Two stories - detached, small or mid-size
87-55 110 STREET
QUEENS · BIN 4194795
💬 Discuss this project
1910Year Built
2Stories
A1Building Class
R3-1Zoning
—Gross Floor Area
1Units
0 Open ViolationsFDNY Report ↗
Two stories - detached, small or mid-size · 0.73 FAR built · Flood zone X
Locations of Work
No floor-level scope or drawing coverage on file for this building.
1 job · most recent 03/27/2018
FiledStatusContractorScope
03/27/2018CompleteISLAND ELECTRIC CORP—
Building Lifecycle
All (1)Violation (1)
11/01/1988
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
Nothing on file for this building.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
BISOTISSUEDPRO CUSTOM SOLAR LLC03/01/2018
Nothing on file for this building.
▾Documents — 32 on file (BIS + DOB NOW)
▸Applications & Permits3
▸BISPLAN / WORK APPROVAL APPLICATION2
02/27/2018440467237Open ↗
09/18/2017440434380Open ↗
▸BISWORK PERMIT APPLICATION1
02/27/2018440467237Open ↗
▸Seals & Professional Certifications4
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION1
02/27/2018440467237Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT1
02/27/2018440467237Open ↗
▸BISAPPLICANT OWNER SIGNATURE1
09/18/2017440434380Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY1
02/27/2018440467237Open ↗
▸Safety & Tenant Protection2
▸BISTENANT PROTECTION PLAN AND NOTES2
02/27/2018440467237Open ↗
09/18/2017440434380Open ↗
▸Environmental & Asbestos2
▸BISASBESTOS: CERTIFICATION (DEP ACP5)2
02/27/2018440467237Open ↗
11/01/2017440434380Open ↗
▸Energy Compliance8
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY3
09/25/2018440467237Open ↗
02/27/2018440467237Open ↗
09/18/2017440434380Open ↗
▸BISAS-BUILT ENERGY ANALYSIS1
09/25/2018440467237Open ↗
▸BISSOLAR TAX ABATEMENT APPLICATION1
09/18/2017440434380Open ↗
▸BISPTA4: SOLAR TAX ABATEMENT APPLICATION (PRELIMINARY)1
02/27/2018440467237Open ↗
▸BISPTA4: SOLAR TAX ABATEMENT APPLICATION (FINAL)1
09/25/2018440467237Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY FOR ENERGY CODE PROGRESS INSPECTIONS1
02/27/2018440467237Open ↗
▸Inspections & Test Reports3
▸BISTECHNICAL REPORT: RESPONSIBILITY3
09/25/2018440467237Open ↗
02/27/2018440467237Open ↗
09/18/2017440434380Open ↗
▸Approvals, Objections & Sign-offs2
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST1
09/25/2018440467237Open ↗
▸BISUtility Company PV System Interconnection Acknowledgement Letter1
09/25/2018440467237Open ↗
▸Cost, Insurance & Ownership3
▸BISCOST AFFIDAVIT3
09/25/2018440467237Open ↗
02/27/2018440467237Open ↗
09/18/2017440434380Open ↗
▸Filing & Intake Forms5
▸BISADDITIONAL INFORMATION3
01/10/2018440434380Open ↗
12/12/2017440434380Open ↗
11/01/2017440434380Open ↗
▸BISEFILING JOB APPLICATION COVER SHEET2
02/27/2018440467237Open ↗
09/18/2017440434380Open ↗