| Owner | Filings | Most Recent |
|---|---|---|
| Esrt | 23 | 10/13/2026 |
| Williamsburg Portfolio II | 20 | 03/21/2026 |
| J.crew Group | 9 | 03/22/2026 |
| L3 Capital | 8 | 07/08/2026 |
| Esrt 81-91 North 6th Street | 1 | 03/22/2026 |
| Degree Properties | 1 | 03/21/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 12/26/2019 | $14.4M | — | WILLIAMSBURG PORTFOLIO II, LLC → L3 89 N 6 LLC | $3,472/sf building |
| 03/13/2015 | $6.5M | — | 1155 DELI INC → WILLIAMSBURG PORTFOLIO II LLC | — not available |
| Firm | Filings | Most Recent |
|---|---|---|
| Studio Huji | 2 | 06/29/2026 |
| Interior Management | 2 | 06/14/2026 |
| Crown Architecture & Consulting | 4 | 05/07/2026 |
| KPFF Consulting Engineers | 1 | 04/09/2026 |
| HNY Consulting Engineers | 3 | 03/30/2026 |
| Building Studio Architects | 2 | 12/21/2021 |
| HC Engineering | 2 | 09/23/2019 |
| Representative | Filings | Most Recent |
|---|---|---|
| Archetype Consultants | 4 | 03/21/2026 |
| JP Expedite | 4 | 03/21/2026 |
| Crown Design Consulting | 6 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| Clune Construction Co | General Contractor | 5 | 08/30/2026 |
| Uni-Lite Electric | Electrical | 3 | 03/21/2026 |
| Paul A. Castrucci, Architects | Electrical | 3 | 03/21/2026 |
| Bray Stephen | Electrical | 3 | 03/21/2026 |
| Stephen Bray | Electrical | 3 | 03/21/2026 |
| BLZ Electric | Electrical | 2 | 03/21/2026 |
| Cavan Builders | General Contractor | 2 | 04/09/2026 |
| Uni-Lite Electric | General Contractor | 2 | 03/22/2026 |
| A1 Specialized | Sign hanger | 2 | 08/30/2026 |
| Signs Cad | Sign hanger | 2 | 07/08/2026 |
| Structure Tone | General Contractor | 1 | 07/08/2026 |
| A&A Plumbing | Plumbing | 1 | 07/08/2026 |
| Five Borough NYC | Fire Protection | 1 | 07/08/2026 |
| BLZ Electric | General Contractor | 1 | 03/22/2026 |
| Plumbing Works | Fire Protection | 1 | 07/04/2026 |
| Kenneth Park | Electrical | 1 | 03/21/2026 |
| G Builders V | General Contractor | 1 | 03/22/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| Codegreen | 510 | 4 | 05/07/2026 |
| AK Engineering | 678 | 4 | 03/30/2026 |
| Alan D Marcus, PE | 1761 | 1 | 09/18/2019 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Permit Issued | Clune Construction Co | 08/28/2026 |
| DOB NOW | Sign | Signed-off | Mad Signs | 08/28/2026 |
| DOB NOW | Sign | Signed-off | Mad Signs | 08/27/2026 |
| DOB NOW | General Construction | Permit Issued | Clune Construction Co | 08/18/2026 |
| DOB NOW | Sprinklers | Permit Issued | Plumbing Works | 07/02/2026 |
| DOB NOW | Plumbing | Permit Issued | A&A Plumbing | 06/08/2026 |
| DOB NOW | General Construction | Permit Issued | Clune Construction Co | 05/18/2026 |
| DOB NOW | Structural | Permit Issued | Clune Construction Co | 05/08/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | Clune Construction Co | 05/07/2026 |
| DOB NOW | General Construction | Signed-off | Cavan Builders | 02/25/2026 |
| DOB NOW | Structural | Signed-off | Cavan Builders | 02/13/2026 |
| DOB NOW | Sprinklers | Signed-off | Five Borough NYC | 02/12/2026 |
| DOB NOW | Mechanical Systems | Signed-off | Structure Tone | 09/11/2020 |
| DOB NOW | Sign | Signed-off | Signs Cad | 09/24/2019 |
| DOB NOW | Sign | Signed-off | Signs Cad | 09/24/2019 |
| BIS | PL | ISSUED | Pace Plumbing | 10/04/2018 |
| BIS | — | ISSUED | G Builders V | 07/27/2018 |
| BIS | — | ISSUED | G Builders V | 07/27/2018 |
| BIS | PL | ISSUED | Pace Plumbing | 08/24/2017 |
| BIS | — | ISSUED | G Builders V | 07/25/2017 |
| BIS | — | ISSUED | G Builders V | 07/25/2017 |
| BIS | — | ISSUED | G Builders V | 07/12/2017 |
| BIS | — | ISSUED | G Builders V | 07/12/2017 |
| BIS | EQ | ISSUED | Spring Scaffolding | 06/13/2017 |
| BIS | EQ | ISSUED | Spring Scaffolding | 06/13/2017 |
| BIS | EQ | ISSUED | Spring Scaffolding | 06/13/2017 |
| BIS | EQ | ISSUED | Spring Scaffolding | 06/13/2017 |
| BIS | SP | ISSUED | SKH Mechanical | 05/12/2017 |
| BIS | EQ | ISSUED | Brenmac | 02/07/2017 |
| BIS | EQ | ISSUED | Brenmac | 01/20/2017 |
| BIS | — | ISSUED | Disano Demolition Co | 01/13/2017 |
| BIS | EQ | ISSUED | Disano Demolition Co | 01/11/2017 |
| BIS | OT | ISSUED | G Builders V | 07/26/2016 |
| BIS | MH | ISSUED | Procold | 08/18/2011 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 04/09/2026 | Permit Issued | Clune Construction Co | Ventilation Systems | Ventilation Greenheck SQ-98-VG 200 CFM · Exhaust Fan ×1 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/09/2026 | Permit Issued | Bluewater P&H | Sprinkler System |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/09/2026 | Permit Issued | A&A Plumbing | Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/19/2026 | Permit Issued | A Electrical Main Service | — |
| 06/08/2026 | Permit Issued | Epic Electric | General Wiring |
| 03/15/2021 | Complete | BLZ Electric | General Wiring |
| 08/23/2019 | Complete | Uni-Lite Electric | General Wiring, Lighting |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/09/2026 | Permit Issued | Clune Construction Co | 1 scope_items |
| Date | Type | Result | Report |
|---|---|---|---|
| 09/24/2026 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 09/14/2026 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 08/13/2026 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 05/15/2026 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 05/13/2026 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 05/13/2026 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 06/29/2026 | Final | Ryan Hung | progress |
| 06/29/2026 | Final | Ryan Hung | progress |
| 05/07/2026 | Sprinkler Systems | HATIM ELSAID | special |
| 05/04/2026 | Sprinkler Systems | HATIM ELSAID | special |
| 03/31/2026 | Final | Ari Kamo | progress |
| 03/28/2026 | Post-installed Anchors | Ari Kamo | special |
| 03/28/2026 | Fire-Resistant Penetrations and Joints | Ari Kamo | special |
| 03/28/2026 | Fire-Resistant Penetrations and Joints | Ari Kamo | special |
| 03/28/2026 | Post-installed Anchors | Ari Kamo | special |
| 03/27/2026 | Lighting controls | Ari Kamo | energy_progress |
| 03/27/2026 | Fire-Resistant Penetrations and Joints | Ari Kamo | special |
| 03/27/2026 | Post-installed Anchors | Ari Kamo | special |
| 03/27/2026 | Interior lighting power | Ari Kamo | energy_progress |
| 03/24/2026 | Mechanical Systems | Ari Kamo | special |
| 03/24/2026 | Sprinkler Systems | Ari Kamo | special |
| 03/24/2026 | Final | Ari Kamo | progress |
| 03/13/2026 | Fire-Resistant Penetrations and Joints | Ari Kamo | special |
| 03/13/2026 | Fire-Resistance Rated Construction | Ari Kamo | progress |
| 03/05/2026 | Final | Stephen Furnstahl | progress |
| 12/22/2025 | Structural Stability – Alterations of existing buildings | HATIM ELSAID | special |
| 12/22/2025 | Energy Code Compliance Inspections | HATIM ELSAID | progress |
| 12/22/2025 | Final | HATIM ELSAID | progress |
| 12/22/2025 | Fire-Resistance Rated Construction | HATIM ELSAID | progress |
| 12/22/2025 | Final | HATIM ELSAID | progress |
| 12/22/2025 | Structural Steel - Welding | HATIM ELSAID | special |
| Tenant | Space | Floors | Renovation projects |
|---|---|---|---|
| Tecovas | Retail | Floors 1, 2 | Project B01403238 Project B01367993 |
| J.Crew Group | Retail | Floor 1 | Project B00229927 Project B00229960 |
| J.Crew / Madewell | Retail | Floor 1 | Project B00226029 |