← Back
Two family converted from one family
89-40 211 STREET
QUEENS · BIN 4225653
💬 Discuss this project
1935Year Built
2.5Stories
B3Building Class
R2Zoning
2,250 sfGross Floor Area
2Units
0 Open ViolationsFDNY Report ↗
Two family converted from one family · 4,306 sf lot · 0.52 FAR built · Flood zone X
Locations of Work
No floor-level scope or drawing coverage on file for this building.
1 job · most recent 04/28/2025
FiledStatusContractorScope
04/28/2025CompleteISLAND ELECTRIC CORP—
Building Lifecycle
All (9)Filed (1)Permit Issued (1)Signed Off (1)Violation (1)Special Inspection (5)
11/18/2025
Signed off — Alteration
INSTALLATION OF SOLAR PANELS, ROOFTOP, RAILED, GRID-TIED, 39 MODULES, 15.99KW
Q01216963-I1
04/30/2025
Permit issued — Solar
Q01216963-I1-SL
04/28/2025
Filed — Alteration
INSTALLATION OF SOLAR PANELS, ROOFTOP, RAILED, GRID-TIED, 39 MODULES, 15.99KW
Q01216963-I1
04/28/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Mina Makar
04/28/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
Mina Makar
04/28/2025
Special inspection requirement — Energy Code Compliance Inspections
Mina Makar
04/28/2025
Special inspection requirement — Final
Mina Makar
04/28/2025
Special inspection requirement — Air barrier - visual inspection
Mina Makar
06/06/2005
Violation issued (ECB, closed)
HPD
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
MOMENTUM SOLAR104/28/2025
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
MXV SIA LLC9281104/28/2025
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarSigned-offMOMENTUM SOLAR04/30/2025
BISPLISSUEDCITY TESTING & PLUMBING I08/05/2005
BISOTISSUEDN/A04/18/2005
▾Special Inspection Requirements (DOB NOW) — 5
DateRequirementInspectorRole
04/28/2025Fire-Resistant Penetrations and JointsMina Makarspecial
04/28/2025Structural Stability – Alterations of existing buildingsMina Makarspecial
04/28/2025Energy Code Compliance InspectionsMina Makarprogress
04/28/2025FinalMina Makarprogress
04/28/2025Air barrier - visual inspectionMina Makarenergy_progress
▾Documents — 7 on file (BIS + DOB NOW)
▸Plans & Drawings1
▸DOB NOWPlans/Sketch1
08/20/2026Q01216963-I1Request digital key ↗
▸Seals & Professional Certifications4
▸DOB NOWProgress Inspector Seal & Signature2
08/23/2026Q01216963-I1Open ↗
08/23/2026Q01216963-I1Open ↗
▸DOB NOWDPL-1: Design Professional Seal & Signature1
08/13/2026Q01216963-I1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature1
08/23/2026Q01216963-I1Open ↗
▸Environmental & Asbestos1
▸DOB NOWDEP ACP-5: Asbestos Assessment Report1
08/13/2026Q01216963-I1Open ↗
▸Approvals, Objections & Sign-offs1
▸DOB NOWUtility Company Final Acceptance Letter1
08/13/2026Q01216963-I1Open ↗