← Back
BuildNYC
Unlicensed parking lot
87-82 153RD STREET
QUEENS · Jamaica · BIN 4812927
💬 Discuss this project
0Year Built
—Stories
G7Building Class
R7XZoning
0 sfGross Floor Area
0Units
Unlicensed parking lot · Owner of record: Darul-U'Loom Inc., New York · 4,000 sf lot · 0 FAR built · Flood zone X
Locations of Work
ArchitectureElectricalGeneral
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
Filed — no permit issuedDarul Uloom INC New York50p · 1 filing · 3 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
Darul Uloom Inc New York103/21/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
Anthony Cucich Architect108/26/2025
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
Anthony Cucich Architect103/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
Anthony Cucich Architect6081108/26/2025
Building Lifecycle
All (46)Filed (1)Objection (21)Special Inspection (24)
12/30/2025
Objection resolved — Addressed
12/30/2025
Objection resolved — Addressed
12/30/2025
Objection resolved — Addressed
12/30/2025
Objection resolved — Addressed
12/30/2025
Objection resolved — Addressed
12/30/2025
Special inspection requirement — Energy Code Compliance Inspections
ANTHONY CUCICH
12/30/2025
Special inspection requirement — Fire-Resistance Rated Construction
ANTHONY CUCICH
10/23/2025
Objection raised — Zoning
10/23/2025
Objection raised — Zoning
10/23/2025
Objection raised — Zoning
10/23/2025
Objection raised — Zoning
10/23/2025
Objection raised — Zoning
10/23/2025
Objection raised — Zoning
10/21/2025
Objection raised — Fire_Protection
10/21/2025
Objection raised — Scope
10/10/2025
Objection raised — Plumbing
10/10/2025
Objection raised — Plumbing
09/24/2025
Objection raised — Fire_Protection
09/24/2025
Objection raised — Admin
09/24/2025
Objection raised — Structural
09/24/2025
Objection raised — Scope
09/24/2025
Objection raised — Energy
09/24/2025
Objection raised — Scope
08/26/2025
Filed — New Building
NEW 6 STORY COMMUNITY FACILITY BUILDING
Q01261254-I1
07/24/2025
Special inspection requirement — Exterior Insulation and Finish Systems (EIFS)
ANTHONY CUCICH
07/24/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
ANTHONY CUCICH
07/24/2025
Special inspection requirement — Masonry
ANTHONY CUCICH
07/24/2025
Special inspection requirement — Subgrade Inspections
ANTHONY CUCICH
07/24/2025
Special inspection requirement — Interior lighting power
ANTHONY CUCICH
07/24/2025
Special inspection requirement — Fenestration air leakage
ANTHONY CUCICH
07/24/2025
Special inspection requirement — Air barrier - visual inspection
ANTHONY CUCICH
07/24/2025
Special inspection requirement — Electric vehicle service equipment requirements
ANTHONY CUCICH
07/24/2025
Special inspection requirement — Lighting controls
ANTHONY CUCICH
07/24/2025
Special inspection requirement — Electrical motors and elevators
ANTHONY CUCICH
07/24/2025
Special inspection requirement — Metering
ANTHONY CUCICH
07/24/2025
Special inspection requirement — Fenestration and door U-factor and product ratings
ANTHONY CUCICH
07/24/2025
Special inspection requirement — Lighting in dwelling units
ANTHONY CUCICH
07/24/2025
Special inspection requirement — Exterior lighting power
ANTHONY CUCICH
07/24/2025
Special inspection requirement — Insulation placement and R values
ANTHONY CUCICH
07/24/2025
Special inspection requirement — Maintenance information
ANTHONY CUCICH
07/24/2025
Special inspection requirement — Vestibules
ANTHONY CUCICH
07/24/2025
Special inspection requirement — Fenestration areas
ANTHONY CUCICH
07/24/2025
Special inspection requirement — Permanent certificate
ANTHONY CUCICH
07/24/2025
Special inspection requirement — Concrete - Cast-In-Place
ANTHONY CUCICH
07/24/2025
Special inspection requirement — Protection of exposed foundation insulation
ANTHONY CUCICH
07/24/2025
Special inspection requirement — Concrete - Precast
ANTHONY CUCICH
Nothing on file for this building.
Nothing on file for this building.
▾Special Inspection Requirements (DOB NOW) — 24
DateRequirementInspectorRole
12/30/2025Energy Code Compliance InspectionsANTHONY CUCICHprogress
12/30/2025Fire-Resistance Rated ConstructionANTHONY CUCICHprogress
07/24/2025Exterior Insulation and Finish Systems (EIFS)ANTHONY CUCICHspecial
07/24/2025Fire-Resistant Penetrations and JointsANTHONY CUCICHspecial
07/24/2025MasonryANTHONY CUCICHspecial
07/24/2025Subgrade InspectionsANTHONY CUCICHspecial
07/24/2025Interior lighting powerANTHONY CUCICHenergy_progress
07/24/2025Fenestration air leakageANTHONY CUCICHenergy_progress
07/24/2025Air barrier - visual inspectionANTHONY CUCICHenergy_progress
07/24/2025Electric vehicle service equipment requirementsANTHONY CUCICHenergy_progress
07/24/2025Lighting controlsANTHONY CUCICHenergy_progress
07/24/2025Electrical motors and elevatorsANTHONY CUCICHenergy_progress
07/24/2025MeteringANTHONY CUCICHenergy_progress
07/24/2025Fenestration and door U-factor and product ratingsANTHONY CUCICHenergy_progress
07/24/2025Lighting in dwelling unitsANTHONY CUCICHenergy_progress
07/24/2025Exterior lighting powerANTHONY CUCICHenergy_progress
07/24/2025Insulation placement and R valuesANTHONY CUCICHenergy_progress
07/24/2025Maintenance informationANTHONY CUCICHenergy_progress
07/24/2025VestibulesANTHONY CUCICHenergy_progress
07/24/2025Fenestration areasANTHONY CUCICHenergy_progress
07/24/2025Permanent certificateANTHONY CUCICHenergy_progress
07/24/2025Concrete - Cast-In-PlaceANTHONY CUCICHspecial
07/24/2025Protection of exposed foundation insulationANTHONY CUCICHenergy_progress
07/24/2025Concrete - PrecastANTHONY CUCICHspecial
▾Tenants in the building
TenantSpaceFloorsRenovation projects
Darul Uloom INC New YorkEducation—
Project Q01261254 New Building · Objections · 08/26/2025
Names are taken automatically from the text of each project’s filed documents (title blocks and cover sheets) and screened to exclude owners, landlords and designers. They may be incomplete or wrong; check the filing.
▾Documents — 9 on file (BIS + DOB NOW)
▸Plans & Drawings1
▸DOB NOWPlans/Sketch1
08/14/2026Q01261254-I1Request digital key ↗
▸Zoning, Tax Lot & Property Records2
▸DOB NOWZD1: DOB Zoning Diagram1
08/13/2026Q01261254-I1Open ↗
▸DOB NOWHouse Number Verification: TOPO Stamp1
08/14/2026Q01261254-I1Open ↗
▸Seals & Professional Certifications1
▸DOB NOWDPL-1: Design Professional Seal & Signature1
08/19/2026Q01261254-I1Open ↗
▸Safety & Tenant Protection1
▸DOB NOWStreet Tree Checklist1
08/13/2026Q01261254-I1Open ↗
▸Approvals, Objections & Sign-offs1
▸DOB NOWFee Exempt Supporting Document - DOF ACRIS report or BIB letter1
08/13/2026Q01261254-I1Open ↗
▸Other Documents3
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone1
08/13/2026Q01261254-I1Open ↗
▸DOB NOWProperty Ownership Certification1
08/14/2026Q01261254-I1Open ↗
▸DOB NOWSite Survey: Initial1
08/13/2026Q01261254-I1Open ↗