← Back
Miscellaneous two family
898 EAST 58 STREET
BROOKLYN · Flatlands · BIN 3214890
💬 Discuss this project
1960Year Built
3Stories
B9Building Class
R3-2Zoning
2,500 sfGross Floor Area
2Units
Miscellaneous two family · 2,050 sf lot · 1.22 FAR built · Flood zone X500
Locations of Work
ArchitectureElectrical
Roof3p · 1 filing · 9 docs
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
TOM PETERSEN ARCHITECT, LLC112/22/2023
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
CENTURION SOLAR ENERGYGeneral Contractor303/21/2026
BERGER QUALITY ELEC'L CONElectrical103/22/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
THOMAS PETERSEN ARCHITECT7854112/22/2023
Building Lifecycle
All (12)Filed (1)Permit Issued (1)Signed Off (1)Objection (4)Special Inspection (5)
04/24/2024
Signed off — Alteration
SCOPE OF WORK IS SOLELY FOR THE INSTALLATION OF THE SOLAR ELECTRONIC GENERATING SYSTEM. ALL OTHER WORK IS NOT TO BE RELIED UPON AS BEING APPROVED AND/OR PERMITTED BY THE NYC DEPARTMENT OF BUILDINGS.*NO CHANGE TO USE, EGRESS, OR OCCUPANCY.*
B00981016-I1
01/24/2024
Permit issued — Solar
B00981016-I1-SL
01/17/2024
Objection resolved — Addressed
01/15/2024
Objection resolved — Addressed
12/26/2023
Objection raised — Other
12/26/2023
Objection raised — Other
12/22/2023
Filed — Alteration
SCOPE OF WORK IS SOLELY FOR THE INSTALLATION OF THE SOLAR ELECTRONIC GENERATING SYSTEM. ALL OTHER WORK IS NOT TO BE RELIED UPON AS BEING APPROVED AND/OR PERMITTED BY THE NYC DEPARTMENT OF BUILDINGS.*NO CHANGE TO USE, EGRESS, OR OCCUPANCY.*
B00981016-I1
12/21/2023
Special inspection requirement — Fire-Resistant Penetrations and Joints
TOM PETERSEN
12/21/2023
Special inspection requirement — Structural Stability – Alterations of existing buildings
TOM PETERSEN
12/21/2023
Special inspection requirement — Energy Code Compliance Inspections
TOM PETERSEN
12/21/2023
Special inspection requirement — Final
TOM PETERSEN
12/21/2023
Special inspection requirement — Air barrier - visual inspection
TOM PETERSEN
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarSigned-offCENTURION SOLAR ENERGY01/24/2024
1 project · most recent 01/05/2024
FiledStatusContractorScope
01/05/2024CompleteBERGER QUALITY ELEC'L CON—
▾Special Inspection Requirements (DOB NOW) — 5
DateRequirementInspectorRole
12/21/2023Fire-Resistant Penetrations and JointsTOM PETERSENspecial
12/21/2023Structural Stability – Alterations of existing buildingsTOM PETERSENspecial
12/21/2023Energy Code Compliance InspectionsTOM PETERSENprogress
12/21/2023FinalTOM PETERSENprogress
12/21/2023Air barrier - visual inspectionTOM PETERSENenergy_progress
▾Documents — 9 on file (BIS + DOB NOW)
▸Plans & Drawings1
▸DOB NOWPlans/Sketch1
08/26/2026B00981016-I1Request digital key ↗
▸Seals & Professional Certifications6
▸DOB NOWProgress Inspector Seal & Signature3
08/23/2026B00981016-I1Open ↗
08/23/2026B00981016-I1Open ↗
08/23/2026B00981016-I1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature2
08/23/2026B00981016-I1Open ↗
08/23/2026B00981016-I1Open ↗
▸DOB NOWDPL-1: Design Professional Seal & Signature1
08/26/2026B00981016-I1Open ↗
▸Environmental & Asbestos1
▸DOB NOWDEP ACP-5: Asbestos Assessment Report1
08/26/2026B00981016-I1Open ↗
▸Approvals, Objections & Sign-offs1
▸DOB NOWUtility Company Final Acceptance Letter1
08/13/2026B00981016-I1Open ↗