| Firm | Filings | Most Recent |
|---|---|---|
| CRICKET ARCHITECTS NJ LLC | 2 | 02/07/2025 |
| Representative | Filings | Most Recent |
|---|---|---|
| NAGAN EX CONSULTANTS | 4 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| DIKER A & V CONTRACTING C | General Contractor | 1 | 04/09/2026 |
| A & E MECHANICAL CORP | Plumbing | 1 | 07/08/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Signed-off | A & E MECHANICAL CORP | 08/18/2025 |
| DOB NOW | General Construction | Signed-off | DIKER A & V CONTRACTING C | 05/16/2025 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 02/07/2025 | Signed-off | A & E MECHANICAL CORP | Water/Sanitary |
| Date | Type | Result | Report |
|---|---|---|---|
| 08/18/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 05/21/2025 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 05/21/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 05/21/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 02/07/2025 | Final | ERROL MCINTOSH | progress |