD, open)
C
07/15/2026
Violation issued (HPD, open)
C
06/17/2026
Violation issued (HPD, closed)
A
06/16/2026
Violation issued (HPD, closed)
B
06/16/2026
Violation issued (HPD, closed)
B
06/16/2026
Violation issued (HPD, open)
B
06/16/2026
Violation issued (HPD, open)
C
06/16/2026
Violation issued (HPD, open)
B
06/16/2026
Violation issued (HPD, closed)
C
06/16/2026
Violation issued (HPD, open)
C
06/16/2026
Violation issued (HPD, open)
B
06/16/2026
Violation issued (HPD, open)
A
06/16/2026
Violation issued (HPD, open)
B
06/16/2026
Violation issued (HPD, open)
C
06/11/2026
Violation issued (HPD, open)
B
06/11/2026
Violation issued (HPD, closed)
B
06/11/2026
Violation issued (HPD, closed)
B
06/11/2026
Violation issued (HPD, open)
A
06/11/2026
Violation issued (HPD, open)
C
06/11/2026
Violation issued (HPD, closed)
C
06/11/2026
Violation issued (HPD, closed)
A
06/11/2026
Violation issued (HPD, closed)
B
06/11/2026
Violation issued (HPD, open)
B
06/11/2026
Violation issued (HPD, closed)
B
06/11/2026
Violation issued (HPD, open)
B
06/11/2026
Violation issued (HPD, open)
A
06/11/2026
Violation issued (HPD, closed)
B
06/11/2026
Violation issued (HPD, closed)
A
06/10/2026
Violation issued (HPD, closed)
C
06/10/2026
Violation issued (HPD, closed)
C
06/10/2026
Violation issued (HPD, closed)
B
06/10/2026
Violation issued (HPD, closed)
B
06/10/2026
Violation issued (HPD, open)
C
06/10/2026
Violation issued (HPD, open)
C
06/10/2026
Violation issued (HPD, open)
B
06/10/2026
Violation issued (HPD, open)
B
06/10/2026
Violation issued (HPD, closed)
B
06/10/2026
Violation issued (HPD, closed)
B
06/10/2026
Violation issued (HPD, open)
C
06/10/2026
Violation issued (HPD, closed)
B
Latest 60 of 89 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSupported ScaffoldPermit IssuedALL EMPIRE BUILDING CON06/03/2021
DOB NOWSidewalk ShedPermit IssuedALL EMPIRE BUILDING CON06/02/2021
DOB NOWSidewalk ShedPermit IssuedALL EMPIRE BUILDING CON05/11/2020
DOB NOWSupported ScaffoldPermit IssuedALL EMPIRE BUILDING CON05/11/2020
DOB NOWSupported ScaffoldPermit IssuedALL EMPIRE BUILDING CON05/14/2019
DOB NOWSidewalk ShedPermit IssuedALL EMPIRE BUILDING CON05/10/2019
DOB NOWSidewalk ShedPermit IssuedALL EMPIRE BUILDING CON03/26/2019
BISOTISSUEDALL EMPIRE BUILDING CON11/02/2020
BISOTISSUEDALL EMPIRE BUILDING CON07/01/2019
BISOTISSUEDTHE DEMAR GEN'L CONSTR LT08/21/2018
BISEQISSUEDPOWERS BRIDGING & SCAFFOLDING12/08/2017
BISEQISSUEDPOWERS BRIDGING & SCAFFOLDING11/07/2016
BISEQISSUEDPOWERS BRIDGING & SCAFFOLDING11/04/2015
BISMHISSUEDBEYS CONTRACTING INC08/24/2001
BISPLISSUEDMAGOR PLUMBING AND HEATING03/22/1993
BISOTISSUEDLINMAR CONSTRUCTION02/07/1991
BIS—ISSUEDLINMAR CONSTRUCTION GENL CONTRAC02/05/1991
BISPLISSUEDNEW YORK CITY PLG AND HEATING01/30/1991
BISPLISSUEDHIRSH PLG CO INC09/19/1990
BISMHISSUEDLINMAR CONSTRUCTION CORP07/05/1990
4 projects · most recent 04/24/2022
General Wiring
FiledStatusContractorScope
04/24/2022Permit IssuedUL ELECTRICAL CORP.1 meters
05/29/2019CompleteDELTEX ELECTRICAL CONT. I—
05/01/2019Permit IssuedUL ELECTRICAL CORP.General Wiring
03/28/2019CompleteRICHARD NEU—
1 project · most recent 12/08/2023
Steel Concrete
FiledStatusContractorScope
12/08/2023——Steel, Concrete
2 projects · most recent 03/04/2020
Sidewalk Shed Scaffold
FiledStatusContractorScope
03/04/2020Permit IssuedALL EMPIRE BUILDING CONSidewalk Shed
03/03/2020Permit IssuedALL EMPIRE BUILDING CONScaffold
▾Special Inspection Requirements (DOB NOW) — 1
DateRequirementInspectorRole
12/22/2022Tenant Protection Plan Compliance—special
▾Documents — 89 on file (BIS + DOB NOW)
▸Plans & Drawings6
▸DOB NOWPlans/Sketch - Sidewalk Shed2
08/28/2026Q00142690-I1Request digital key ↗
08/15/2026Q00142690-P1Request digital key ↗
▸DOB NOWPlans/Sketch - Supported Scaffold2
08/28/2026Q00162976-I1Request digital key ↗
08/15/2026Q00162976-P1Request digital key ↗
▸DOB NOWPlans/Sketch2
08/23/2026Q00924854-I1Request digital key ↗
08/14/2026Q00793692-I1Request digital key ↗
▸Applications & Permits12
▸BISPLAN / WORK APPROVAL APPLICATION6
07/09/2025421937140Open ↗
06/08/2019421937140Open ↗
05/02/2019421948646Open ↗
Showing 3 of 6 on file for this type
▸BISWORK PERMIT APPLICATION6
11/18/2020421937140Open ↗
07/16/2019421937140Open ↗
10/01/2018421564845Open ↗
Showing 3 of 6 on file for this type
▸Seals & Professional Certifications25
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION10
07/30/2019440263670Open ↗
07/30/2019440263670Open ↗
07/30/2019440263670Open ↗
Showing 3 of 10 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature6
08/28/2026Q00162976-I1Open ↗
08/28/2026Q00142690-P1Open ↗
08/28/2026Q00142690-I1Open ↗
Showing 3 of 6 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT4
06/08/2019421937140Open ↗
10/22/2017421564845Open ↗
10/27/2015440263670Open ↗
Showing 3 of 4 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST3
06/08/2019421937140Open ↗
10/22/2017421564845Open ↗
09/18/2014420987141Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY1
10/27/2015440263670Open ↗
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION1
10/27/2015440263670Open ↗
▸Trade Schedules & Equipment2
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE1
05/02/2019421948646Open ↗
▸BISJAMAICA: DEP SEWER CONNECTION APPROVAL1
10/27/2015440263670Open ↗
▸Safety & Tenant Protection4
▸BISHPD: SRO MD CERTIFICATE OF NO HARASSMENT1
07/30/2019440263670Open ↗
▸BISSTREET TREE CHECKLIST1
05/02/2019421948646Open ↗
▸BISTenant Protection Plan and Notes1
06/08/2019421937140Open ↗
▸BISST-1 Street Tree Checklist1
01/08/2015420987141Open ↗
▸Environmental & Asbestos3
▸BISASBESTOS: CERTIFICATION (DEP ACP5)2
06/08/2019421937140Open ↗
10/22/2017421564845Open ↗
▸BISACP5 ASBESTOS: CERTIFICATION (DEP ACP5)1
01/08/2015420987141Open ↗
▸Energy Compliance7
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS6
07/20/2019421937140Open ↗
06/08/2019421937140Open ↗
06/08/2019421937140Open ↗
Showing 3 of 6 on file for this type
▸BISELECTRICAL APPLICATION FOR SIDEWALK SHED LIGHTING1
10/27/2015440263670Open ↗
▸Inspections & Test Reports1
▸BISTECHNICAL REPORT: RESPONSIBILITY1
10/27/2015440263670Open ↗
▸Approvals, Objections & Sign-offs11
▸BISLETTERS - SUPPORTING DOCUMENTATION3
05/02/2019421948646Open ↗
06/26/2015420987141Open ↗
09/17/2014420987141Open ↗
▸BISSCHEDULE A - OCCUPANCY / USE3
05/02/2019421948646Open ↗
12/17/2014420987141Open ↗
11/08/2014420987141Open ↗
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST2
07/31/2019440263670Open ↗
07/30/2019440263670Open ↗
▸BISSHED LETTER2
12/12/2017440263670Open ↗
12/12/2017440263670Open ↗
▸BISLETTERS - APPRVD FAB CERT-INTENT1
11/16/2016440263670Open ↗
▸Cost, Insurance & Ownership5
▸BISCOST AFFIDAVIT5
06/08/2019421937140Open ↗
05/02/2019421948646Open ↗
10/22/2017421564845Open ↗
Showing 3 of 5 on file for this type
▸Filing & Intake Forms7
▸BISEFILING COVER SHEET4
06/10/2019421937140Open ↗
05/03/2019421948646Open ↗
10/22/2017421564845Open ↗
Showing 3 of 4 on file for this type
▸BISBOROUGH INTAKE FORM2
09/29/2021421937140Open ↗
07/30/2019440263670Open ↗
▸BISEFILING JOB APPLICATION COVER SHEET1
10/27/2015440263670Open ↗
▸Other Documents6
▸DOB NOWHPD4: CONH Pilot Program2
08/13/2026Q00924854-I1Open ↗
08/13/2026Q00793692-I1Open ↗
▸BISPLOT DIAGRAM1
09/17/2014420987141Open ↗
▸BISHPD: CONH PILOT1
07/20/2019421937140Open ↗
▸BISEXTERNAL FORMS - SUPPORTING DOCUMENTATION1
10/27/2015440263670Open ↗
▸BISTENANT/OCCUPANT PROTECTION PLAN 2008 CODE1
10/27/2015440263670Open ↗