← Back
Elevator cooperative
Masaryk Towers
87 DELANCEY STREET · Lower East Side · BIN 1082666
💬 Discuss this project
1966Year Built
21Stories
D4Building Class
R7-2Zoning
1,191,180 sfGross Floor Area
1,104Units
LL97 CoveredRent Stabilized76 Open Violations 37 unresolved · 39 paperwork only ▸FISP: UNSAFEFDNY Report ↗
Elevator cooperative · Owner of record: MASARYK TOWERS CORP · 357,575 sf lot · 3.33 FAR built · Flood zone X500
Locations of Work
ArchitectureStructuralElectricalEquipmentGeneralOther
Permit Issued — active, not yet Signed-off
RoofUnder Construction10p · 3 filings · 20 docs
Site & exteriorUnder Construction15p · 3 filings · 18 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
MASARYK TOWERS3203/21/2026
XINOS CONSTRUCTION1209/13/2026
C O MASARYK TOWERS203/21/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
QUEENS ENGINEERING303/28/2026
CRIBSTONE ENGINEERING PLLC203/20/2026
LAWLESS & MANGIONE101/17/2025
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
XINOS CONSTRUCTION CORPGeneral Contractor709/02/2026
ANASTASIOS MATSIKASElectrical103/21/2026
REGIONAL ELEC'L VOICE &Electrical103/22/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
QUEENS ENGINEERING PLLC8898303/28/2026
NY RESTORATION TECHNOLOGY6187101/17/2025
Building Lifecycle
All (99)Filed (6)Permit Issued (8)Facade (FISP) (14)Violation (60)Special Inspection (11)
09/01/2026
Permit issued — Sidewalk Shed
M01230374-I1-SH
06/02/2026
Permit issued — Sidewalk Shed
M01230374-I1-SH
05/08/2026
Violation issued (HPD, closed)
C
05/08/2026
Violation issued (HPD, open)
C
04/30/2026
Permit issued — Suspended Scaffold
M01233064-I1-SC
04/20/2026
Violation issued (ECB, open)
Local Law
04/15/2026
Violation issued (HPD, closed)
B
04/15/2026
Violation issued (HPD, closed)
B
04/15/2026
Violation issued (HPD, closed)
B
04/15/2026
Violation issued (HPD, open)
B
04/15/2026
Violation issued (HPD, closed)
B
04/15/2026
Violation issued (HPD, closed)
B
04/15/2026
Violation issued (HPD, closed)
B
04/14/2026
Violation issued (HPD, open)
A
04/14/2026
Violation issued (HPD, closed)
A
04/14/2026
Violation issued (HPD, closed)
B
04/14/2026
Violation issued (HPD, closed)
A
04/14/2026
Violation issued (HPD, closed)
B
04/14/2026
Violation issued (HPD, closed)
A
04/14/2026
Violation issued (HPD, closed)
B
04/14/2026
Violation issued (HPD, closed)
B
04/14/2026
Violation issued (HPD, closed)
B
04/14/2026
Violation issued (HPD, closed)
A
04/14/2026
Violation issued (HPD, closed)
B
04/14/2026
Violation issued (HPD, open)
A
04/14/2026
Violation issued (HPD, closed)
A
04/14/2026
Violation issued (HPD, closed)
B
03/31/2026
Special inspection requirement — Alternative Materials - OTCR Buildings Bulletin Number
ANDREAS CHRISTOFOROU
03/31/2026
Special inspection requirement — Post-installed Anchors
ANDREAS CHRISTOFOROU
03/28/2026
Filed — Alteration
OUTRIGGERS SYSTEM INSTALLATION FOR FACADE REPAIRS. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
M01233064-P1
03/25/2026
Violation issued (HPD, closed)
A
03/25/2026
Violation issued (HPD, closed)
B
03/25/2026
Violation issued (HPD, closed)
B
03/20/2026
Filed — Alteration
PROPOSED INSTALLATION OF A TEMPORARY SIDEWALK SHED AS PER PLANS SUBMITTED. WORK SHALL COMPLY WITH 2022 BUILDING CODES, CHAPTER 33, NO CHANGE IN USE, EGRESS OR OCCUPANCY.
M01230374-P1
03/18/2026
Special inspection requirement — Post-installed Anchors
ANDREAS CHRISTOFOROU
03/18/2026
Special inspection requirement — Alternative Materials - OTCR Buildings Bulletin Number
ANDREAS CHRISTOFOROU
03/09/2026
Permit issued — Sidewalk Shed
M01230374-I1-SH
01/20/2026
Violation issued (FDNY_NOV, closed)
01/09/2026
Cycle 10 facade report submitted
12/12/2025
Permit issued — General Construction
M01153185-I1-GC
11/20/2025
Permit issued — Supported Scaffold
M01317502-I1-SF
11/19/2025
Filed — Alteration
PROPOSED INSTALLATION OF A TEMPORARY PIPE SCAFFOLDING AS PER PLANS SUBMITTED. WORK SHALL COMPLY WITH 2022 BUILDING CODE, CHAPTER 33. NO CHANGES IN USE, EGRESS OR OCCUPANCY.
M01317502-I1
11/11/2025
Cycle 10 facade inspection completed
11/05/2025
Cycle 10 facade report signed — UNSAFE
05/30/2025
Filed — Alteration
OUTRIGGERS SYSTEM INSTALLATION FOR FACADE REPAIRS. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
M01233064-I1
05/30/2025
Permit issued — Suspended Scaffold
M01233064-I1-SC
05/23/2025
Permit issued — Sidewalk Shed
M01230374-I1-SH
05/22/2025
Filed — Alteration
PROPOSED INSTALLATION OF A TEMPORARY SIDEWALK SHED AS PER PLANS SUBMITTED. WORK SHALL COMPLY WITH 2022 BUILDING CODES, CHAPTER 33, NO CHANGE IN USE, EGRESS OR OCCUPANCY.
M01230374-I1
04/24/2025
Violation issued (ECB, open)
Local Law
01/17/2025
Filed — Alteration
M01153185-I1
12/18/2024
Special inspection requirement — Structural Stability – Alterations of existing buildings
Hamidreza Saghari
12/18/2024
Special inspection requirement — Air barrier - visual inspection
Kenneth Santelli
12/18/2024
Special inspection requirement — Tenant Protection Plan Compliance
Hamidreza Saghari
12/18/2024
Special inspection requirement — Insulation placement and R values
Kenneth Santelli
12/18/2024
Special inspection requirement — Post-installed Anchors
Hamidreza Saghari
12/18/2024
Special inspection requirement — Masonry
Hamidreza Saghari
12/09/2024
Special inspection requirement — Final
Kenneth Santelli
09/27/2024
Violation issued (HPD, open)
C
09/27/2024
Violation issued (HPD, closed)
A
09/27/2024
Violation issued (HPD, closed)
B
Latest 60 of 99 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSidewalk ShedPermit IssuedXINOS CONSTRUCTION CORP09/01/2026
DOB NOWSidewalk ShedPermit IssuedXINOS CONSTRUCTION CORP06/02/2026
DOB NOWSuspended ScaffoldPermit IssuedXINOS CONSTRUCTION CORP04/30/2026
DOB NOWSidewalk ShedPermit IssuedXINOS CONSTRUCTION CORP03/09/2026
DOB NOWGeneral ConstructionPermit IssuedXINOS CONSTRUCTION CORP12/12/2025
DOB NOWSupported ScaffoldPermit IssuedXINOS CONSTRUCTION CORP11/20/2025
DOB NOWSuspended ScaffoldPermit IssuedXINOS CONSTRUCTION CORP05/30/2025
DOB NOWSidewalk ShedPermit IssuedXINOS CONSTRUCTION CORP05/23/2025
BISOTISSUEDAM&G WATERPROOFING LLC04/30/2025
BISOTISSUEDAM&G WATERPROOFING LLC04/25/2024
BISOTISSUEDAM&G WATERPROOFING LLC04/20/2023
BISPLISSUEDHARLEY PLUMB & HEAT INC01/03/2023
BISOTISSUEDAM&G WATERPROOFING LLC04/21/2022
BISPLISSUEDHARLEY PLUMB & HEAT INC12/20/2021
BISOTISSUEDAM&G WATERPROOFING LLC04/15/2021
BISPLISSUEDHARLEY PLUMB & HEAT INC07/01/2020
BISOTISSUEDAM&G WATERPROOFING LLC04/09/2020
BISOTISSUEDAM&G WATERPROOFING LLC03/27/2020
BISOTISSUEDAM&G WATERPROOFING LLC04/16/2019
BISPLISSUEDHARLEY PLUMB & HEAT INC04/15/2019
BISOTISSUEDAM&G WATERPROOFING LLC01/18/2019
BISOTISSUEDCENTRAL CONSTRUCTION MANAGEMENT06/01/2015
BISOTISSUEDCENTRAL CONSTRUCTION MANAGEMENT04/09/2015
BISOTISSUEDCENTRAL CONSTRUCTION MANAGEMENT04/09/2015
BISEQISSUEDB & S RESTORATION INC02/24/2015
BISOTISSUEDCENTRAL CONSTRUCTION MANAGEMENT01/23/2015
BISOTISSUEDCENTRAL CONSTRUCTION MANAGEMENT01/10/2014
BISOTISSUEDCENTRAL CONSTRUCTION MANAGEMENT01/10/2014
BISOTISSUEDCENTRAL CONSTRUCTION MANAGEMENT10/02/2013
BISEQISSUEDCENTRAL CONSTRUCTION MANAGEMENT08/28/2013
BISOTISSUEDCENTRAL CONSTRUCTION MANAGEMENT07/15/2013
BISCCISSUEDCENTRAL CONSTRUCTION MANAGEMENT06/20/2013
BISEQISSUEDB & S RESTORATION INC05/14/2013
BISOTISSUEDCENTRAL CONSTRUCTION MANAGEMENT09/18/2012
BISEQISSUEDCENTRAL CONSTRUCTION MANAGEMENT08/03/2012
BISOTISSUEDCENTRAL CONSTRUCTION MANAGEMENT07/18/2012
BISEQISSUEDB & S RESTORATION INC05/17/2012
BISEQISSUEDB & S RESTORATION INC09/20/2011
BISEQISSUEDTWIN & SWING SCAFFOLDING03/25/2011
BISEQISSUEDMETROPOLITAN ENTERPRISES12/05/2008
5 projects · most recent 01/14/2026
General Wiring
FiledStatusContractorScope
01/14/2026Permit IssuedDENALI ELECTRIC CORP—
01/13/2026Permit IssuedDENALI ELECTRIC CORP—
08/04/2025CompleteREGIONAL ELEC'L VOICE &General Wiring
07/23/2025Permit IssuedTOWER ELECTRIC INC.—
11/20/2019CompleteE-J ELEC. INSTALLATION COGeneral Wiring
2 projects · most recent 03/20/2026
Sidewalk Shed Scaffold
FiledStatusContractorScope
03/20/2026Permit IssuedXINOS CONSTRUCTION CORPSidewalk Shed
11/19/2025Permit IssuedXINOS CONSTRUCTION CORPScaffold
1 project · most recent 03/28/2026
Suspended Scaffold (SC)
FiledStatusContractorScope
03/28/2026Permit IssuedXINOS CONSTRUCTION CORPSuspended Scaffold (SC)
▾Special Inspection Requirements (DOB NOW) — 11
DateRequirementInspectorRole
03/31/2026Alternative Materials - OTCR Buildings Bulletin NumberANDREAS CHRISTOFOROUspecial
03/31/2026Post-installed AnchorsANDREAS CHRISTOFOROUspecial
03/18/2026Post-installed AnchorsANDREAS CHRISTOFOROUspecial
03/18/2026Alternative Materials - OTCR Buildings Bulletin NumberANDREAS CHRISTOFOROUspecial
12/18/2024Structural Stability – Alterations of existing buildingsHamidreza Sagharispecial
12/18/2024Air barrier - visual inspectionKenneth Santellienergy_progress
12/18/2024Tenant Protection Plan ComplianceHamidreza Sagharispecial
12/18/2024Insulation placement and R valuesKenneth Santellienergy_progress
12/18/2024Post-installed AnchorsHamidreza Sagharispecial
12/18/2024MasonryHamidreza Sagharispecial
12/09/2024FinalKenneth Santelliprogress
▾Documents — 174 on file (BIS + DOB NOW)
▸Plans & Drawings6
▸DOB NOWPlans/Sketch6
08/25/2026M01153185-I1Request digital key ↗
08/23/2026M01230374-P1Request digital key ↗
08/23/2026M01230374-I1Request digital key ↗
Showing 3 of 6 on file for this type
▸Applications & Permits39
▸BISWORK PERMIT APPLICATION22
06/10/2021123574480Open ↗
04/17/2019123574480Open ↗
04/16/2019123574480Open ↗
Showing 3 of 22 on file for this type
▸BISPLAN / WORK APPROVAL APPLICATION16
01/30/2026123574480Open ↗
06/20/2018123574480Open ↗
05/10/2017121072953Open ↗
Showing 3 of 16 on file for this type
▸BISPLAN - WORK & PERMITS - SUPPPORTING DOCUMENTATION1
10/31/2011120829826Open ↗
▸Seals & Professional Certifications48
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION22
12/20/2018123574480Open ↗
12/12/2018123574480Open ↗
06/20/2018123574480Open ↗
Showing 3 of 22 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature8
09/23/2026M01153185-I1Open ↗
09/23/2026M01153185-I1Open ↗
09/23/2026M01153185-I1Open ↗
Showing 3 of 8 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature7
08/23/2026M01230374-I1Open ↗
08/23/2026M01230374-P1Open ↗
08/23/2026M01233064-P1Open ↗
Showing 3 of 7 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST4
02/28/2015122265235Open ↗
03/19/2012120976186Open ↗
10/31/2011120829826Open ↗
Showing 3 of 4 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM3
03/19/2012120976186Open ↗
10/31/2011120829826Open ↗
09/03/2008110332961Open ↗
▸DOB NOWProgress Inspector Seal & Signature3
09/23/2026M01153185-I1Open ↗
08/25/2026M01153185-I1Open ↗
08/25/2026M01153185-I1Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT1
02/28/2015122265235Open ↗
▸Trade Schedules & Equipment1
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE1
06/20/2018123574480Open ↗
▸Safety & Tenant Protection3
▸BISTenant Protection Plan and Notes2
12/12/2018123574480Open ↗
06/20/2018123574480Open ↗
▸BISSTREET TREE CHECKLIST1
04/13/2011120653747Open ↗
▸Environmental & Asbestos8
▸BISASBESTOS EXEMPTION CERTIFICATION LETTER4
05/29/2013121629416Open ↗
03/19/2012120976186Open ↗
10/31/2011120829826Open ↗
Showing 3 of 4 on file for this type
▸BISTHIS IS 'NOT AN ASBESTOS PROJECT'2
05/14/2012121072953Open ↗
04/13/2011120653747Open ↗
▸BISASBESTOS: CERTIFICATION (DEP ACP5)1
12/12/2018123574480Open ↗
▸BISDEP ASBESTOS PROJECT COMPLETION FORM1
09/19/2012121054508Open ↗
▸Energy Compliance7
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS3
12/20/2018123574480Open ↗
06/06/2017121072953Open ↗
05/05/2017121054508Open ↗
▸BISTECHNICAL REPORT: ENERGY2
05/14/2012121072953Open ↗
04/25/2012121054508Open ↗
▸BISAS-BUILT ENERGY ANALYSIS2
06/06/2017121072953Open ↗
05/05/2017121054508Open ↗
▸Approvals, Objections & Sign-offs24
▸BISADMINISTRATIVE OBJECTIONS8
05/29/2013121629416Open ↗
08/02/2012120829826Open ↗
05/14/2012121072953Open ↗
Showing 3 of 8 on file for this type
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST6
06/06/2017121072953Open ↗
05/05/2017121054508Open ↗
05/05/2017121629416Open ↗
Showing 3 of 6 on file for this type
▸BISLETTERS - SUPPORTING DOCUMENTATION5
06/07/2017121072953Open ↗
05/05/2017121054508Open ↗
05/05/2017121629416Open ↗
Showing 3 of 5 on file for this type
▸BISSHED LETTER2
05/20/2013120829826Open ↗
05/18/2012120829826Open ↗
▸BISCONSTRUCTION CODE DETERMINATION1
11/16/2015121054508Open ↗
▸BISSUPERSEDING LETTER1
06/11/2015121054508Open ↗
▸DOB NOWDEP Variance (V5) letter1
08/13/2026M01153185-I1Open ↗
▸Cost, Insurance & Ownership17
▸BISCOST AFFIDAVIT17
06/20/2018123574480Open ↗
06/07/2017121072953Open ↗
05/05/2017121054508Open ↗
Showing 3 of 17 on file for this type
▸Filing & Intake Forms12
▸BISEFILING COVER SHEET9
06/20/2018123574480Open ↗
02/28/2015122265235Open ↗
05/29/2013121629416Open ↗
Showing 3 of 9 on file for this type
▸BISADDITIONAL INFORMATION3
12/12/2018123574480Open ↗
06/15/2017121072953Open ↗
02/24/2017121054508Open ↗
▸Other Documents9
▸BISEXTERNAL FORMS - SUPPORTING DOCUMENTATION4
03/04/2015122265235Open ↗
07/19/2012121072953Open ↗
04/25/2012121054508Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWManufacturer's Specifications2
08/23/2026M01233064-P1Open ↗
08/13/2026M01233064-I1Open ↗
▸DOB NOWCalculations2
08/23/2026M01233064-P1Open ↗
08/13/2026M01233064-I1Open ↗
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone1
08/13/2026M01153185-I1Open ↗