| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 06/16/2021 | $1.7M | — | Private party → 89 OCEAN COURT LLC. | $493/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| GARFINKEL ARCHITECT, PLLC | 10 | 11/25/2025 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| G BUILDERS MANAGEMENT INC | General Contractor | 17 | 07/08/2026 |
| AL PLUMBING & CONT. INC | Plumbing | 1 | 07/08/2026 |
| INFINITI ESC PLUMBING COR | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| AZ PROFESSIONAL ENGINEERI | 766 | 6 | 11/25/2025 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Signed-off | INFINITI ESC PLUMBING COR | 09/16/2024 |
| DOB NOW | Construction Fence | Signed-off | G BUILDERS MANAGEMENT INC | 04/16/2024 |
| DOB NOW | Foundation | Permit Issued | G BUILDERS MANAGEMENT INC | 04/16/2024 |
| DOB NOW | Plumbing | Signed-off | AL PLUMBING & CONT. INC | 06/01/2023 |
| DOB NOW | Construction Fence | Signed-off | G BUILDERS MANAGEMENT INC | 05/17/2023 |
| DOB NOW | Structural | Permit Issued | G BUILDERS MANAGEMENT INC | 05/17/2023 |
| DOB NOW | Earth Work | Permit Issued | G BUILDERS MANAGEMENT INC | 11/22/2022 |
| DOB NOW | Structural | Permit Issued | G BUILDERS MANAGEMENT INC | 06/08/2022 |
| DOB NOW | Construction Fence | Signed-off | G BUILDERS MANAGEMENT INC | 05/20/2022 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 11/25/2025 | Signed-off | INFINITI ESC PLUMBING COR | Gas, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/09/2025 | Complete | KINGS ELECTRIC CO., INC. | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 11/25/2025 | Signed-off | INFINITI ESC PLUMBING COR | Concrete, Wood |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 11/25/2025 | Signed-off | INFINITI ESC PLUMBING COR | Earthwork |
| Date | Type | Result | Report |
|---|---|---|---|
| 10/01/2024 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 09/27/2024 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 10/19/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 09/20/2023 | Fail-Final PL - Up to 3 Requested Floors | Fail | View ↗ |
| 06/08/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 06/08/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 11/25/2025 | Exterior Insulation and Finish Systems (EIFS) | VIJAY KUMAR | special |
| 11/25/2025 | Energy Code Compliance Inspections | VIJAY KUMAR | progress |
| 11/25/2025 | Subgrade Inspections | VIJAY KUMAR | special |
| 11/25/2025 | Structural Stability – Alterations of existing buildings | VIJAY KUMAR | special |
| 11/25/2025 | Concrete - Cast-In-Place | VIJAY KUMAR | special |
| 11/25/2025 | Excavations - Sheeting, Shoring, and Bracing | VIJAY KUMAR | special |
| 11/25/2025 | Fire-Resistant Penetrations and Joints | VIJAY KUMAR | special |
| 11/25/2025 | Fenestration and door U-factor and product ratings | VIJAY KUMAR | energy_progress |
| 11/25/2025 | Metering | VIJAY KUMAR | energy_progress |
| 11/25/2025 | HVAC-R and service water piping design and insulation | VIJAY KUMAR | energy_progress |
| 11/25/2025 | Interior lighting power | VIJAY KUMAR | energy_progress |
| 11/25/2025 | Air barrier - visual inspection | VIJAY KUMAR | energy_progress |
| 11/25/2025 | Fenestration areas | VIJAY KUMAR | energy_progress |
| 11/25/2025 | Electric vehicle service equipment requirements | VIJAY KUMAR | energy_progress |
| 11/25/2025 | Fenestration air leakage | VIJAY KUMAR | energy_progress |
| 11/25/2025 | Insulation placement and R values | VIJAY KUMAR | energy_progress |
| 11/25/2025 | Maintenance information | VIJAY KUMAR | energy_progress |
| 11/25/2025 | Structural Wood Frame | VIJAY KUMAR | progress |
| 11/25/2025 | Lowest Floor Elevation | VIJAY KUMAR | progress |
| 11/25/2025 | Footing and Foundation | VIJAY KUMAR | progress |
| 11/25/2025 | Fire-Resistance Rated Construction | VIJAY KUMAR | progress |
| 11/25/2025 | Final | VIJAY KUMAR | progress |
| 05/16/2025 | HVAC-R and service water heating equipment | LEWIS GARFINKEL | energy_progress |
| 05/16/2025 | HVAC-R and service water heating system controls | LEWIS GARFINKEL | energy_progress |
| 05/16/2025 | Energy Code Compliance Inspections | LEWIS GARFINKEL | progress |