| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/12/2026 | Permit Issued | ABCO-PEERLESS SPRKLR CORP | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/12/2026 | Signed-off | ASHLAND PLUMBING CORP | Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/14/2026 | Permit Issued | D&D ELECTL CONST CO INC | General Wiring |
| 02/10/2026 | Complete | RONAN ELECTRICAL LLC | General Wiring |
| 09/24/2024 | Complete | M.C. ELECTRICAL NY INC | General Wiring |
| 08/09/2024 | Complete | CRANA ELECTRIC, INC | General Wiring |
| 09/01/2022 | Complete | POLO ELECTRIC CORP. D/B/A | General Wiring |
| 03/18/2021 | Complete | LIVE WIRE ELECTRIC 1 LLC | General Wiring |
| 03/16/2021 | Complete | FREEDOM ELECTL & DATA INC | General Wiring, Lighting |
| 12/14/2020 | Complete | UPDATE SYSTEMS ELECTRICAL | General Wiring |
| 12/01/2020 | Complete | FREEDOM ELECTL & DATA INC | General Wiring |
| 09/13/2018 | Complete | V. VASS ELECTRIC CORP | — |
| 04/30/2018 | Permit Issued | JAM ELECTRICAL CORP | — |
| Owner | Filings | Most Recent |
|---|---|---|
| NORMANDY REALTY | 54 | 07/08/2026 |
| COLUMBIA PROPERTY TRUST | 7 | 07/08/2026 |
| OWNERS REP | 24 | 07/08/2026 |
| CANNON HILL CAPITAL PARTNERS | 37 | 07/08/2026 |
| NORMANDY REAL ESTATE PARTNERS | 70 | 03/22/2026 |
| PLAZA CONSTRUCTION | 5 | 03/22/2026 |
| TO THE OWNER OF | 2 | 03/22/2026 |
| NARMANDRX REAL ESTATE PAR | 1 | 03/22/2026 |
| CORE SCAFFOLD SYSTEMS | 11 | 03/22/2026 |
| HUDRUF REALTY LLC | 1 | 03/22/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| GENSLER | 5 | 06/24/2026 |
| ROBERT DERECTOR ASSOCIATES | 27 | 06/12/2026 |
| GILSANZ MURRAY STEFICEK LLP | 2 | 03/02/2026 |
| ADVANCED PROFESSIONAL ENGINEERING | 2 | 01/31/2025 |
| STUDIOS ARCHITECTURE | 2 | 12/05/2024 |
| TOHFAZ UDDIN PE PC | 2 | 07/27/2023 |
| MG ENGINEERING D.P.C. | 5 | 03/03/2023 |
| FOGARTY FINGER ARCHITECTURE PLLC | 2 | 02/15/2023 |
| KZ ENGINEERING, P.C | 7 | 03/01/2022 |
| CROSS ARCHITECTURE | 1 | 03/01/2022 |
| DESIMONE CONSULTING ENGINEERING | 2 | 10/02/2020 |
| DIRECT ACCESS EXPEDITING, INC | 1 | 01/28/2020 |
| Representative | Filings | Most Recent |
|---|---|---|
| RIZZO GROUP | 33 | 03/21/2026 |
| A1 EXPEDITING SERVICE CORP. | 10 | 03/21/2026 |
| SPRING SCAFFOLDING LLC | 4 | 03/21/2026 |
| SYNERGY BUILDING CONSULTANTS | 7 | 03/21/2026 |
| KADI DESIGN STUDIO | 3 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| CORE SCAFFOLD SYSTEMS INC. | General Contractor | 32 | 07/08/2026 |
| ICON INTERIORS INC | General Contractor | 25 | 07/08/2026 |
| JT MAGEN & COMPANY INC | General Contractor | 14 | 07/08/2026 |
| CLUNE CONSTRUCTION CO LP | General Contractor | 10 | 07/08/2026 |
| PAR PLUMBING CO., INC | Plumbing | 5 | 07/08/2026 |
| PAR FIRE PROTECTION LLC | Fire Protection | 5 | 07/08/2026 |
| FREEDOM ELECTL & DATA INC | Electrical | 3 | 03/22/2026 |
| ABCO-PEERLESS SPRKLR CORP | Fire Protection | 2 | 07/08/2026 |
| POLO ELECTRIC CORP. D/B/A | Electrical | 2 | 03/22/2026 |
| MEATHWAY CONTRACTING INC | General Contractor | 2 | 03/21/2026 |
| ASHLAND PLUMBING CORP | Plumbing | 2 | 07/08/2026 |
| MARTY ALLEN ELEC'L CO.,IN | Electrical | 1 | 03/21/2026 |
| CRANA ELECTRIC, INC | Electrical | 1 | 03/22/2026 |
| METROTECH MECHANICAL CORP | Plumbing | 1 | 07/08/2026 |
| SPRING SCAFFOLDING LLC | General Contractor | 1 | 07/08/2026 |
| ARMON MECHANICAL INC | Plumbing | 1 | 07/08/2026 |
| ARMON MECHANICAL INC | Fire Protection | 1 | 07/08/2026 |
| ABOVE ALL STORE FRONTS IN | General Contractor | 1 | 07/08/2026 |
| RULLO, ANTHONY | Electrical | 1 | 03/21/2026 |
| IMPACT PLUMBING INC | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| MILROSE CONSULTANTS LLC | 2003 | 8 | 06/24/2026 |
| STEEL CORE ENGINEERING PL | 1098 | 3 | 01/31/2025 |
| AMARACON TESTING & INSPEC | 5842 | 3 | 06/24/2024 |
| DOMANI INSPECTION SERVICE | 843 | 5 | 03/03/2023 |
| CODEGREEN | 510 | 18 | 09/07/2021 |
| CHEN ENGINEERING SERVICES | 1826 | 2 | 10/02/2020 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Permit Issued | ABCO-PEERLESS SPRKLR CORP | 04/03/2026 |
| DOB NOW | Plumbing | Signed-off | ASHLAND PLUMBING CORP | 03/31/2026 |
| DOB NOW | Structural | Signed-off | JT MAGEN & COMPANY INC | 03/10/2026 |
| DOB NOW | General Construction | Permit Issued | JT MAGEN & COMPANY INC | 03/10/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | JT MAGEN & COMPANY INC | 03/05/2026 |
| DOB NOW | General Construction | Permit Issued | JT MAGEN & COMPANY INC | 12/17/2025 |
| DOB NOW | Structural | Signed-off | JT MAGEN & COMPANY INC | 12/16/2025 |
| DOB NOW | General Construction | Permit Issued | JT MAGEN & COMPANY INC | 12/10/2024 |
| DOB NOW | General Construction | Signed-off | JT MAGEN & COMPANY INC | 09/24/2024 |
| DOB NOW | Mechanical Systems | Signed-off | JT MAGEN & COMPANY INC | 09/24/2024 |
| DOB NOW | Mechanical Systems | Signed-off | JT MAGEN & COMPANY INC | 06/25/2024 |
| DOB NOW | Plumbing | Signed-off | ASHLAND PLUMBING CORP | 06/24/2024 |
| DOB NOW | Plumbing | Signed-off | ABCO-PEERLESS SPRKLR CORP | 06/20/2024 |
| DOB NOW | General Construction | Signed-off | JT MAGEN & COMPANY INC | 06/13/2024 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | SPRING SCAFFOLDING LLC | 06/15/2023 |
| DOB NOW | Sprinklers | Signed-off | ARMON MECHANICAL INC | 03/27/2023 |
| DOB NOW | Plumbing | Signed-off | ARMON MECHANICAL INC | 02/27/2023 |
| DOB NOW | Mechanical Systems | Signed-off | CLUNE CONSTRUCTION CO LP | 02/24/2023 |
| DOB NOW | General Construction | Signed-off | CLUNE CONSTRUCTION CO LP | 02/17/2023 |
| DOB NOW | General Construction | Signed-off | CLUNE CONSTRUCTION CO LP | 02/17/2023 |
| DOB NOW | Mechanical Systems | Signed-off | CLUNE CONSTRUCTION CO LP | 02/09/2023 |
| DOB NOW | Construction Fence | Signed-off | CORE SCAFFOLD SYSTEMS INC | 08/23/2022 |
| DOB NOW | Plumbing | Signed-off | METROTECH MECHANICAL CORP | 04/07/2022 |
| DOB NOW | General Construction | Signed-off | MEATHWAY CONTRACTING INC | 03/14/2022 |
| DOB NOW | Supported Scaffold | Permit Issued | CORE SCAFFOLD SYSTEMS INC | 11/26/2021 |
| DOB NOW | Plumbing | Signed-off | IMPACT PLUMBING INC | 10/08/2021 |
| DOB NOW | Plumbing | Permit Issued | PAR PLUMBING CO., INC | 06/02/2021 |
| DOB NOW | Sprinklers | Signed-off | LAWRENCE J. LEVINE | 03/24/2021 |
| DOB NOW | Sprinklers | Signed-off | LAWRENCE J. LEVINE | 03/24/2021 |
| DOB NOW | Structural | Signed-off | ICON INTERIORS INC | 01/25/2021 |
| DOB NOW | Structural | Signed-off | ICON INTERIORS INC | 01/25/2021 |
| DOB NOW | Construction Fence | Signed-off | CORE SCAFFOLD SYSTEMS INC | 11/09/2020 |
| DOB NOW | Supported Scaffold | Permit Issued | CORE SCAFFOLD SYSTEMS INC | 11/09/2020 |
| DOB NOW | Sprinklers | Signed-off | LAWRENCE J. LEVINE | 10/08/2020 |
| DOB NOW | Plumbing | Signed-off | PAR PLUMBING CO., INC | 10/08/2020 |
| DOB NOW | Mechanical Systems | Signed-off | ICON INTERIORS INC | 09/25/2020 |
| DOB NOW | Sidewalk Shed | Signed-off | CORE SCAFFOLD SYSTEMS INC | 09/14/2020 |
| DOB NOW | Plumbing | Permit Issued | PAR PLUMBING CO., INC | 07/02/2020 |
| DOB NOW | Mechanical Systems | Permit Issued | ICON INTERIORS INC | 06/29/2020 |
| DOB NOW | Mechanical Systems | Signed-off | ICON INTERIORS INC | 06/29/2020 |
| Date | Type | Result | Report |
|---|---|---|---|
| 08/04/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 06/18/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 05/29/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 04/15/2026 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 04/10/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 05/19/2025 | Pass-Final General Construction Non-Directive 14 | Pass | View ↗ |
| 01/17/2025 | Fail-Final Curb Cut Non-Directive 14 | Fail | View ↗ |
| 12/19/2024 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 11/14/2024 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 10/26/2024 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 08/20/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 03/01/2024 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 02/27/2024 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 02/27/2024 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 09/26/2023 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 05/16/2022 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 04/29/2022 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 04/29/2022 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 12/15/2021 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 11/12/2021 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 11/12/2021 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 06/25/2026 | Mastic and Intumescent Fire-resistant Coatings | Christopher Drutjons | special |
| 06/25/2026 | Final | Stephanie Lan | progress |
| 06/25/2026 | Fire-Resistant Penetrations and Joints | Christopher Drutjons | special |
| 06/25/2026 | Sprayed fire-resistant materials | Christopher Drutjons | special |
| 02/04/2026 | Structural Steel - High Strength Bolting | Christopher Drutjons | special |
| 02/04/2026 | Final | Christopher Drutjons | progress |
| 02/04/2026 | Structural Steel - Welding | Christopher Drutjons | special |
| 02/04/2026 | Structural Cold-Formed Steel | Christopher Drutjons | special |
| 02/04/2026 | Structural Stability – Alterations of existing buildings | Christopher Drutjons | special |
| 02/04/2026 | Structural Steel - Details | Christopher Drutjons | special |
| 11/05/2025 | Sprayed fire-resistant materials | Christopher Drutjons | special |
| 11/05/2025 | Fire-Resistance Rated Construction | Christopher Drutjons | progress |
| 11/05/2025 | Post-installed Anchors | Christopher Drutjons | special |
| 11/05/2025 | Final | Christopher Drutjons | progress |
| 11/05/2025 | Fire-Resistant Penetrations and Joints | Christopher Drutjons | special |
| 11/05/2025 | Structural Stability – Alterations of existing buildings | Christopher Drutjons | special |
| 11/05/2025 | Structural Steel - Welding | Christopher Drutjons | special |
| 11/05/2025 | Structural Steel - High Strength Bolting | Christopher Drutjons | special |
| 11/05/2025 | Structural Steel - Details | Christopher Drutjons | special |
| 10/22/2025 | Final | Stephanie Lan | progress |
| 02/04/2025 | HVAC-R and service water piping design and insulation | Alexander Sheyman | energy_progress |
| 02/04/2025 | HVAC-R and service water heating system controls | Alexander Sheyman | energy_progress |
| 02/04/2025 | HVAC-R and service water heating equipment | Alexander Sheyman | energy_progress |
| 02/04/2025 | Energy Code Compliance Inspections | Alexander Sheyman | progress |
| 02/04/2025 | Fire-Resistant Penetrations and Joints | Alexander Sheyman | special |