| Firm | Filings | Most Recent |
|---|---|---|
| ROGERS CALVANICO GROUP PLLC | 5 | 07/14/2023 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| AL-RICH BUILDERS LLC | General Contractor | 9 | 07/08/2026 |
| FLOW-RIGHT PLBG & HTG COR | Plumbing | 2 | 07/08/2026 |
| JSP ELECTL CNTNG CORP | Electrical | 1 | 03/22/2026 |
| RICHMOND ELEC'L CONTR'S | Electrical | 1 | 03/22/2026 |
| RSF BUILDING CORP | General Contractor | 1 | 07/08/2026 |
| QUALITY PLUMBING, INC | Plumbing | 1 | 07/08/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Signed-off | FLOW-RIGHT PLBG & HTG COR | 05/23/2023 |
| DOB NOW | Curb Cut | Signed-off | AL-RICH BUILDERS LLC | 03/01/2023 |
| DOB NOW | Construction Fence | Signed-off | AL-RICH BUILDERS LLC | 12/07/2022 |
| DOB NOW | Construction Fence | Signed-off | AL-RICH BUILDERS LLC | 06/16/2022 |
| DOB NOW | Construction Fence | Signed-off | AL-RICH BUILDERS LLC | 01/27/2022 |
| DOB NOW | Plumbing | Signed-off | FLOW-RIGHT PLBG & HTG COR | 07/06/2021 |
| DOB NOW | Construction Fence | Signed-off | AL-RICH BUILDERS LLC | 07/01/2021 |
| DOB NOW | Plumbing | Signed-off | QUALITY PLUMBING, INC | 06/28/2021 |
| DOB NOW | Construction Fence | Signed-off | AL-RICH BUILDERS LLC | 06/28/2021 |
| DOB NOW | Construction Fence | Signed-off | RSF BUILDING CORP | 03/23/2021 |
| BIS | — | ISSUED | AL-RICH BUILDERS LLC | 05/01/2023 |
| BIS | — | ISSUED | AL-RICH BUILDERS LLC | 12/06/2022 |
| BIS | — | ISSUED | AL-RICH BUILDERS LLC | 06/15/2022 |
| BIS | OT | ISSUED | J.B.I. CONSTRUCTION GROUP | 05/18/2022 |
| BIS | — | ISSUED | AL-RICH BUILDERS LLC | 01/27/2022 |
| BIS | — | ISSUED | AL-RICH BUILDERS LLC | 06/30/2021 |
| BIS | — | ISSUED | AL-RICH BUILDERS LLC | 02/25/2021 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/04/2023 | Cancelled | RICHMOND ELEC'L CONTR'S | General Wiring |
| 08/01/2022 | Complete | JSP ELECTL CNTNG CORP | — |
| 11/14/2021 | Complete | RICHMOND ELEC'L CONTR'S | General Wiring |
| Date | Type | Result | Report |
|---|---|---|---|
| 09/09/2023 | Pass-Final Curb Cut Non-Directive 14 | Pass | View ↗ |
| 06/20/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 05/22/2023 | Fail-Final PL - Up to 3 Requested Floors | Fail | View ↗ |
| 02/11/2022 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 11/19/2021 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 07/27/2021 | Pass-Final PL - Underground | Pass | View ↗ |
| 06/29/2021 | Certified Storm Drainage-ST-Fixtures-Finish | Certified | View ↗ |
| 06/29/2021 | Certified Storm Drainage-ST-Piping-Water Test | Certified | View ↗ |
| 06/29/2021 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 06/29/2021 | Certified Water and Sanitary-WS-Sanitary Piping-Water Test | Certified | View ↗ |
| 06/29/2021 | Certified Water Pressure - WP - PL - Underground Test | Certified | View ↗ |