← Back
BuildNYC
Miscellaneous one family
89 SOUTH PORTLAND AVENUE
BROOKLYN · Fort Greene · BIN 3059311
💬 Discuss this project
1899Year Built
3Stories
A9Building Class
R6BZoning
2,250 sfGross Floor Area
1Units
Rent Stabilized9 Active Violations ▸FDNY Report ↗
Miscellaneous one family · Owner of record: 89 SP Ave · 1,875 sf lot · 1.2 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralElectricalMechanicalPlumbingFire ProtectionGeneral
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
Permit Issued — active, not yet Signed-off
RoofRoof mounted photovoltaic system installationUnder Construction13p · 2 filings · 20 docs
Floor 3Under Construction13p · 1 filing · 20 docs
Floor 2Under Construction13p · 1 filing · 20 docs
Floor 1Under Construction13p · 1 filing · 20 docs
CellarRoof mounted photovoltaic system installationUnder Construction13p · 2 filings · 20 docs
BasementUnder Construction14p · 1 filing · 20 docs
Sub-BasementUnder Construction13p · 1 filing · 20 docs
Site & exteriorPipe scaffolding installationUnder Construction13p · 3 filings · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
89 SPA4111/14/2026
Frank Minaudo Trust203/21/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
01/23/2024$2.3M—FRANK MINAUDO TRUST → 89 SP AVE LLC$1,040/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
Sharon Associates1011/13/2026
Eric Safyan Architect306/10/2026
NY Building Associates109/29/2025
Bangash Associates109/10/2025
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
BMB Building Consulting1603/21/2026
Joseph Fellner203/21/2026
Green Studio203/21/2026
Brooklyn Solarworks103/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
TumenGeneral Contractor607/08/2026
TumenScaffold407/08/2026
XH&RC Plumbing and Heatingspecialty_contractor307/08/2026
Tumenspecialty_contractor203/21/2026
Tumenspecialty_contractor403/21/2026
Ace Group NYScaffold104/08/2026
Brooklyn Solarworksspecialty_contractor104/09/2026
Brookyln SolarworksElectrical103/22/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
D&E Build Evergreen I93421311/13/2026
NKM Engineering6244209/29/2025
Building Lifecycle
11/13/2026
Filed — Alteration CO
Propose plumbing scope of work as per plan filed in conjunction with Alt-CO # B01026202-I1.
B01026202-P5
09/02/2026
Permit expired, never signed off — General Construction
The city's record still shows this permit as issued, with no sign-off on its filing
B01026202-I1-GC
08/10/2026
Signed off — Alteration CO
Propose plumbing scope of work as per plan filed in conjunction with Alt-CO # B01026202-I1.
B01026202-S6
08/10/2026
Signed off — Alteration
B01118202-I1
08/05/2026
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
115 history events on file for this building. Sign in free to see the full history. Sign in · Create account
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingPermit IssuedXH&RC Plumbing and Heating04/28/2026
DOB NOWSolarSigned-offBrooklyn Solarworks10/01/2025
DOB NOWSupported ScaffoldSigned-offAce Group NY09/11/2025
DOB NOWSprinklersSigned-offXH&RC Plumbing and Heating09/03/2025
DOB NOWGeneral ConstructionPermit IssuedTumen09/02/2025
DOB NOWConstruction FenceSigned-offTumen08/27/2025
DOB NOWMechanical SystemsSigned-offTumen08/27/2025
DOB NOWPlumbingPermit IssuedXH&RC Plumbing and Heating02/24/2025
DOB NOWStructuralSigned-offTumen02/11/2025
DOB NOWSupport of ExcavationSigned-offTumen12/27/2024
DOB NOWMechanical SystemsSigned-offTumen12/02/2024
DOB NOWGeneral ConstructionPermit IssuedTumen10/18/2024
DOB NOWConstruction FenceSigned-offTumen10/15/2024
1 project · most recent 11/13/2026
Heating and Air Conditioning Systems Ventilation Systems
FiledStatusContractorScope
11/13/2026Permit IssuedTumenHeating and Air Conditioning Systems, Ventilation Systems
1 project · most recent 11/13/2026
Sprinkler System
FiledStatusContractorScope
11/13/2026Signed-offXH&RC Plumbing and HeatingSprinkler System
1 project · most recent 11/13/2026
Storm Water/Sanitary
FiledStatusContractorScope
11/13/2026Permit IssuedXH&RC Plumbing and HeatingStorm, Water/Sanitary
2 projects · most recent 10/08/2025
General Wiring
FiledStatusContractorScope
10/08/2025CompleteA.M.J. ElectricGeneral Wiring
09/24/2025CompleteBrookyln Solarworks—
1 project · most recent 11/13/2026
Steel Concrete Masonry
FiledStatusContractorScope
11/13/2026Permit IssuedXH&RC Plumbing and HeatingSteel, Concrete, Masonry
1 project · most recent 09/29/2025
FiledStatusContractorScope
09/29/2025Signed-offBrooklyn Solarworks—
▾Field Inspections (DOB CAP) — 6
DateTypeResultReport
08/05/2026Pass-Final CND-Occupancy InspectionPassView ↗
04/27/2026Pass-Final SP - Up to 3 Requested FloorsPassView ↗
11/17/2025Certified Storm Drainage-ST-Piping-RoughingCertifiedView ↗
11/17/2025Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
11/17/2025Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
03/14/2025Certified Storm Drainage-ST-Piping-UndergroundCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 64
DateRequirementInspectorRole
07/20/2026Post-installed AnchorsDanny Chenspecial
07/20/2026HVAC-R and service water heating system controlsDanny Chenenergy_progress
07/20/2026HVAC-R and service water piping design and insulationDanny Chenenergy_progress
07/20/2026Maintenance informationDanny Chenenergy_progress
07/20/2026HVAC-R and service water heating equipmentDanny Chenenergy_progress
07/20/2026Energy Code Compliance InspectionsDanny Chenprogress
07/20/2026Fire-Resistant Penetrations and JointsDanny Chenspecial
07/07/2026HVAC-R and service water piping design and insulationDanny Chenenergy_progress
07/07/2026Maintenance informationDanny Chenenergy_progress
07/07/2026HVAC-R and service water heating equipmentDanny Chenenergy_progress
07/07/2026Fire-Resistant Penetrations and JointsDanny Chenspecial
07/07/2026Post-installed AnchorsDanny Chenspecial
07/07/2026Energy Code Compliance InspectionsDanny Chenprogress
07/07/2026HVAC-R and service water heating system controlsDanny Chenenergy_progress
05/28/2026Insulation placement and R valuesDanny Chenenergy_progress
05/28/2026Exterior lighting powerDanny Chenenergy_progress
05/28/2026Lighting in dwelling unitsDanny Chenenergy_progress
05/28/2026Fenestration air leakageDanny Chenenergy_progress
05/28/2026Fenestration and door U-factor and product ratingsDanny Chenenergy_progress
05/28/2026Fenestration areasDanny Chenenergy_progress
05/28/2026Fire-Resistant Penetrations and JointsDanny Chenspecial
05/28/2026Structural Stability – Alterations of existing buildingsDanny Chenspecial
05/28/2026Energy Code Compliance InspectionsDanny Chenprogress
05/28/2026Fire-Resistance Rated ConstructionDanny Chenprogress
05/28/2026Protection of exposed foundation insulationDanny Chenenergy_progress
Latest 25 of 64.
93 filed documents on file for this building. Sign in free to see the full history. Sign in · Create account