RoofUnder Construction5p · 3 filings · 20 docs
ArchitectureDMMechanicalStructural
Issued Permit Scope
General Construction · Mechanical Systems · Protection and Mechanical Methods · Structural
temporary shoring and bracing
On file for this project
41 documents
Removal of Plumbing fixture in a commercial space. No change to use egress or occupancy.
On file for this project
25 documents · 3 drawing sheets
TEMPORARY ROOF PROTECTION AS PER DRAWINGS DURING NB CONSTRUCTION AT 18 WEST 55 STREET, FILED SEP. ROOF PROTECTION SHALL COMPLY WITH CH #33 OF THE NYC BC. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
On file for this project
2 documents · 1 drawing sheet
Floor 6Under Construction9p · 2 filings · 20 docs
ArchitectureDMFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Sprinklers · Structural
temporary shoring and bracing
On file for this project
41 documents
Removal of Plumbing fixture in a commercial space. No change to use egress or occupancy.
On file for this project
25 documents · 4 drawing sheets
Floor 5Under Construction9p · 2 filings · 20 docs
ArchitectureDMFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers · Structural
temporary shoring and bracing
On file for this project
41 documents
Removal of Plumbing fixture in a commercial space. No change to use egress or occupancy.
On file for this project
25 documents · 4 drawing sheets
Floor 4Under Construction9p · 2 filings · 20 docs
ArchitectureDMFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers · Structural
temporary shoring and bracing
On file for this project
41 documents
Removal of Plumbing fixture in a commercial space. No change to use egress or occupancy.
On file for this project
25 documents · 4 drawing sheets
Floor 3Under Construction12p · 3 filings · 20 docs
ArchitectureDMFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Sprinklers · Structural
temporary shoring and bracing
On file for this project
41 documents
Removal of Plumbing fixture in a commercial space. No change to use egress or occupancy.
On file for this project
25 documents · 4 drawing sheets
Installation of a temporary shoring per plan submitted. Work shall comply with 2022 building codes chapter 33. No change in use, egress and/or occupancy with this application.
On file for this project
8 documents
Floor 2Under Construction12p · 3 filings · 20 docs
ArchitectureDMFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers · Structural
temporary shoring and bracing
On file for this project
41 documents
Removal of Plumbing fixture in a commercial space. No change to use egress or occupancy.
On file for this project
25 documents · 4 drawing sheets
Installation of a temporary shoring per plan submitted. Work shall comply with 2022 building codes chapter 33. No change in use, egress and/or occupancy with this application.
On file for this project
8 documents
Floor 1Under Construction12p · 3 filings · 20 docs
ArchitectureDMFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers · Structural
temporary shoring and bracing
On file for this project
41 documents
Removal of Plumbing fixture in a commercial space. No change to use egress or occupancy.
On file for this project
25 documents · 4 drawing sheets
Installation of a temporary shoring per plan submitted. Work shall comply with 2022 building codes chapter 33. No change in use, egress and/or occupancy with this application.
On file for this project
8 documents
CellarUnder Construction9p · 2 filings · 20 docs
ArchitectureDMFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers · Structural
temporary shoring and bracing
On file for this project
41 documents
Removal of Plumbing fixture in a commercial space. No change to use egress or occupancy.
On file for this project
25 documents · 4 drawing sheets