Two stories - detached, small or mid-size
89-14 115 STREET
QUEENS · Richmond Hill · BIN 4195711
💬 Discuss this project
1920Year Built
2.5Stories
A1Building Class
R4AZoning
2,138 sfGross Floor Area
1Units
Two stories - detached, small or mid-size · 5,000 sf lot · 0.43 FAR built · Flood zone X
Locations of Work
ArchitectureElectricalPlumbingGeneral
Permit Issued — active, not yet Signed-off
Roof6p · 1 filing · 12 docs
Floor 2Under Construction11p · 1 filing · 20 docs
Floor 1Under Construction10p · 1 filing · 20 docs
CellarUnder Construction11p · 1 filing · 20 docs
Site & exteriorUnder Construction13p · 1 filing · 20 docs
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
04/13/2021$540K—Private party → Private party$253/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
PARKER AND WEST ENGINEERING, PLLC204/02/2026
ASKON ARCHITECTS, P.C.501/28/2026
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
SUNRUN103/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
BIG APPLE BUSINESS SOLGeneral Contractor308/04/2026
SUNRUN INSTALLATION SVCGeneral Contractor107/08/2026
TRI CITY MECHANICAL GROUP CORPPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
PARKER AND WEST ENGINEERI5272204/02/2026
ASKON ARCHITECT, P.C.3596401/28/2026
Building Lifecycle
All (51)Filed (7)Permit Issued (5)Signed Off (2)Objection (12)Special Inspection (25)
08/03/2026
Permit issued — General Construction
Q01057835-I1-GC
08/02/2026
Signed off — Alteration CO
FILING FOR CONSTRUCTION FENCE
Q01057835-S2
06/01/2026
Signed off — Alteration
FILING HEREWITH TAX ABATEMENT APPLICATION FOR INSTALLATION OF ROOF-MOUNTED SOLAR PANELS. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
Q01369778-I1
04/05/2026
Objection resolved — Open
04/05/2026
Objection resolved — Resolved
04/03/2026
Objection resolved — Resolved
04/03/2026
Objection resolved — Resolved
04/03/2026
Objection resolved — Resolved
04/02/2026
Filed — Alteration
FILING HEREWITH TAX ABATEMENT APPLICATION FOR INSTALLATION OF ROOF-MOUNTED SOLAR PANELS. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
Q01369778-P1
03/25/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
Walid Abdulla
03/25/2026
Special inspection requirement — Structural Stability – Alterations of existing buildings
Walid Abdulla
03/25/2026
Special inspection requirement — Energy Code Compliance Inspections
Walid Abdulla
03/25/2026
Special inspection requirement — Final
Walid Abdulla
03/25/2026
Special inspection requirement — Air barrier - visual inspection
Walid Abdulla
03/16/2026
Permit issued — Solar
Q01369778-I1-SL
03/13/2026
Objection raised — Cost
03/13/2026
Objection raised — Scope
03/13/2026
Objection raised — Admin
03/13/2026
Objection raised — Scope
03/13/2026
Objection raised — Scope
03/11/2026
Filed — Alteration
FILING HEREWITH TAX ABATEMENT APPLICATION FOR INSTALLATION OF ROOF-MOUNTED SOLAR PANELS. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
Q01369778-I1
01/28/2026
Filed — Alteration CO
FILING FOR CONSTRUCTION FENCE
Q01057835-P2
01/27/2026
Filed — Alteration CO
FILING FOR CONSTRUCTION FENCE
Q01057835-P1
01/16/2026
Special inspection requirement — Concrete - Cast-In-Place
Akeeb Shekoni
01/16/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
Akeeb Shekoni
01/16/2026
Special inspection requirement — Structural Stability – Alterations of existing buildings
Akeeb Shekoni
01/16/2026
Special inspection requirement — Energy Code Compliance Inspections
Akeeb Shekoni
01/16/2026
Special inspection requirement — Fire-Resistance Rated Construction
Akeeb Shekoni
01/16/2026
Special inspection requirement — Fenestration and door U-factor and product ratings
Akeeb Shekoni
01/16/2026
Special inspection requirement — Permanent certificate
Akeeb Shekoni
01/16/2026
Special inspection requirement — Electric vehicle service equipment requirements
Akeeb Shekoni
01/16/2026
Special inspection requirement — Maintenance information
Akeeb Shekoni
01/16/2026
Special inspection requirement — Fenestration areas
Akeeb Shekoni
01/16/2026
Special inspection requirement — Air barrier - visual inspection
Akeeb Shekoni
01/16/2026
Special inspection requirement — Fenestration air leakage
Akeeb Shekoni
01/16/2026
Special inspection requirement — Insulation placement and R values
Akeeb Shekoni
01/16/2026
Special inspection requirement — Metering
Akeeb Shekoni
01/16/2026
Special inspection requirement — Lighting in dwelling units
Akeeb Shekoni
09/10/2025
Permit issued — Plumbing
Q01057835-S1-PL
08/29/2025
Permit issued — General Construction
Q01057835-I1-GC
08/26/2025
Permit issued — Construction Fence
Q01057835-S2-FN
07/25/2025
Objection resolved — Addressed
07/21/2025
Objection raised — Plumbing
07/06/2025
Filed — Alteration CO
FILING FOR CONSTRUCTION FENCE
Q01057835-S1
07/03/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Akeeb Shekoni
07/03/2025
Special inspection requirement — Energy Code Compliance Inspections
Akeeb Shekoni
07/03/2025
Special inspection requirement — Maintenance information
Akeeb Shekoni
07/03/2025
Special inspection requirement — Metering
Akeeb Shekoni
07/03/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
Akeeb Shekoni
04/15/2025
Filed — Alteration CO
FILING FOR CONSTRUCTION FENCE
Q01057835-S2
06/17/2024
Filed — Alteration CO
FILING FOR CONSTRUCTION FENCE
Q01057835-I1
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWGeneral ConstructionPermit IssuedBIG APPLE BUSINESS SOL08/03/2026
DOB NOWSolarSigned-offSUNRUN INSTALLATION SVC03/16/2026
DOB NOWPlumbingPermit IssuedFLAVIO MECHANICAL CORP09/10/2025
DOB NOWGeneral ConstructionPermit IssuedBIG APPLE BUSINESS SOL08/29/2025
DOB NOWConstruction FenceSigned-offBIG APPLE BUSINESS SOL08/26/2025
1 project · most recent 01/28/2026
Gas Water/Sanitary
FiledStatusContractorScope
01/28/2026Permit IssuedTRI CITY MECHANICAL GROUPGas, Water/Sanitary
2 projects · most recent 03/25/2026
FiledStatusContractorScope
03/25/2026CompleteSUNRUN SOLAR ELECTL CORP—
12/09/2025Permit IssuedTRI-AN ELECTRIC. CONTRAT2 meters, 1 new_meters
1 project · most recent 04/02/2026
FiledStatusContractorScope
04/02/2026Signed-offSUNRUN INSTALLATION SVC48 panels, 20.48 kw, 504.48 roof_area_sqft
1 project · most recent 01/28/2026
Fence
FiledStatusContractorScope
01/28/2026Permit IssuedBIG APPLE BUSINESS SOLFence
▾Special Inspection Requirements (DOB NOW) — 25
DateRequirementInspectorRole
03/25/2026Fire-Resistant Penetrations and JointsWalid Abdullaspecial
03/25/2026Structural Stability – Alterations of existing buildingsWalid Abdullaspecial
03/25/2026Energy Code Compliance InspectionsWalid Abdullaprogress
03/25/2026FinalWalid Abdullaprogress
03/25/2026Air barrier - visual inspectionWalid Abdullaenergy_progress
01/16/2026Concrete - Cast-In-PlaceAkeeb Shekonispecial
01/16/2026Fire-Resistant Penetrations and JointsAkeeb Shekonispecial
01/16/2026Structural Stability – Alterations of existing buildingsAkeeb Shekonispecial
01/16/2026Energy Code Compliance InspectionsAkeeb Shekoniprogress
01/16/2026Fire-Resistance Rated ConstructionAkeeb Shekoniprogress
01/16/2026Fenestration and door U-factor and product ratingsAkeeb Shekonienergy_progress
01/16/2026Permanent certificateAkeeb Shekonienergy_progress
01/16/2026Electric vehicle service equipment requirementsAkeeb Shekonienergy_progress
01/16/2026Maintenance informationAkeeb Shekonienergy_progress
01/16/2026Fenestration areasAkeeb Shekonienergy_progress
01/16/2026Air barrier - visual inspectionAkeeb Shekonienergy_progress
01/16/2026Fenestration air leakageAkeeb Shekonienergy_progress
01/16/2026Insulation placement and R valuesAkeeb Shekonienergy_progress
01/16/2026MeteringAkeeb Shekonienergy_progress
01/16/2026Lighting in dwelling unitsAkeeb Shekonienergy_progress
07/03/2025Fire-Resistant Penetrations and JointsAkeeb Shekonispecial
07/03/2025Energy Code Compliance InspectionsAkeeb Shekoniprogress
07/03/2025Maintenance informationAkeeb Shekonienergy_progress
07/03/2025MeteringAkeeb Shekonienergy_progress
07/03/2025HVAC-R and service water piping design and insulationAkeeb Shekonienergy_progress
▾Documents — 47 on file (BIS + DOB NOW)
▸Plans & Drawings7
▸DOB NOWPlans/Sketch7
08/17/2026Q01057835-S1Request digital key ↗
08/17/2026Q01057835-I1Request digital key ↗
08/17/2026Q01057835-P2Request digital key ↗
Showing 3 of 7 on file for this type
▸Zoning, Tax Lot & Property Records4
▸DOB NOWZD1: DOB Zoning Diagram2
08/13/2026Q01057835-P1Open ↗
08/13/2026Q01057835-I1Open ↗
▸DOB NOWHouse Number Verification: TOPO Stamp2
08/13/2026Q01057835-P1Open ↗
08/13/2026Q01057835-I1Open ↗
▸Seals & Professional Certifications18
▸DOB NOWDPL-1: Design Professional Seal & Signature7
08/17/2026Q01057835-S1Open ↗
08/17/2026Q01057835-P2Open ↗
08/17/2026Q01057835-P1Open ↗
Showing 3 of 7 on file for this type
▸DOB NOWProgress Inspector Seal & Signature7
08/31/2026Q01369778-P1Open ↗
08/31/2026Q01369778-P1Open ↗
08/31/2026Q01369778-P1Open ↗
Showing 3 of 7 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature4
08/31/2026Q01369778-P1Open ↗
08/31/2026Q01369778-P1Open ↗
08/28/2026Q01057835-P1Open ↗
Showing 3 of 4 on file for this type
▸Safety & Tenant Protection2
▸DOB NOWStreet Tree Checklist2
08/13/2026Q01057835-P1Open ↗
08/13/2026Q01057835-I1Open ↗
▸Environmental & Asbestos7
▸DOB NOWDEP ACP-5: Asbestos Assessment Report7
08/17/2026Q01057835-P2Open ↗
08/17/2026Q01057835-P1Open ↗
08/17/2026Q01057835-S2Open ↗
Showing 3 of 7 on file for this type
▸Approvals, Objections & Sign-offs1
▸DOB NOWUtility Company Final Acceptance Letter1
08/17/2026Q01369778-I1Open ↗
▸Other Documents8
▸DOB NOWPlot Diagram2
08/13/2026Q01057835-I1Open ↗
08/13/2026Q01057835-P1Open ↗
▸DOB NOWSite Survey: Initial2
08/13/2026Q01057835-P1Open ↗
08/13/2026Q01057835-I1Open ↗
▸DOB NOWProperty Ownership Certification2
08/17/2026Q01057835-I1Open ↗
08/17/2026Q01057835-P1Open ↗
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone2
08/13/2026Q01057835-P1Open ↗
08/13/2026Q01057835-I1Open ↗