← Back
Two family frame
88-01 80 STREET
QUEENS · BIN 4183565
💬 Discuss this project
1920Year Built
2.5Stories
B2Building Class
R3-1Zoning
2,650 sfGross Floor Area
2Units
Two family frame · 2,200 sf lot · 1.2 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralMechanicalPlumbing
Floor 23p · 2 filings · 20 docs
Floor 1
Cellar1p · 1 filing · 13 docs
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
11/23/2021$950K—Private party → Private party$358/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
HPL ENGINEERING P.C.403/01/2022
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
JM CONSULTANT STUDIO803/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
NEW YORK STANDARD MECH CORPPlumbing307/08/2026
ST SAFETY CONS. INCGeneral Contractor107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
HPL ENGINEERING PC5613403/01/2022
Building Lifecycle
All (35)Filed (4)Permit Issued (4)Signed Off (2)Inspection (3)Special Inspection (22)
08/26/2022
Signed off — Alteration
RENOVATE CELLAR, 1ST & 2ND FLOOR FOR AN EXISTING 2 1/2 STORY, 2 FAMILY HOUSE. NEW PARTITION, DOOR & WINDOW WORK AS PER PLAN SUBMITTED. PLUMBING WORK TO BE FILED UNDER DOBNow APPLICATION#: Q00652522. NO CHANGE TO USE, EGRESS OR OCCUPANCY.
Q00652476-I1
08/26/2022
Signed off — Alteration
FILE PLUMBING WORK IN-CONJUNCTION WITH DOBNow GENERAL CONSTRUCTION JOB#: Q00652476. CAP & REMOVE BOILER & HW HEATER AT CELLAR. INSTALL NEW & REPLACE PLUMBING FIXTURES AS PER PLAN SUBMITTED. NO CHANGE TO USE, EGRESS OR OCCUPANCY.
Q00652522-I1
07/06/2022
Permit issued — Plumbing
Q00652522-I1-PL
07/06/2022
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
06/08/2022
Permit issued — Plumbing
Q00652522-I1-PL
03/18/2022
Inspection — Certified Gas-Gas-Piping-Roughing
Certified
View inspection ↗
03/18/2022
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
03/04/2022
Special inspection requirement — Fire-Resistant Penetrations and Joints
Fran Huang
03/04/2022
Special inspection requirement — Final
Fran Huang
03/04/2022
Special inspection requirement — Energy Code Compliance Inspections
Fran Huang
03/04/2022
Special inspection requirement — Fenestration and door U-factor and product ratings
Fran Huang
03/04/2022
Special inspection requirement — Air barrier - visual inspection
Fran Huang
03/04/2022
Special inspection requirement — Fenestration air leakage
Fran Huang
03/04/2022
Special inspection requirement — Permanent certificate
Fran Huang
03/04/2022
Special inspection requirement — Interior lighting power
Fran Huang
03/01/2022
Filed — Alteration
RENOVATE CELLAR, 1ST & 2ND FLOOR FOR AN EXISTING 2 1/2 STORY, 2 FAMILY HOUSE. NEW PARTITION, DOOR & WINDOW WORK AS PER PLAN SUBMITTED. PLUMBING WORK TO BE FILED UNDER DOBNow APPLICATION#: Q00652522. NO CHANGE TO USE, EGRESS OR OCCUPANCY.
Q00652476-P1
03/01/2022
Special inspection requirement — Fire-Resistant Penetrations and Joints
Fran Huang
03/01/2022
Special inspection requirement — Energy Code Compliance Inspections
Fran Huang
03/01/2022
Special inspection requirement — Final
Fran Huang
03/01/2022
Special inspection requirement — Interior lighting power
Fran Huang
03/01/2022
Special inspection requirement — Air barrier - visual inspection
Fran Huang
03/01/2022
Special inspection requirement — Fenestration and door U-factor and product ratings
Fran Huang
03/01/2022
Special inspection requirement — Permanent certificate
Fran Huang
03/01/2022
Special inspection requirement — Fenestration air leakage
Fran Huang
02/10/2022
Filed — Alteration
FILE PLUMBING WORK IN-CONJUNCTION WITH DOBNow GENERAL CONSTRUCTION JOB#: Q00652476. CAP & REMOVE BOILER & HW HEATER AT CELLAR. INSTALL NEW & REPLACE PLUMBING FIXTURES AS PER PLAN SUBMITTED. NO CHANGE TO USE, EGRESS OR OCCUPANCY.
Q00652522-P1
02/10/2022
Special inspection requirement — Fire-Resistant Penetrations and Joints
Fran Huang
02/10/2022
Special inspection requirement — Energy Code Compliance Inspections
Fran Huang
02/10/2022
Special inspection requirement — HVAC-R and service water heating equipment
Fran Huang
02/10/2022
Special inspection requirement — HVAC-R and service water heating system controls
Fran Huang
02/10/2022
Special inspection requirement — HVAC-R and service water piping design and insulation
Fran Huang
02/10/2022
Special inspection requirement — Maintenance information
Fran Huang
02/09/2022
Permit issued — Plumbing
Q00652522-I1-PL
01/17/2022
Permit issued — General Construction
Q00652476-I1-GC
01/12/2022
Filed — Alteration
FILE PLUMBING WORK IN-CONJUNCTION WITH DOBNow GENERAL CONSTRUCTION JOB#: Q00652476. CAP & REMOVE BOILER & HW HEATER AT CELLAR. INSTALL NEW & REPLACE PLUMBING FIXTURES AS PER PLAN SUBMITTED. NO CHANGE TO USE, EGRESS OR OCCUPANCY.
Q00652522-I1
01/03/2022
Filed — Alteration
RENOVATE CELLAR, 1ST & 2ND FLOOR FOR AN EXISTING 2 1/2 STORY, 2 FAMILY HOUSE. NEW PARTITION, DOOR & WINDOW WORK AS PER PLAN SUBMITTED. PLUMBING WORK TO BE FILED UNDER DOBNow APPLICATION#: Q00652522. NO CHANGE TO USE, EGRESS OR OCCUPANCY.
Q00652476-I1
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingSigned-offNEW YORK STANDARD MECH CORP07/06/2022
DOB NOWPlumbingSigned-offNEW YORK STANDARD MECH CORP06/08/2022
DOB NOWPlumbingSigned-offNEW YORK STANDARD MECH CORP02/09/2022
DOB NOWGeneral ConstructionSigned-offST SAFETY CONS. INC01/17/2022
1 project · most recent 02/04/2022
General Wiring
FiledStatusContractorScope
02/04/2022CompleteA.C. MORGAN ELECTRICGeneral Wiring
▾Field Inspections (DOB CAP) — 3
DateTypeResultReport
07/06/2022Pass-Final PL - Up to 3 Requested FloorsPassView ↗
03/18/2022Certified Gas-Gas-Piping-RoughingCertifiedView ↗
03/18/2022Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 22
DateRequirementInspectorRole
03/04/2022Fire-Resistant Penetrations and JointsFran Huangspecial
03/04/2022FinalFran Huangprogress
03/04/2022Energy Code Compliance InspectionsFran Huangprogress
03/04/2022Fenestration and door U-factor and product ratingsFran Huangenergy_progress
03/04/2022Air barrier - visual inspectionFran Huangenergy_progress
03/04/2022Fenestration air leakageFran Huangenergy_progress
03/04/2022Permanent certificateFran Huangenergy_progress
03/04/2022Interior lighting powerFran Huangenergy_progress
03/01/2022Fire-Resistant Penetrations and JointsFran Huangspecial
03/01/2022Energy Code Compliance InspectionsFran Huangprogress
03/01/2022FinalFran Huangprogress
03/01/2022Interior lighting powerFran Huangenergy_progress
03/01/2022Air barrier - visual inspectionFran Huangenergy_progress
03/01/2022Fenestration and door U-factor and product ratingsFran Huangenergy_progress
03/01/2022Permanent certificateFran Huangenergy_progress
03/01/2022Fenestration air leakageFran Huangenergy_progress
02/10/2022Fire-Resistant Penetrations and JointsFran Huangspecial
02/10/2022Energy Code Compliance InspectionsFran Huangprogress
02/10/2022HVAC-R and service water heating equipmentFran Huangenergy_progress
02/10/2022HVAC-R and service water heating system controlsFran Huangenergy_progress
02/10/2022HVAC-R and service water piping design and insulationFran Huangenergy_progress
02/10/2022Maintenance informationFran Huangenergy_progress
▾Documents — 36 on file (BIS + DOB NOW)
▸Plans & Drawings4
▸DOB NOWPlans/Sketch4
08/26/2026Q00652522-I1Request digital key ↗
08/26/2026Q00652522-P1Request digital key ↗
08/26/2026Q00652476-P1Request digital key ↗
Showing 3 of 4 on file for this type
▸Seals & Professional Certifications26
▸DOB NOWProgress Inspector Seal & Signature19
09/01/2026Q00652476-P1Open ↗
09/01/2026Q00652476-P1Open ↗
09/01/2026Q00652476-P1Open ↗
Showing 3 of 19 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature4
08/26/2026Q00652522-P1Open ↗
08/26/2026Q00652522-I1Open ↗
08/26/2026Q00652476-I1Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature3
09/01/2026Q00652476-P1Open ↗
08/29/2026Q00652476-I1Open ↗
08/24/2026Q00652522-P1Open ↗
▸Environmental & Asbestos4
▸DOB NOWDEP ACP-5: Asbestos Assessment Report4
08/26/2026Q00652522-P1Open ↗
08/26/2026Q00652522-I1Open ↗
08/26/2026Q00652476-I1Open ↗
Showing 3 of 4 on file for this type
▸Energy Compliance2
▸DOB NOWEN2: As Built Energy Analysis2
08/13/2026Q00652476-I1Open ↗
08/13/2026Q00652522-I1Open ↗