← Back
BuildNYC
BROOKLYN
Eighty Nine DeKalb
89 DEKALB AVENUE · Fort Greene · BIN 3429317
💬 Discuss this project
—Year Built
—Stories
—Building Class
—Zoning
—Gross Floor Area
—Units
2 Active Violations ▸FDNY Report ↗
Flood zone X
Locations of Work
ArchitectureStructuralElectricalMechanicalPlumbingFire ProtectionEquipmentCivilGeneral
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
Permit Issued — active, not yet Signed-off
Whole building & multi-floor projectsLong Island UniversityUnder Construction5 filings
RoofLong Island University3p · 3 filings
Floor 6Sprinkler Demolition2p · 2 filings
Floor 5Sprinkler Demolition2p · 2 filings
Floor 4Long Island University2p · 3 filings
Floor 3Long Island University2p · 3 filings
Floor 2Long Island University20p · 3 filings · 8 docs
Floor 1Long Island University24p · 10 filings · 8 docs
CellarLong Island University13p · 3 filings · 8 docs
Sub-CellarSprinkler Demolition2 filings · 5 docs
Sub-BasementSprinkler Demolition2 filings · 5 docs
Site & exteriorLong Island University7 filings
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
RXR Liu Pii Developer TRS20809/20/2026
▾Design Consultants (Architect / Engineer of Record)
▾Filing Representatives (Expediters)
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
TT MechanicalPlumbing4907/08/2026
LRC ConstructionGeneral Contractor4107/08/2026
Rael Automatic SprinklerPlumbing3603/22/2026
Arsenal ScaffoldScaffold1307/08/2026
Highbury ConcreteScaffold1207/08/2026
Suffolk Construction CompanyGeneral Contractor1207/08/2026
Rael Automatic Sprinkler CoFire Protection607/08/2026
LRC MaintanenceGeneral Contractor407/08/2026
Almar Plumbing & HeatingPlumbing307/08/2026
Hunter Roberts ConstructionGeneral Contractor304/09/2026
King InstallationScaffold309/09/2026
LRC ConstructionScaffold304/09/2026
Hunter Roberts ConstructionScaffold207/08/2026
TF ElectricalElectrical203/21/2026
Suffolk Construction CompanyScaffold203/21/2026
G.N.T. MechanicalFire Protection207/08/2026
Adam's European ContractingScaffold104/09/2026
LRC MaintanenceScaffold107/08/2026
With Pride Air ConditioningScaffold107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
Project Tactical Solution5859506/04/2026
Atlas ATC Engineering80111904/10/2026
PCS Engineering3745209/08/2025
Desimone Consulting Engineering5942806/25/2025
Lombardo Prof Engineering8566406/13/2025
Langan Engineering, Env, Surveyin1265509/10/2024
MJ Engineering & Design5546203/12/2024
Atlantic Engineeringlabor1381305/19/2022
H & O Engineering5595203/22/2022
Building Lifecycle
All (300)Filed (60)Permit Issued (80)Signed Off (29)Violation (22)Inspection (22)Objection (57)Special Inspection (30)
10/01/2026
Violation issued (ECB, open)
Cranes and Derricks
09/08/2026
Signed off — Alteration
Application for the installation and use of suspended scaffold as per plans filed herein. No change in egress, use, or occupancy.
B01173016-I1
09/08/2026
Permit issued — Suspended Scaffold
B01173016-I1-SC
09/04/2026
Objection raised — Scope
08/10/2026
Objection resolved — Resolved
08/10/2026
Objection resolved — Resolved
08/06/2026
Special inspection requirement — Structural Stability – Alterations of existing buildings
08/05/2026
Objection raised — Scope
08/05/2026
Objection raised — Scope
08/04/2026
Objection resolved — Resolved
08/03/2026
Objection raised — Fire_Protection
07/23/2026
Objection resolved — Addressed
07/23/2026
Objection resolved — Addressed
07/23/2026
Objection resolved — Addressed
07/23/2026
Objection resolved — Addressed
07/23/2026
Objection resolved — Addressed
07/23/2026
Objection resolved — Open
07/23/2026
Objection resolved — Open
07/23/2026
Objection resolved — Open
07/23/2026
Objection resolved — Open
06/30/2026
Objection resolved — Resolved
06/30/2026
Objection resolved — Resolved
06/30/2026
Objection resolved — Resolved
06/17/2026
Signed off — New Building
Sprinkler & Standpipe application filed subsequently with the new building application.
B00664860-S5
06/11/2026
Objection raised — Structural
06/11/2026
Objection raised — Scope
06/11/2026
Objection raised — Scope
06/11/2026
Objection raised — Inspections
06/11/2026
Objection raised — Admin
06/10/2026
Objection resolved — Resolved
06/10/2026
Objection resolved — Resolved
06/10/2026
Objection resolved — Resolved
06/08/2026
Objection raised — Structural
06/08/2026
Objection raised — Scope
06/05/2026
Objection raised — Scope
06/05/2026
Objection raised — Mechanical
06/05/2026
Objection raised — Scope
06/05/2026
Objection raised — Structural
06/05/2026
Objection raised — Structural
06/05/2026
Objection raised — Scope
06/05/2026
Objection raised — Structural
06/04/2026
Filed — Alteration
Alt. GC application filed to renovate existing cellar, first and second floors of the mixed use high rise building for high education use.
B01291865-S2
06/04/2026
Filed — Alteration
Alt. GC application filed to renovate existing cellar, first and second floors of the mixed use high rise building for high education use.
B01291865-S3
06/03/2026
Filed — Alteration
Alt. GC application filed to renovate existing cellar, first and second floors of the mixed use high rise building for high education use.
B01291865-S4
06/03/2026
Special inspection requirement — HVAC-R and service water heating system controls
Max Lee
06/03/2026
Special inspection requirement — Duct leakage testing, insulation and design
Max Lee
06/03/2026
Special inspection requirement — HVAC-R and service water heating equipment
Max Lee
06/03/2026
Special inspection requirement — Ventilation and air distribution system
Max Lee
06/03/2026
Special inspection requirement — HVAC-R and service water piping design and insulation
Max Lee
06/02/2026
Objection raised — Admin
05/29/2026
Signed off — Alteration
B01064062-I1
05/26/2026
Signed off — Alteration
TEMPORARY FIELD OFFICE
B01120114-I1
05/21/2026
Filed — Alteration
Alt. GC application filed to renovate existing cellar, first and second floors of the mixed use high rise building for high education use.
B01291865-S1
05/19/2026
Filed — Alteration
Alt. GC application filed to renovate existing cellar, first and second floors of the mixed use high rise building for high education use.
B01291865-I1
04/27/2026
Special inspection requirement — Tenant Protection Plan Compliance
Max Lee
04/10/2026
Filed — New Building
Sprinkler & Standpipe application filed subsequently with the new building application.
B00664860-B6
04/09/2026
Permit issued — General Construction
B00664860-I1-GC
04/07/2026
Signed off — Alteration
Fence application filed as per plan provided.
B00694442-I1
03/31/2026
Signed off — New Building
Sprinkler & Standpipe application filed subsequently with the new building application.
B00664860-S6
03/31/2026
Signed off — New Building
Sprinkler & Standpipe application filed subsequently with the new building application.
B00664860-S7
Latest 60 of 300 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSuspended ScaffoldSigned-offKing Installation09/08/2026
DOB NOWGeneral ConstructionPermit IssuedLRC Construction04/09/2026
DOB NOWSupport of ExcavationSigned-offLRC Construction03/02/2026
DOB NOWSuspended ScaffoldSigned-offKing Installation01/13/2026
DOB NOWStandpipeSigned-offRael Automatic Sprinkler Co12/02/2025
DOB NOWSprinklersSigned-offRael Automatic Sprinkler Co12/02/2025
DOB NOWMechanical SystemsSigned-offLRC Construction10/15/2025
DOB NOWCurb CutSigned-offLRC Construction09/05/2025
DOB NOWStructuralPermit IssuedLRC Construction07/10/2025
DOB NOWStructuralPermit IssuedLRC Construction04/16/2025
DOB NOWGeneral ConstructionPermit IssuedLRC Construction04/03/2025
DOB NOWSuspended ScaffoldSigned-offPoltech Wall Surfacing02/19/2025
DOB NOWPlumbingSigned-offTT Mechanical02/12/2025
DOB NOWSidewalk ShedSigned-offArsenal Scaffold02/10/2025
DOB NOWProtection and Mechanical MethodsSigned-offArsenal Scaffold02/10/2025
DOB NOWSupported ScaffoldSigned-offArsenal Scaffold02/10/2025
DOB NOWProtection and Mechanical MethodsSigned-offArsenal Scaffold02/10/2025
DOB NOWProtection and Mechanical MethodsSigned-offArsenal Scaffold02/10/2025
DOB NOWConstruction FenceSigned-offArsenal Scaffold02/10/2025
DOB NOWStandpipeSigned-offRael Automatic Sprinkler Co02/06/2025
DOB NOWGeneral ConstructionPermit IssuedLRC Construction02/05/2025
DOB NOWSuspended ScaffoldSigned-offKing Installation02/05/2025
DOB NOWConstruction FenceSigned-offLRC Construction01/16/2025
DOB NOWSprinklersSigned-offRael Automatic Sprinkler Co11/13/2024
DOB NOWStandpipeSigned-offRael Automatic Sprinkler Co11/13/2024
DOB NOWProtection and Mechanical MethodsSigned-offAdam's European Contracting11/12/2024
DOB NOWSuspended ScaffoldPermit IssuedVik XS Services09/10/2024
DOB NOWSupported ScaffoldSigned-offHighbury Concrete07/25/2024
DOB NOWProtection and Mechanical MethodsSigned-offHighbury Concrete07/25/2024
DOB NOWProtection and Mechanical MethodsSigned-offHighbury Concrete07/25/2024
DOB NOWProtection and Mechanical MethodsSigned-offHighbury Concrete07/24/2024
DOB NOWProtection and Mechanical MethodsSigned-offHighbury Concrete07/24/2024
DOB NOWProtection and Mechanical MethodsSigned-offWith Pride Air Conditioni06/14/2024
DOB NOWProtection and Mechanical MethodsSigned-offHighbury Concrete05/20/2024
DOB NOWProtection and Mechanical MethodsSigned-offHighbury Concrete04/05/2024
DOB NOWProtection and Mechanical MethodsSigned-offHighbury Concrete04/03/2024
DOB NOWStructuralPermit IssuedLRC Construction03/29/2024
DOB NOWFoundationSigned-offLRC Construction03/27/2024
DOB NOWPlumbingSigned-offAlmar Plumbing & Heating03/14/2024
DOB NOWSupported ScaffoldSigned-offHighbury Concrete03/13/2024
+ 23 more permits on file
2 projects · most recent 06/04/2026
Heating and Air Conditioning Systems Ventilation Systems Air Conditioning Systems Associated Ducts and Piping
FiledStatusContractorScopeMake / Model / Capacity
06/04/2026——Heating and Air Conditioning Systems, Ventilation Systems
Heat / Cool
Daikin REYQ96XBTJA 87,035 BTU · Vrf Outdoor ×4
RXTQ36TAVJ9 32,912 BTU · Vrf Outdoor ×3
REYQ120AATJB 97,462 BTU · Vrf Outdoor ×2
REYQ144AATJB 124,778 BTU · Vrf Outdoor ×2
REYQ144XBTJA 115,201 BTU · Vrf Outdoor ×2
REYQ72AATJB, REYQ72XBTJA 73,823 BTU · Vrf Outdoor ×2
REYQ120XBTJA 92,041 BTU · Vrf Outdoor ×1
REYQ168AATJB 126,288 BTU · Vrf Outdoor ×1
REYQ168XBTJA 125,522 BTU · Vrf Outdoor ×1
Ventilation
Daikin REYQ120XBTJA 106,750 BTU · Vrf Outdoor ×2
04/10/2026Permit IssuedLRC ConstructionAir Conditioning Systems, Associated Ducts and Piping, Heating and Air Conditioning Systems, Ventilation Systems
Cooling
Aaon RN-006 69,300 BTU · Rooftop Unit ×2
Heat / Cool
Daikin REYQ192AAYDA 344,000 BTU · Vrf Outdoor ×4
REYQ144XBYDA 276,000 BTU · Vrf Outdoor ×2
REYQ168XBYDA 156 BTU · Vrf Outdoor ×2
REYQ216AAYDA 206,000 BTU · Vrf Outdoor ×2
REYQ288XBYDA 276,000 BTU · Vrf Outdoor ×2
RXLQ240TAYDAX2 256,000 BTU · Vrf Outdoor ×1
RXYQ72AATJA 69,000 BTU · Vrf Outdoor ×2
Swegon CUSTOM GOLD F RX-060 284,000 BTU ×2
Custom GOLD F RX-060 479,000 BTU ×2
Ventilation
Greenheck SP-900 610 CFM · Exhaust Fan ×18
AX-113-533-0818-A500 40,000 CFM · Exhaust Fan ×4
AX-113-553-0809-A300 24,000 tons · Exhaust Fan ×4
BSQ-130HP 890 CFM · Exhaust Fan ×4
BSQ-140HP 400 CFM · Exhaust Fan ×2
BSQ-160HP 2,400 CFM · Exhaust Fan ×2
QEI-15 3,390 CFM · Exhaust Fan ×2
QEI-18 5,580 CFM · Exhaust Fan ×2
QEI-20 9,325 CFM · Exhaust Fan ×2
SQ-16-VG 4,000 CFM · Exhaust Fan ×2
SQ-99-VG 650 CFM · Exhaust Fan ×2
USF-13 1,820 CFM · Exhaust Fan ×2
Lf Systems DEF015 700 CFM · Exhaust Fan ×2
Ducts & Piping
__Junk__ Associated ducts and piping 1 BTU · Ductwork ×2
2 projects · most recent 06/04/2026
Sprinkler System
FiledStatusContractorScope
06/04/2026——Sprinkler System
04/10/2026Signed-offRael Automatic Sprinkler CoSprinkler System
2 projects · most recent 06/04/2026
Water/Sanitary Gas Storm
FiledStatusContractorScope
06/04/2026——Water/Sanitary
04/10/2026Signed-offTT MechanicalGas, Storm, Water/Sanitary
10 projects · most recent 08/13/2026
General Wiring
FiledStatusContractorScope
08/13/2026CompleteTF ElectricalGeneral Wiring
07/29/2026Permit IssuedS. J. ElectricGeneral Wiring
08/20/2024CompleteTF ElectricalGeneral Wiring
05/15/2024CompleteS. J. Electric—
03/28/2024CompleteS. J. Electric—
03/27/2024CompleteS. J. Electric—
03/27/2024CompleteS. J. Electric—
02/08/2024CompleteSolas Electrical—
02/08/2024CompleteSolas Electrical—
11/21/2023CompleteS. J. Electric1 meters, 1 new_meters
4 projects · most recent 06/04/2026
Concrete Steel Masonry
FiledStatusContractorScope
06/04/2026——Steel, Concrete, Masonry
04/10/2026Permit IssuedLRC ConstructionConcrete
06/25/2025Permit IssuedLRC ConstructionConcrete
05/19/2022Permit IssuedLRC Construction2 scope_items
1 project · most recent 09/10/2024
Scaffold
FiledStatusContractorScope
09/10/2024Permit IssuedVik XS ServicesScaffold
2 projects · most recent 06/13/2025
Suspended Scaffold (SC)
FiledStatusContractorScope
06/13/2025Signed-offKing InstallationSuspended Scaffold (SC)
09/10/2024Permit IssuedVik XS ServicesSuspended Scaffold (SC)
▾Field Inspections (DOB CAP) — 23
DateTypeResultReport
02/05/2026Pass-Final Curb Cut Non-Directive 14PassView ↗
12/10/2025Fail-Final Curb Cut Non-Directive 14FailView ↗
10/31/2025Pass-Final CND-Occupancy InspectionPassView ↗
10/01/2025Pass-Final CND-Occupancy InspectionPassView ↗
09/11/2025Certified StandPipe-SD-Piping-Hydrostatic TestCertifiedView ↗
09/10/2025Pass-Final CND-Occupancy InspectionPassView ↗
09/08/2025Pass-Final SD - Up to 3 Requested FloorsPassView ↗
07/29/2025Pass-Final SD - Fire PumpPassView ↗
07/28/2025Pass-Final SD - Fire PumpPassView ↗
07/22/2025Certified StandPipe-SD-Piping-Hydrostatic TestCertifiedView ↗
02/05/2025Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
01/15/2025Pass-Final PL - Up to 3 Requested FloorsPassView ↗
12/12/2024Pass-Final PL - Up to 3 Requested FloorsPassView ↗
11/18/2024Pass-Final PL - Up to 3 Requested FloorsPassView ↗
07/16/2024Pass-Final Curb Cut Non-Directive 14PassView ↗
05/06/2024Certified StandPipe - SD - Hydrostatic 63/09 Test (Initial 75 Feet)CertifiedView ↗
02/23/2024Pass-Final PL - UndergroundPassView ↗
02/02/2024Certified Storm Drainage-ST-Piping-UndergroundCertifiedView ↗
02/02/2024Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
12/14/2023Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
11/09/2023Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
01/09/2023Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
01/09/2023Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 150
DateRequirementInspectorRole
08/06/2026Structural Stability – Alterations of existing buildings—special
06/03/2026Duct leakage testing, insulation and designMax Leeenergy_progress
06/03/2026Ventilation and air distribution systemMax Leeenergy_progress
06/03/2026HVAC-R and service water heating equipmentMax Leeenergy_progress
06/03/2026HVAC-R and service water piping design and insulationMax Leeenergy_progress
06/03/2026HVAC-R and service water heating system controlsMax Leeenergy_progress
04/27/2026Tenant Protection Plan ComplianceMax Leespecial
03/31/2026Structural Steel - Details—special
03/31/2026Structural Cold-Formed Steel—special
03/31/2026Post-installed Anchors—special
03/31/2026Masonry—special
03/31/2026Concrete - Cast-In-Place—special
03/31/2026FinalMax Leeprogress
03/31/2026Mechanical SystemsMax Leespecial
03/31/2026Final—progress
03/31/2026Tenant Protection Plan Compliance—special
03/31/2026Structural Steel - Welding—special
03/31/2026Structural Steel - High Strength Bolting—special
03/01/2026FinalRONALD GRAPINprogress
03/01/2026Maintenance informationRONALD GRAPINenergy_progress
03/01/2026HVAC-R and service water heating system controlsRONALD GRAPINenergy_progress
03/01/2026HVAC-R and service water heating equipmentRONALD GRAPINenergy_progress
03/01/2026Shutoff dampersRONALD GRAPINenergy_progress
03/01/2026HVAC-R and service water piping design and insulationRONALD GRAPINenergy_progress
03/01/2026Ventilation and air distribution systemRONALD GRAPINenergy_progress
Latest 25 of 150.
▾Tenants in the building
TenantSpaceFloorsRenovation projects
Long Island UniversityEducationCellar, Floors 1–30
Project B01291865 Alteration · Objections · 05/19/2026
Project B01245804 Alteration · Permit Entire · 06/25/2025
Project B01030141 Alteration · LOC Issued · 04/04/2024
Project B01005875 Alteration · LOC Issued · 04/03/2024
Project B01005868 Alteration · LOC Issued · 03/08/2024
Project B00997524 Alteration · LOC Issued · 02/01/2024
Names are taken automatically from the text of each project’s filed documents (title blocks and cover sheets) and screened to exclude owners, landlords and designers. They may be incomplete or wrong; check the filing.
▾Documents — 307 on file (BIS + DOB NOW)
▸Plans & Drawings60
▸DOB NOWPlans/Sketch60
08/30/2026B00695483-I1Request digital key ↗
08/30/2026B00701198-I1Request digital key ↗
08/30/2026B00694442-I1Request digital key ↗
Showing 3 of 60 on file for this type
▸Applications & Permits21
▸BISPLAN / WORK APPROVAL APPLICATION13
12/17/2025322122065Open ↗
09/23/2025322122065Open ↗
11/20/2024340840095Open ↗
Showing 3 of 13 on file for this type
▸BISWORK PERMIT APPLICATION5
06/20/2011320040273Open ↗
01/19/2011320072050Open ↗
06/02/2010320040273Open ↗
Showing 3 of 5 on file for this type
▸BISBPP-5 - Authorization to the Department of Transportation3
01/02/2024340840095Open ↗
07/11/2023340840095Open ↗
03/23/2023340840095Open ↗
▸Zoning, Tax Lot & Property Records18
▸DOB NOWZD1: DOB Zoning Diagram8
08/13/2026B00664860-I1Open ↗
08/13/2026B00664860-B5Open ↗
08/13/2026B00664860-B2Open ↗
Showing 3 of 8 on file for this type
▸DOB NOWZoning Exhibit form (1-5)4
08/13/2026B00664860-B5Open ↗
Showing 1 of 4 on file for this type
▸BISTAX LOT: TENTATIVE LOT NUMBER ISSUED2
12/22/2025322122065Open ↗
03/23/2023340840095Open ↗
▸BISZONING EXHIBIT IV: CERTIFICATION1
12/22/2025322122065Open ↗
▸BISZONING EXHIBIT II: CERTIFICATION1
12/22/2025322122065Open ↗
▸BISZONING EXHIBIT III:DESC. & OWNRSHP.STMNT1
12/22/2025322122065Open ↗
▸DOB NOWHouse Number Verification: TOPO Stamp1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Seals & Professional Certifications136
▸DOB NOWDPL-1: Design Professional Seal & Signature59
08/30/2026B00695483-I1Open ↗
08/29/2026B00713108-I1Open ↗
08/27/2026B00885404-I1Open ↗
Showing 3 of 59 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature42
09/15/2026B00664860-S6Open ↗
09/02/2026B00664860-S3Open ↗
09/02/2026B00664860-S3Open ↗
Showing 3 of 42 on file for this type
▸DOB NOWProgress Inspector Seal & Signature29
09/15/2026B00664860-S6Open ↗
09/15/2026B00664860-S6Open ↗
09/02/2026B00664860-P1Open ↗
Showing 3 of 29 on file for this type
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION3
11/09/2009320072050Open ↗
09/23/2009320072050Open ↗
06/23/2009320040273Open ↗
▸BISAPPLICANT OWNER SIGNATURE1
04/18/2022340840095Open ↗
▸BISPROFESSIONAL CERTIFIED CHECKLIST1
06/23/2009320040273Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM1
06/23/2009320040273Open ↗
▸Trade Schedules & Equipment1
▸DOB NOWStandpipe Alarms Drawings1
08/15/2026B00664860-I1—
▸Safety & Tenant Protection7
▸DOB NOWStreet Tree Checklist4
08/24/2026B00664860-B2Open ↗
08/24/2026B00664860-A2Open ↗
08/15/2026B00664860-I1Open ↗
Showing 3 of 4 on file for this type
▸BISSTREET TREE CHECKLIST1
01/02/2024340840095Open ↗
▸DOB NOWStreet Trees Site Plan1
08/13/2026B00664860-I1Open ↗
▸DOB NOWParks Department Acknowledgment Letter for Street Trees Plan1
08/13/2026B00664860-I1Open ↗
▸Environmental & Asbestos2
▸BISASBESTOS EXEMPTION CERTIFICATION LETTER2
09/23/2009320072050Open ↗
06/23/2009320040273Open ↗
▸Energy Compliance3
▸DOB NOWPreliminary Commissioning Report Certification2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸DOB NOWEN2: As Built Energy Analysis1
08/15/2026B00664860-I1Open ↗
▸Inspections & Test Reports2
▸DOB NOWTR5 Test Report2
08/13/2026B00885404-I1Open ↗
Showing 1 of 2 on file for this type
▸Approvals, Objections & Sign-offs15
▸DOB NOWFee Exempt Supporting Document - DOF ACRIS report or BIB letter8
08/26/2026B00996101-I1Open ↗
08/26/2026B00996092-I1Open ↗
Showing 2 of 8 on file for this type
▸BISLETTERS - SUPPORTING DOCUMENTATION4
01/02/2024340840095Open ↗
09/25/2023340840095Open ↗
09/20/2023340840095Open ↗
Showing 3 of 4 on file for this type
▸BISADMINISTRATIVE OBJECTIONS1
06/23/2009320040273Open ↗
▸BISSHED LETTER1
06/20/2011320040273Open ↗
▸BISSCHEDULE A - OCCUPANCY / USE1
12/22/2025322122065Open ↗
▸Cost, Insurance & Ownership1
▸BISCOST AFFIDAVIT1
09/23/2009320072050Open ↗
▸Filing & Intake Forms12
▸BISADDITIONAL INFORMATION5
11/26/2024340840095Open ↗
01/02/2024340840095Open ↗
09/20/2023340840095Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWAI1 Form4
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 4 on file for this type
▸BISEFILING COVER SHEET2
09/23/2025322122065Open ↗
06/23/2009320040273Open ↗
▸BISEFILING JOB APPLICATION COVER SHEET1
04/18/2022340840095Open ↗
▸Other Documents29
▸DOB NOWManufacturer's Specifications7
08/24/2026B01011550-S1Open ↗
08/13/2026B01174906-P1Open ↗
08/13/2026B01174906-I1Open ↗
Showing 3 of 7 on file for this type
▸DOB NOWCalculations7
08/24/2026B01011550-S1Open ↗
08/13/2026B01174906-I1Open ↗
08/13/2026B01173016-P1Open ↗
Showing 3 of 7 on file for this type
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone4
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 4 on file for this type
▸DOB NOWProperty Ownership Certification4
08/24/2026B00664860-B2Open ↗
08/24/2026B00664860-A2Open ↗
08/15/2026B00664860-I1Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWSite Survey: Initial4
08/13/2026B00664860-I1Open ↗
08/13/2026B00664860-B2Open ↗
Showing 2 of 4 on file for this type
▸BISPLOT DIAGRAM1
10/24/2025322122065Open ↗
▸DOB NOWAdjoining Owners Notification1
08/13/2026B00664860-S4Open ↗
▸DOB NOWProject Specific General Liability (PGL1)1
08/13/2026B00664860-I1Open ↗