| Owner | Filings | Most Recent |
|---|---|---|
| ZHR | 6 | 07/08/2026 |
| IK DEVELOPMENT | 2 | 03/21/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 04/24/2025 | $1.4M | — | — → — | $1,015/sf building |
| 11/01/2023 | $922K | — | 89 GRANITE MANAGEMENT LLC → 89 GRANITE BPC HOLDINGS, LLC | $670/sf building |
| 09/16/2022 | $850K | — | Private party → 89 GRANITE MANAGEMENT LLC, | $618/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| J.K.DESIGN | 3 | 05/20/2024 |
| BGM ENGINEERING | 2 | 06/09/2022 |
| Representative | Filings | Most Recent |
|---|---|---|
| NYC PERMIT SERVICES | 4 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| TCS CONSTRUCTION CORP | General Contractor | 3 | 03/21/2026 |
| BEST MECHANICAL SVCS INC | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| STEEL CORE ENGINEERING PL | 1098 | 3 | 05/20/2024 |
| CENTURY TESTING & CONSULT | 4081 | 1 | 06/09/2022 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Signed-off | BEST MECHANICAL SVCS INC | 03/14/2024 |
| DOB NOW | Structural | Permit Issued | TCS CONSTRUCTION CORP | 02/23/2024 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 03/03/2024 | Complete | C & A ELECTRICAL CORP | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/20/2024 | Permit Issued | TCS CONSTRUCTION CORP | Wood |
| 06/09/2022 | — | — | 1 scope_items |
| 06/09/2022 | — | — | 1 scope_items |
| Date | Type | Result | Report |
|---|---|---|---|
| 11/19/2024 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 11/14/2024 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 08/22/2024 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 07/26/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 05/27/2024 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 03/22/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 05/28/2024 | Fenestration areas | Alexander Sheyman | energy_progress |
| 05/28/2024 | Permanent certificate | Alexander Sheyman | energy_progress |
| 05/28/2024 | Fenestration and door U-factor and product ratings | Alexander Sheyman | energy_progress |
| 05/28/2024 | Fenestration air leakage | Alexander Sheyman | energy_progress |
| 05/28/2024 | Interior lighting power | Alexander Sheyman | energy_progress |
| 05/28/2024 | Insulation placement and R values | Alexander Sheyman | energy_progress |
| 05/28/2024 | Fire-Resistant Penetrations and Joints | Alexander Sheyman | special |
| 05/28/2024 | Energy Code Compliance Inspections | Alexander Sheyman | progress |
| 05/28/2024 | Final | Alexander Sheyman | progress |
| 05/28/2024 | Fire-Resistance Rated Construction | Alexander Sheyman | progress |
| 05/28/2024 | Air barrier - visual inspection | Alexander Sheyman | energy_progress |
| 05/13/2024 | Insulation placement and R values | Alexander Sheyman | energy_progress |
| 05/13/2024 | Permanent certificate | Alexander Sheyman | energy_progress |
| 05/13/2024 | Fenestration air leakage | Alexander Sheyman | energy_progress |
| 05/13/2024 | Fenestration and door U-factor and product ratings | Alexander Sheyman | energy_progress |
| 05/13/2024 | Interior lighting power | Alexander Sheyman | energy_progress |
| 05/13/2024 | Fenestration areas | Alexander Sheyman | energy_progress |
| 05/13/2024 | Fire-Resistant Penetrations and Joints | Alexander Sheyman | special |
| 05/13/2024 | Energy Code Compliance Inspections | Alexander Sheyman | progress |
| 05/13/2024 | Final | Alexander Sheyman | progress |
| 05/13/2024 | Fire-Resistance Rated Construction | Alexander Sheyman | progress |
| 05/13/2024 | Air barrier - visual inspection | Alexander Sheyman | energy_progress |
| 03/01/2024 | Fire-Resistant Penetrations and Joints | Alexander Sheyman | special |
| 03/01/2024 | Energy Code Compliance Inspections | Alexander Sheyman | progress |
| 03/01/2024 | HVAC-R and service water heating system controls | Alexander Sheyman | energy_progress |