| Owner | Filings | Most Recent |
|---|---|---|
| HKS CONSTRUCTION | 19 | 07/08/2026 |
| RELIABLE ENTERPRISES | 8 | 07/08/2026 |
| OWNERS REP | 4 | 03/22/2026 |
| 88 LINDEN EQUITIES LLC | 1 | 03/22/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 05/01/2025 | $28.0M | — | — → — | $465/sf building |
| 05/20/2015 | $2.1M | — | — → — | — not available |
| Firm | Filings | Most Recent |
|---|---|---|
| PAUL PERDEK, PROF. ENG. PLLC | 2 | 10/13/2021 |
| ENTHINK ENGINEERS LLC | 2 | 07/21/2021 |
| HAIDER ENGINEERING, P.E. | 3 | 04/19/2018 |
| Representative | Filings | Most Recent |
|---|---|---|
| AE DESIGN SOLUTION | 4 | 03/21/2026 |
| HAIDER ENGINEERING, P.E. | 3 | 03/21/2026 |
| HAIDER ENGINEERING P E | 3 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| RELIABLE ENTERPRISES INC | General Contractor | 19 | 07/08/2026 |
| ENDRE BANYA | Electrical | 6 | 03/21/2026 |
| TFK ELECTRIC CORP 004849 | General Contractor | 6 | 03/22/2026 |
| CORE SCAFFOLD SYSTEMS INC. | General Contractor | 3 | 03/21/2026 |
| HKS CONSTRUCTION CORP | General Contractor | 1 | 07/08/2026 |
| DOWNEY, CONOR | Electrical | 1 | 03/21/2026 |
| JOSEPH FRANKL | Electrical | 1 | 03/21/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Supported Scaffold | Signed-off | RELIABLE ENTERPRISES INC | 07/21/2021 |
| DOB NOW | Supported Scaffold | Signed-off | CORE SCAFFOLD SYSTEMS INC | 07/13/2021 |
| DOB NOW | Sidewalk Shed | Signed-off | RELIABLE ENTERPRISES INC | 06/25/2021 |
| DOB NOW | Supported Scaffold | Signed-off | RELIABLE ENTERPRISES INC | 06/11/2021 |
| DOB NOW | Sidewalk Shed | Signed-off | RELIABLE ENTERPRISES INC | 10/05/2020 |
| DOB NOW | Supported Scaffold | Signed-off | RELIABLE ENTERPRISES INC | 06/12/2020 |
| DOB NOW | Sidewalk Shed | Signed-off | HKS CONSTRUCTION CORP | 03/20/2019 |
| DOB NOW | Sidewalk Shed | Signed-off | RELIABLE ENTERPRISES INC | 03/07/2019 |
| DOB NOW | Supported Scaffold | Signed-off | RELIABLE ENTERPRISES INC | 02/01/2019 |
| DOB NOW | Supported Scaffold | Signed-off | RELIABLE ENTERPRISES INC | 05/09/2018 |
| DOB NOW | Sidewalk Shed | Signed-off | RELIABLE ENTERPRISES INC | 02/09/2018 |
| BIS | SD | ISSUED | MPI PLUMBING CORP | 03/04/2022 |
| BIS | — | ISSUED | TARGET CONSTRUCTION LLC | 03/04/2022 |
| BIS | EQ | ISSUED | TARGET CONSTRUCTION LLC | 01/24/2022 |
| BIS | — | ISSUED | TARGET CONSTRUCTION LLC | 03/04/2021 |
| BIS | SD | ISSUED | MPI PLUMBING CORP | 02/16/2021 |
| BIS | EQ | ISSUED | TARGET CONSTRUCTION LLC | 01/26/2021 |
| BIS | — | ISSUED | TARGET CONSTRUCTION LLC | 01/26/2021 |
| BIS | — | ISSUED | PRESTIGE CONSTRUCTION NY | 11/26/2019 |
| BIS | EQ | ISSUED | PRESTIGE CONSTRUCTION NY | 09/04/2019 |
| BIS | — | ISSUED | PRESTIGE CONSTRUCTION NY | 09/04/2019 |
| BIS | — | ISSUED | PRESTIGE CONSTRUCTION NY | 09/04/2019 |
| BIS | EQ | ISSUED | DAWNY CONSTRUCTION LTD | 08/30/2018 |
| BIS | SD | ISSUED | BRANCH PLUMBING LLC | 08/28/2018 |
| BIS | PL | ISSUED | BRANCH PLUMBING LLC | 08/28/2018 |
| BIS | — | ISSUED | DAWNY CONSTRUCTION LTD | 06/21/2018 |
| BIS | EQ | ISSUED | HKS CONSTRUCTION CORP | 04/09/2018 |
| BIS | SP | ISSUED | BRANCH PLUMBING LLC | 04/06/2018 |
| BIS | PL | ISSUED | THE PLBG & HTG SPECIALIST | 12/26/2017 |
| BIS | — | ISSUED | DAWNY CONSTRUCTION LTD | 09/14/2017 |
| BIS | — | ISSUED | DAWNY CONSTRUCTION LTD | 09/13/2017 |
| BIS | EQ | ISSUED | DAWNY CONSTRUCTION LTD | 09/06/2017 |
| BIS | — | ISSUED | DAWNY CONSTRUCTION LTD | 09/06/2017 |
| BIS | — | ISSUED | DAWNY CONSTRUCTION LTD | 09/06/2017 |
| BIS | — | ISSUED | DVIR MOG 18 INC | 08/01/2017 |
| BIS | — | ISSUED | DVIR MOG 18 INC | 08/01/2017 |
| BIS | EQ | ISSUED | DVIR MOG 18 INC | 06/21/2017 |
| BIS | — | ISSUED | DVIR MOG 18 INC | 06/21/2017 |
| BIS | — | ISSUED | DVIR MOG 18 INC | 06/21/2017 |
| BIS | — | RE-ISSUED | DAWNY CONSTRUCTION LTD | 06/16/2017 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 01/20/2023 | Complete | SOLAS ELECTRICAL CORP | — |
| 09/22/2022 | Complete | TFK ELECTRIC CORP | 67 meters, 67 new_meters |
| 09/21/2022 | Complete | TFK ELECTRIC CORP | General Wiring |
| 04/01/2022 | Complete | STAR ELEC'L CONTRACTORS C | — |
| 11/14/2019 | Complete | TFK ELECTRIC CORP | — |
| 10/22/2019 | Complete | WCK ELECTRIC CORP. | — |
| 02/04/2019 | Complete | RICHARD NEU | — |
| 07/10/2018 | Complete | QUEENSBORO ELEC'L CONTR'G | General Wiring |
| 05/11/2018 | Complete | 4000 ELECTRIC CORP | — |
| 02/27/2018 | Complete | QUEENSBORO ELEC'L CONTR'G | — |
| 02/09/2018 | Complete | WCK ELECTRIC CORP. | — |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 10/18/2021 | Final | Paul Perdek | progress |
| 06/24/2021 | Final | Sunil Saigal | progress |