RoofUnder Construction2p · 1 filing · 3 docs
Architecture
Issued Permit Scope
General Construction
Work includes per filed plans remove/replace cracked stone coping, repair stone panels/copings, sealant joint restoration, replace damaged veneer anchors, repair stucco wall finish, brick replacement, brick stitching repair, brick corner reconstruction.
On file for this project
3 documents · 1 drawing sheet
BulkheadUnder Construction1p · 1 filing · 10 docs
Structural
Suspended Scaffold for Facade Restoration & Inspection as Shown on Plans
On file for this project
10 documents · 1 drawing sheet
Floor 512p · 1 filing · 3 docs
Mechanical
MECHANICAL MODIFICATIONS TAKING PLACE ON 50TH FLOOR CONSTRUCTION (51ST MARKETING) AS PER PLANS FILED HEREWITH. MECHANICAL FLOOR NO OCCUPANCY. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
3 documents · 2 drawing sheets
Floor 50Under Construction12p · 3 filings · 18 docs
GeneralMechanicalStructural
Issued Permit Scope
Mechanical Systems · Structural
GENERAL CONSTRUCTION TAKING PLACE ON 49TH FLOOR CONSTRUCTION (50TH FLOOR MARKETING) AS PER PLANS FILED HREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
5 documents · 1 drawing sheet
STRUCTURAL MODIFICATIONS TAKING PLACE ON 50TH FL CONSTRUCTION (51ST MARKETING) AS PER PLANS FILED HEREWITH. MECHANICAL FLOOR, NO OCCUPANCY. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
10 documents
MECHANICAL MODIFICATIONS TAKING PLACE ON 50TH FLOOR CONSTRUCTION (51ST MARKETING) AS PER PLANS FILED HEREWITH. MECHANICAL FLOOR NO OCCUPANCY. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
3 documents
Floor 49Under Construction15p · 5 filings · 20 docs
ArchitectureFire ProtectionPlumbing
Issued Permit Scope
General Construction · Plumbing · Sprinklers
GENERAL CONSTRUCTION TAKING PLACE ON 49TH FLOOR CONSTRUCTION (50TH FLOOR MARKETING) AS PER PLANS FILED HREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
5 documents
PLUMBING MODIFICATIONS TAKING PLACE ON 49TH FLOOR CONSTRUCTON (50TH FLOOR MARKETING) AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
3 documents
SPRINKLER MODIFICATIONS TAKING PLACE ON 49TH FLOOR CONSTRUCTION (50TH FLOOR MARKETING) AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
8 documents
Latest 3 of 5 filings on this floor.
Floor 48Under Construction14p · 6 filings · 20 docs
ArchitectureFire ProtectionGeneral
Issued Permit Scope
General Construction · Sprinklers
GENERAL CONSTRUCTION TAKING PLACE ON 47TH FLOOR CONSTRUCTION (48TH FLOOR MARKETING) AS PER PLANS FILED HREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
5 documents · 1 drawing sheet
SPRINKLER MODIFICATIONS TAKING PLACE ON 48TH FLOOR CONSTRUCTION (49TH FLOOR MARKETING) AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
7 documents
GENERAL CONSTRUCTION TAKING PLACE ON 48TH FLOOR CONSTRUCTION (49TH FLOOR MARKETING) AS PER PLANS FILED HREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
3 documents
Latest 3 of 6 filings on this floor.
Floor 47Under Construction52p · 4 filings · 20 docs
ArchitectureDMFire ProtectionMechanicalStructural
Issued Permit Scope
General Construction · Mechanical Systems · Sprinklers · Structural
SPRINKLER MODIFICATIONS TAKING PLACE ON 47TH FLOOR CONSTRUCTION (48TH FLOOR MARKETING) AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
5 documents
GENERAL CONSTRUCTION TAKING PLACE ON 47TH FLOOR CONSTRUCTION (48TH FLOOR MARKETING) AS PER PLANS FILED HREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
5 documents
Structural modifications including concrete on metal deck infill at existing stair opening. No change in use, egress or occupancy.
On file for this project
24 documents · 4 drawing sheets
Latest 3 of 4 filings on this floor.
Floor 4667p · 6 filings · 20 docs
ArchitectureDMFire ProtectionMechanicalPlumbing
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers
Modification of sprinkler system
On file for this project
23 documents · 10 drawing sheets
GENERAL CONSTRUCTION TAKING PLACE ON 45TH FL CONSTRUCTION (46TH MARKETING) AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
6 documents · 2 drawing sheets
Modification to sprinkler system as shown on plans
On file for this project
3 documents · 2 drawing sheets
Latest 3 of 6 filings on this floor.
Floor 45112p · 14 filings · 20 docs
ArchitectureDMFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers · Standpipe · Structural
STANDPIPE MODIFICATIONS TAKING PLACE ON 45TH FLOOR CONSTRUCTION (46TH MKT) AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
5 documents
PLUMBING MODIFICATIONS TAKING PLACE ON 45TH FL CONSTRUCTION (46TH MKT) AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
6 documents
GENERAL CONSTRUCTION TAKING PLACE ON 45TH FL CONSTRUCTION (46TH MARKETING) AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
6 documents
Latest 3 of 14 filings on this floor.
Floor 44Under Construction32p · 7 filings · 20 docs
ArchitectureFire ProtectionMechanical
Issued Permit Scope
General Construction · Mechanical Systems · Sprinklers
GENERAL CONSTRUCTION TAKING PLACE ON 44TH FLOOR CONSTRUCTION (45TH FLOOR MARKETING) AS PER PLANS FILED HREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
4 documents
MECHANICAL MODIFICATIONS TAKING PLACE ON 44TH FLOOR CONSTRUCTION (45TH FLOOR MARKETING) AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
5 documents
SPRINKLER MODIFICATIONS TAKING PLACE ON 44TH FLOOR CONSTRUCTION (45TH MARKETING) AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
4 documents · 2 drawing sheets
Latest 3 of 7 filings on this floor.
Floor 437p · 2 filings · 20 docs
ArchitectureDMFire ProtectionMechanicalPlumbingOther
Issued Permit Scope
General Construction
MECHANICAL MODIFICATIONS TAKING PLACE ON 42ND FLOOR CONSTRUCTION (43RD MKT) AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
12 documents · 3 drawing sheets
INTERIOR DEMOLITION OF 43RD FLOOR INCLUDING BUT NOT LIMITED TO NON-LOAD BEARING PARTITIONS, DOORS, FLOORING, CEILING, EQUIPMENT, WIRING, FINISHES, LIGHTS, SUPPORTS, TOILETS, LAVATORIES, & SHOWERS PER DESIGN DRAWINGS
On file for this project
12 documents · 4 drawing sheets
Floor 42204p · 14 filings · 20 docs
ArchitectureDMFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers · Standpipe · Structural
SPRINKLER MODIFICATIONS TAKING PLACE ON 42ND FLOOR CONSTRUCTION (43RD MKT) AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
7 documents · 1 drawing sheet
PLUMBING MODIFICATIONS TAKING PLACE ON 42ND FLOOR CONSTRUCTION (43RD MKT) AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
9 documents · 3 drawing sheets
STANDPIPE MODIFICATIONS TAKING PLACE ON 42ND FLOOR CONSTRUCTION (43RD MKT) AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
5 documents · 1 drawing sheet
Latest 3 of 14 filings on this floor.
Floor 4168p · 8 filings · 20 docs
ArchitectureDMFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers · Standpipe · Structural
Filing herewith modification to the existing sprinkler and standpipe system as per plans filed herewith. Marketing Floors: 9,10,11,41,42, Construction Floors: 8,9,10,40,41. No change to use, egress or occupancy.
On file for this project
21 documents · 4 drawing sheets
Filing herewith Structural work as per plans filed herewith. Marketing Floors:10,11,41,42, Construction Floors:9,10,40,41. No change to use, egress or occupancy.
On file for this project
10 documents · 1 drawing sheet
Filing herewith interior renovation of the 10, 11, 41 and 42 FLS. as per plans filed herewith. Construction Floors 9,10,40,41. Marketing Floors 10,11,41,42. No change to use, egress or occupancy.
On file for this project
14 documents · 1 drawing sheet
Latest 3 of 8 filings on this floor.
Floor 4042p · 5 filings · 20 docs
ArchitectureDMFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers · Structural
Modification/additions to existing sprinkler system on the 39th & 40th Floors. Installation of new pre-action sprinkler system on the 40th Floor as shown on drawings. No change in use, egress or occupancy.
On file for this project
4 documents · 1 drawing sheet
Modification to plumbing fixtures and related piping as shown on drawings. No change in use, egress or occupancy.
On file for this project
8 documents · 3 drawing sheets
Minor interior revisions to office space, removal of stair and expansion to men's restroom as show on drawings. No change in use, egress or occupancy.
On file for this project
6 documents · 8 drawing sheets
Latest 3 of 5 filings on this floor.
Floor 3962p · 5 filings · 20 docs
ArchitectureFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers · Structural
Removal and installation of interior non bearing partitions and related finishes as per drawings. No change to use, egress or occupancy.
On file for this project
22 documents
Modification/additions to existing sprinkler system on the 39th & 40th Floors. Installation of new pre-action sprinkler system on the 40th Floor as shown on drawings. No change in use, egress or occupancy.
On file for this project
4 documents · 1 drawing sheet
Modification to plumbing fixtures and related piping as shown on drawings. No change in use, egress or occupancy.
On file for this project
8 documents · 2 drawing sheets
Latest 3 of 5 filings on this floor.
Floor 38Under Construction74p · 8 filings · 20 docs
ArchitectureDMFire ProtectionGeneralMechanicalPlumbing
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers · Standpipe
SPRINKLER MODIFICATIONS TAKING PLACE ON 37TH FLOOR CONSTRUCTION (38TH FLOOR MARKETING) AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
2 documents · 1 drawing sheet
REMOVAL OF EXISTING PRIMARY AIR DUCTS, SECONDARY WATER RETURN RISERS, PERIMETER INDUCTION UNITS, SUPPLY AIR MAIN & DUCT; INSTALLATION OF VARIOUS EQUIPMENTS, DUCTS, LINES, FANS, UNITS, PIPING AS PER DESIGN DRAWINGS
On file for this project
27 documents · 10 drawing sheets
Modifications to the existing Standpipe System: Installation of one (1) new Fire Hose Cabinet and associated Standpipe piping on the 38th Floor as per plans (Artisan Partners.) No change to use, egress or occupancy.
On file for this project
12 documents
Latest 3 of 8 filings on this floor.
Floor 37Under Construction234p · 11 filings · 20 docs
ArchitectureDMFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers · Structural
Removal and construction of interior partitions, doors and ceilings as shown on drawings. No change in use, egress or occupancy.
On file for this project
36 documents · 14 drawing sheets
SPRINKLER MODIFICATIONS TAKING PLACE ON 37TH FLOOR CONSTRUCTION (38TH FLOOR MARKETING) AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
2 documents
GENERAL CONSTRUCTION TAKING PLACE ON 37TH FLOOR CONSTRUCTION (38TH FLOOR MARKETING) AS PER PLANS FILED HREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
2 documents · 1 drawing sheet
Latest 3 of 11 filings on this floor.
Floor 364p · 1 filing · 3 docs
Mechanical
Issued Permit Scope
Mechanical Systems
Modification to HVAC ductwork and related piping as shown on drawings filed herewith. No change in use, egress or occupancy.
On file for this project
3 documents · 1 drawing sheet
Floor 35
Floor 3484p · 9 filings · 20 docs
ArchitectureDMFire ProtectionGeneralMechanicalPlumbing
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers
Modification to sprinkler system and related piping as shown on drawings filed herewith. No change in use, egress or occupancy.
On file for this project
8 documents · 1 drawing sheet
Modification to HVAC ductwork and related piping as shown on drawings filed herewith. No change in use, egress or occupancy.
On file for this project
8 documents · 4 drawing sheets
Modification to existing plumbing systems and installation of plumbing fixtures. No change to use, egress or occupancy.
On file for this project
3 documents · 2 drawing sheets
Latest 3 of 9 filings on this floor.
Floor 3313p · 3 filings · 11 docs
ArchitectureMechanicalPlumbing
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing
PLUMBING MODIFICATIONS TAKING PLACE AT 33RD FLOOR AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
3 documents · 1 drawing sheet
GENERAL CONSTRUCTION TAKING PLACE ON 33RD FLOOR PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
5 documents · 3 drawing sheets
MECHANICAL MODIFICATIONS TAKING PLACE AT 33RD FLOOR AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
3 documents
Floor 3216p · 6 filings · 20 docs
ArchitectureFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Sprinklers · Standpipe · Structural
Partial 31st floor office renovation and new convenience stair to the 32nd floor as shown on drawings filed herewith. No change in use, egress or occupancy.
On file for this project
4 documents
STRUCTURAL REFRAMING OF FLOOR TO ACCOMMODATE NEW CONVENIENCE STAIR OPENING AS SHOWN ON PLANS FILED HEREWITH. NO CHANGE TO USE, EGRESS OR OCCUPANCY.
On file for this project
5 documents · 1 drawing sheet
FILING FOR STRUCTURAL FRAMING. WELDING RELATED TO BUILD-OUT FOR THE 32ND FL. INTERIOR MODIFICATIONS AS SHOWN ON DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
7 documents
Latest 3 of 6 filings on this floor.
Floor 3113p · 8 filings · 20 docs
ArchitectureDMFire ProtectionGeneralMechanicalPlumbingOther
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers
Filing for sprinkler work to accommodate the Veritas - 31st Floor Expansion as shown on drawings filed herewith. No change in use, egress or occupancy.
On file for this project
3 documents · 6 drawing sheets
Partial 31st floor office renovation and new convenience stair to the 32nd floor as shown on drawings filed herewith. No change in use, egress or occupancy.
On file for this project
4 documents
Filing for plumbing work to accommodate the Veritas - 31st Floor Expansion as shown on drawings filed herewith. No change in use, egress or occupancy.
On file for this project
3 documents · 5 drawing sheets
Latest 3 of 8 filings on this floor.
Floor 30Under Construction5p · 3 filings · 14 docs
ArchitectureFire ProtectionMechanicalPlumbing
Issued Permit Scope
General Construction
GENERAL CONSTRUCTION TAKING PLACE ON 30TH FL CONSTRUCTION (31ST MARKETING)AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
4 documents
Modification to existing Plumbing fixtures and Sprinkler system as per plans filed herewith
On file for this project
4 documents · 3 drawing sheets
Modification to existing HVAC system as per plans filed herewith. No change in use, egress or occupancy under this application.
On file for this project
6 documents · 2 drawing sheets
Floor 29Under Construction107p · 18 filings · 20 docs
ArchitectureFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers · Structural
PLUMBING MODIFICATIONS TAKING PLACE ON 29TH FLOOR CONSTRUCTON (30TH FLOOR MARKETING) AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
3 documents
SPRINKLER MODIFICATIONS TAKING PLACE ON 29TH FLOOR CONSTRUCTION (30TH FLOOR MARKETING) AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
4 documents
GENERAL CONSTRUCTION TAKING PLACE ON 29TH FL (CONSTRUCTION / 30TH FL (MARKETING) AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
9 documents · 1 drawing sheet
Latest 3 of 18 filings on this floor.
Floor 2885p · 8 filings · 20 docs
ArchitectureDMFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers · Standpipe · Structural
Removal and installation of interior nonbearing partitions as per plans filed herewith. No change in use, egress or occupancy under this application.
On file for this project
3 documents · 3 drawing sheets
Modification to existing HVAC system as per plans filed herewith. No change in use, egress or occupancy under this application.
On file for this project
13 documents · 2 drawing sheets
Modification to existing Plumbing fixtures, Sprinkler system, and Standpipe system as per plans filed herewith
On file for this project
12 documents
Latest 3 of 8 filings on this floor.
Floor 2713p · 12 filings · 20 docs
ArchitectureDMFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers · Structural
REMOVAL AND INSTALLATION OF INTERIOR NON-BEARING PARTITIONS AND RELATED FINISHES AS PER DRAWINGS FILED HEREWITH. ADDITION OF ASSEMBLY OCCUPANCY, AND INCREASE IN FLOOR CAPACITY ON THE 27TH FLOOR.
On file for this project
8 documents · 2 drawing sheets
Removal and installation of interior nonbearing partitions as per plans filed herewith. No change in use, egress or occupancy under this application.
On file for this project
6 documents · 7 drawing sheets
Modification to existing Plumbing fixtures, Sprinkler System, and Standpipe system as per plans filed herewith
On file for this project
12 documents · 3 drawing sheets
Latest 3 of 12 filings on this floor.
Floor 26Under Construction71p · 11 filings · 20 docs
ArchitectureDMFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers
GENERAL CONSTRUCTION TAKING PLACE ON 25TH FLOOR CONSTRUCTION (26TH FLOOR MARKETING) FOR CHANGE OF USE - OFFICE WITH ACCESSORY EXERCISE ROOM AND COMMERCIAL KITCHEN
On file for this project
10 documents
STANDPIPE MODIFICATIONS TAKING PLACE ON 25TH FLOOR CONSTRUCTION (26TH MKT) AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
4 documents · 1 drawing sheet
SPRINKLER MODIFICATIONS TAKING PLACE ON 25TH FL CONSTRUCTION (26TH FL MARKETING) AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
4 documents · 1 drawing sheet
Latest 3 of 11 filings on this floor.
Floor 25Under Construction105p · 10 filings · 20 docs
ArchitectureCivilFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers · Standpipe · Structural
GENERAL CONSTRUCTION TAKING PLACE ON 25TH FLOOR CONSTRUCTION (26TH FLOOR MARKETING) AS PER PLANS FILED HREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
12 documents · 1 drawing sheet
GENERAL CONSTRUCTION TAKING PLACE ON 25TH FLOOR CONSTRUCTION (26TH FLOOR MARKETING) FOR CHANGE OF USE - OFFICE WITH ACCESSORY EXERCISE ROOM AND COMMERCIAL KITCHEN
On file for this project
10 documents
MECHANICAL MODIFICATIONS TAKING PLACE ON 25TH FL CONSTRUCTION (26TH FL MARKETING) AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
3 documents
Latest 3 of 10 filings on this floor.
Floor 2422p · 5 filings · 20 docs
ArchitectureFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Sprinklers · Structural
Modification to existing Plumbing fixtures, Sprinkler system, and Standpipe system as per plans filed herewith
On file for this project
12 documents · 7 drawing sheets
Modification to existing HVAC system as per plans filed herewith. No change in use, egress or occupancy under this application.
On file for this project
7 documents · 2 drawing sheets
Support of slab opening for new feature stair, and support of mechanical equipment .Approximate Linear footage: 280 ft.
On file for this project
3 documents · 1 drawing sheet
Latest 3 of 5 filings on this floor.
Floor 2364p · 4 filings · 20 docs
ArchitectureFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers · Standpipe
MECHANICAL MODIFICATIONS TAKING PLACE ON 22ND FL CONSTRUCTION (23RD FL MARKETING) AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
18 documents · 1 drawing sheet
Removal and installation of interior nonbearing partitions as per plans filed herewith. No change in use, egress or occupancy under this application.
On file for this project
3 documents · 3 drawing sheets
Modification to existing Plumbing fixtures, Sprinkler system, and Standpipe system as per plans filed herewith
On file for this project
12 documents
Latest 3 of 4 filings on this floor.
Floor 2291p · 9 filings · 20 docs
ArchitectureFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers · Structural
SPRINKLER MODIFICATIONS TAKING PLACE ON 22ND FL CONSTRUCTION (23RD FL MARKETING) AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
8 documents
MECHANICAL MODIFICATIONS TAKING PLACE ON 22ND FL CONSTRUCTION (23RD FL MARKETING) AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
18 documents
PLUMBING MODIFICATIONS TAKING PLACE ON 22ND FL CONSTRUCTION (23RD MKT) AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
6 documents
Latest 3 of 9 filings on this floor.
Floor 2138p · 4 filings · 19 docs
ArchitectureFire ProtectionMechanicalStructural
Issued Permit Scope
General Construction · Mechanical Systems · Sprinklers · Structural
Filing herewith Structural work on the 21st FL. and 22nd FL. (Construction FL.20, 21 Marketing FL.21, 22) as per plans filed herewith. No change to use, egress or occupancy.
On file for this project
3 documents
Filing herewith modification to an existing sprinkler and standpipe system on the 21st FL. (Construction FL.20, Marketing FL.21) as per plans filed herewith. No change to use, egress or occupancy.
On file for this project
5 documents
Filing herewith interior renovation of the 21st FL. (Construction FL.20, Marketing FL.21) as per plans filed herewith. No change to use, egress or occupancy.
On file for this project
5 documents · 1 drawing sheet
Latest 3 of 4 filings on this floor.
Floor 2068p · 7 filings · 20 docs
ArchitectureFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers · Standpipe · Structural
Sprinkler and standpipe work in conjunction with an interior fit-out. No change to use, egress, or occupancy.
On file for this project
12 documents · 2 drawing sheets
Filing herewith plumbing work as per plans filed herewith (Construction FL.19 and 20, Marketing FL.20 and 21) . No change to use, egress or occupancy.
On file for this project
7 documents
Installation of Core Restroom, Wellness, and Pantry piping and fixtures on the 19th & 20th floors. No change to use, egress, or occupancy.
On file for this project
6 documents
Latest 3 of 7 filings on this floor.
Floor 1969p · 7 filings · 20 docs
ArchitectureFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers · Standpipe · Structural
Sprinkler and standpipe work in conjunction with an interior fit-out. No change to use, egress, or occupancy.
On file for this project
12 documents · 2 drawing sheets
Filing herewith plumbing work as per plans filed herewith (Construction FL.19 and 20, Marketing FL.20 and 21) . No change to use, egress or occupancy.
On file for this project
7 documents
Installation of Core Restroom, Wellness, and Pantry piping and fixtures on the 19th & 20th floors. No change to use, egress, or occupancy.
On file for this project
6 documents · 1 drawing sheet
Latest 3 of 7 filings on this floor.
Floor 1813p · 6 filings · 20 docs
ArchitectureFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers · Standpipe · Structural
Removal and installation of interior non-bearing partitions and related finishes as per plans filed herewith. No change in use, egress or occupancy.
On file for this project
6 documents · 2 drawing sheets
Modification to existing HVAC system as per plans filed herewith. NO change in use, egress or occupancy.
On file for this project
14 documents · 1 drawing sheet
Modification to existing Sprinkler system & Additions / modifications to existing plumbing system as plans filed herewith. No change in use, egress or occupancy under this application.
On file for this project
8 documents · 6 drawing sheets
Latest 3 of 6 filings on this floor.
Floor 17109p · 19 filings · 20 docs
ArchitectureDMFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers · Standpipe · Structural
WORK UNDER THIS APPLICATION IS LIMITED TO THE RENOVATION OF PARTIAL 17THFLOOR INVOLVING WIRING MECHANICAL UNITS.
On file for this project
15 documents · 6 drawing sheets
Removal and installation of interior non-bearing partitions and related finishes as per plans filed herewith. No change in use, egress or occupancy.
On file for this project
6 documents
Modification to existing HVAC system as per plans filed herewith. NO change in use, egress or occupancy.
On file for this project
14 documents
Latest 3 of 19 filings on this floor.
Floor 1661p · 3 filings · 20 docs
ArchitectureFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers · Standpipe · Structural
Filing herewith plumbing work as per plans filed herewith (Construction FL.14,15, Marketing FL.15,16). No change to use, egress or occupancy.
On file for this project
16 documents
Filing herewith mechanical work as per plans filed herewith (Construction FL. 13,14,15, Marketing FL.14,15,16). No change to use, egress or occupancy.
On file for this project
19 documents · 7 drawing sheets
Filing herewith Structural work as per plans filed herewith. Construction FL.:13,14,15, Marketing FL.:14,15,16. No change to use, egress or occupancy.
On file for this project
5 documents
Floor 1558p · 3 filings · 20 docs
ArchitectureDMFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers · Standpipe · Structural
Filing herewith plumbing work as per plans filed herewith (Construction FL.14,15, Marketing FL.15,16). No change to use, egress or occupancy.
On file for this project
16 documents
Filing herewith mechanical work as per plans filed herewith (Construction FL. 13,14,15, Marketing FL.14,15,16). No change to use, egress or occupancy.
On file for this project
19 documents · 4 drawing sheets
Filing herewith Structural work as per plans filed herewith. Construction FL.:13,14,15, Marketing FL.:14,15,16. No change to use, egress or occupancy.
On file for this project
5 documents
Floor 1480p · 9 filings · 20 docs
ArchitectureDMFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers · Standpipe · Structural
Filing herewith plumbing work as per plans filed herewith (Construction FL.14,15, Marketing FL.15,16). No change to use, egress or occupancy.
On file for this project
16 documents · 1 drawing sheet
Filing herewith mechanical work as per plans filed herewith (Construction FL. 13,14,15, Marketing FL.14,15,16). No change to use, egress or occupancy.
On file for this project
19 documents · 5 drawing sheets
Filing herewith Structural work as per plans filed herewith. Construction FL.:13,14,15, Marketing FL.:14,15,16. No change to use, egress or occupancy.
On file for this project
5 documents
Latest 3 of 9 filings on this floor.
Floor 1331p · 9 filings · 20 docs
ArchitectureDMFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers · Standpipe · Structural
Filing herewith interior renovation to existing spaces as per plans filed herewith. Marketing Floors: 11, 12, 13, 14. Construction Floors: 10, 11, 12, 13. No change to use, egress or occupancy.
On file for this project
6 documents
Filing herewith plumbing demo. work on the 13th FL.. as per plans filed herewith. Construction Floor:12, Marketing Floor:13. No change to use, egress or occupancy.
On file for this project
3 documents · 1 drawing sheet
Filing herewith modification to the sprinkler and standpipe system as per plans filed herewith. Marketing Floors: 11,13,14. Construction Floors: 10,12,13. No change to use, egress or occupancy.
On file for this project
8 documents
Latest 3 of 9 filings on this floor.
Floor 1262p · 9 filings · 20 docs
ArchitectureFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers · Structural
Filing herewith interior renovation to existing spaces as per plans filed herewith. Marketing Floors: 11, 12, 13, 14. Construction Floors: 10, 11, 12, 13. No change to use, egress or occupancy.
On file for this project
6 documents
Filing herewith plumbing work as per plans filed herewith. Marketing FL.12 and 22, Construction FL.11 and 21. No change to use, egress or occupancy.
On file for this project
8 documents · 1 drawing sheet
Filing herewith modification to the existing sprinkler and standpipe system as per plans filed herewith. (Construction FL. 11, 21, Marketing FL. 12, 22). No change to use, egress or occupancy.
On file for this project
3 documents · 1 drawing sheet
Latest 3 of 9 filings on this floor.
Floor 1178p · 12 filings · 20 docs
ArchitectureFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers · Standpipe · Structural
Filing herewith interior renovation to existing spaces as per plans filed herewith. Marketing Floors: 11, 12, 13, 14. Construction Floors: 10, 11, 12, 13. No change to use, egress or occupancy.
On file for this project
6 documents
Filing herewith modification to the existing sprinkler and standpipe system as per plans filed herewith. Marketing Floors: 9,10,11,41,42, Construction Floors: 8,9,10,40,41. No change to use, egress or occupancy.
On file for this project
21 documents · 2 drawing sheets
Filing herewith modification to the sprinkler and standpipe system as per plans filed herewith. Marketing Floors: 11,13,14. Construction Floors: 10,12,13. No change to use, egress or occupancy.
On file for this project
8 documents
Latest 3 of 12 filings on this floor.
Floor 10100p · 13 filings · 20 docs
ArchitectureFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers · Standpipe · Structural
Filing herewith modification to the existing standpipe system as per plans filed herewith. (Construction FL.9, Marketing FL.10.) No change to use, egress or occupancy.
On file for this project
5 documents · 1 drawing sheet
Filing herewith Plumbing and Sprinkler work on the 10th FL. (Construction FL.:9, Marketing FL:10) as per plans filed herewith. No change to use, egress or occupancy.
On file for this project
7 documents
Filing herewith mechanical work on the 10th FL. (Construction FL.:9, Marketing FL:10) as per plans filed herewith. No change to use, egress, or occupancy.
On file for this project
13 documents · 1 drawing sheet
Latest 3 of 13 filings on this floor.
Floor 9Under Construction64p · 8 filings · 20 docs
ArchitectureCivilFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Protection and Mechanical Methods · Sprinklers · Standpipe
Filing herewith interior demolition and renovation as per plan filed herewith (8th FL. Construction, 9th FL. Marketing). No change to use, egress or occupancy.
On file for this project
9 documents · 2 drawing sheets
Filing herewith Plumbing and Sprinkler work on the 10th FL. (Construction FL.:9, Marketing FL:10) as per plans filed herewith. No change to use, egress or occupancy.
On file for this project
7 documents · 1 drawing sheet
GENERAL CONSTRUCTION TAKING PLACE ON CELLAR FOR CHANGE OF USE AND INCREASE IN POPULATION
On file for this project
14 documents
Latest 3 of 8 filings on this floor.
Floor 856p · 7 filings · 20 docs
ArchitectureFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers · Standpipe · Structural
Filing herewith interior demolition and renovation as per plans filed herewith. (Construction FL.7, Marketing FL.8) No change to use, egress, or occupancy.
On file for this project
5 documents · 1 drawing sheet
Filing herewith modification to the existing Sprinkler System as per plans filed herewith (Construction FL.7, Marketing FL.8). No change to use, egress or occupancy.
On file for this project
3 documents
Filing herewith mechanical work as per plans filed herewith (Construction FL.7, Marketing FL.8). No change to use, egress or occupancy.
On file for this project
9 documents
Latest 3 of 7 filings on this floor.
Floor 769p · 8 filings · 20 docs
ArchitectureFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers · Standpipe · Structural
Filing herewith mechanical work as per plans filed herewith (Construction FL.7, Marketing FL.8). No change to use, egress or occupancy.
On file for this project
9 documents · 3 drawing sheets
Filing herewith modification to the existing Sprinkler System on the 7th FL. (Construction FL.6, Marketing FL.7) as per plans filed herewith. No change to use, egress or occupancy.
On file for this project
3 documents · 2 drawing sheets
Filing herewith mechanical work on the 7th FL. (Construction FL.:6, Marketing FL:7) as per plans filed herewith. No change to use, egress, or occupancy.
On file for this project
6 documents · 3 drawing sheets
Latest 3 of 8 filings on this floor.
Floor 629p · 2 filings · 20 docs
ArchitectureStructural
Issued Permit Scope
General Construction · Structural
GENERAL CONSTRUCTION TAKING PLACE ON 26TH FLOOR CONSTRUCTION (27TH FLOOR MARKETING) FOR CHANGE OF USE AND POPULATION INCREASE.
On file for this project
30 documents
STRUCTURAL MODIFICATIONS AS PER PLANS FILED HEREWITH.
On file for this project
31 documents
Floor 5Under Construction13p · 2 filings · 20 docs
Architecture
Issued Permit Scope
General Construction
MECHANICAL MODIFICATIONS TAKING PLACE ON CELLAR AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
3 documents
GENERAL CONSTRUCTION TAKING PLACE ON 26TH FLOOR CONSTRUCTION (27TH FLOOR MARKETING) FOR CHANGE OF USE AND POPULATION INCREASE.
On file for this project
30 documents
Floor 424p · 2 filings · 20 docs
ArchitectureMechanical
Issued Permit Scope
General Construction · Mechanical Systems
GENERAL CONSTRUCTION TAKING PLACE ON 26TH FLOOR CONSTRUCTION (27TH FLOOR MARKETING) FOR CHANGE OF USE AND POPULATION INCREASE.
On file for this project
30 documents
MECHANICAL MODIFICATIONS TAKING PLACE ON CELLAR AND 4TH FLOOR AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
3 documents · 1 drawing sheet
Floor 321p · 1 filing · 20 docs
Architecture
Issued Permit Scope
General Construction
GENERAL CONSTRUCTION TAKING PLACE ON 26TH FLOOR CONSTRUCTION (27TH FLOOR MARKETING) FOR CHANGE OF USE AND POPULATION INCREASE.
On file for this project
30 documents
Floor 242p · 5 filings · 20 docs
ArchitectureFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers · Structural
GENERAL CONSTRUCTION TAKING PLACE ON 26TH FLOOR CONSTRUCTION (27TH FLOOR MARKETING) FOR CHANGE OF USE AND POPULATION INCREASE.
On file for this project
30 documents
STRUCTURAL MODIFICATIONS TAKING PLACE ON CELLAR, 1ST AND 2ND FLOORS AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY
On file for this project
21 documents · 1 drawing sheet
Plumbing work to include Installation of new water heater, plumbing roughing to new lavatory and new water closet. Sprinkler work to include minor modifications to the existing system. No change to use, egress or occupancy.
On file for this project
4 documents
Latest 3 of 5 filings on this floor.
Floor 113p · 13 filings · 20 docs
ArchitectureCivilDMElectricalFire ProtectionGeneralLandscapeMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Protection and Mechanical Methods · Sprinklers · Structural
SPRINKLER MODIFICATIONS TAKING PLACE ON SC#2 (3B MKT), SC#1 (2B MKT), CEL (1B MKT) & 1ST Fl AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
4 documents · 1 drawing sheet
GENERAL CONSTRUCTION TAKING PLACE ON 1ST FLOOR AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
6 documents · 3 drawing sheets
GENERAL CONSTRUCTION TAKING PLACE ON 1ST FLOOR AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
4 documents · 2 drawing sheets
Latest 3 of 13 filings on this floor.
Mezzanine21p · 1 filing · 20 docs
Architecture
Issued Permit Scope
General Construction
GENERAL CONSTRUCTION TAKING PLACE ON 26TH FLOOR CONSTRUCTION (27TH FLOOR MARKETING) FOR CHANGE OF USE AND POPULATION INCREASE.
On file for this project
30 documents
CellarUnder Construction199p · 27 filings · 20 docs
ArchitectureDMFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers · Structural
GENERAL CONSTRUCTION TAKING PLACE ON 25TH FLOOR CONSTRUCTION (26TH FLOOR MARKETING) FOR CHANGE OF USE - OFFICE WITH ACCESSORY EXERCISE ROOM AND COMMERCIAL KITCHEN
On file for this project
10 documents
GENERAL CONSTRUCTION TAKING PLACE ON CELLAR AS PER PLANS FILED HREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
6 documents · 2 drawing sheets
MECHANICAL MODIFICATIONS TAKING PLACE ON CELLAR AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
3 documents
Latest 3 of 25 filings on this floor.
Sub-CellarUnder Construction140p · 12 filings · 20 docs
ArchitectureDMFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers · Structural
MECHANICAL MODIFICATIONS TAKING PLACE ON SUB-CELLAR #1 (MARKETING B-2) AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
6 documents
GENERAL CONSTRUCTION TAKING PLACE ON SUB-CELLAR #1 (B-2 MARKETING) AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
14 documents
SPRINKLER MODIFICATIONS TAKING PLACE ON SUB-CELLAR #1 (MARKETING B-2) AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
8 documents
Latest 3 of 12 filings on this floor.
Sub-Basement34p · 3 filings · 20 docs
ArchitectureFire ProtectionPlumbing
Issued Permit Scope
General Construction · Plumbing · Sprinklers
SPRINKLER MODIFICATIONS TAKING PLACE ON CELLAR, SUB-CELLAR, AND 1ST FLOOR AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
28 documents
INCLUDING BUT NOT LIMITED TO ADDITION OF NEW WATER & SANITARY LINES AND HOT WATER HEATER PER DESIGN DRAWINGS
On file for this project
8 documents
Renovation of locker room in Basement 1 as per design drawings
On file for this project
5 documents
Site & exteriorUnder Construction49p · 7 filings · 19 docs
ArchitectureElectricalEquipmentGeneralMechanicalPlumbingStructural
Issued Permit Scope
Construction Fence · General Construction · Sidewalk Shed
INSTALLATION OF 300 PSF SIDEWALK SHED AS PER PLANS. ALL EQUIPMENT SHALL COMPLY WITH CHAPTER #33 OF THE 2022 CODE. NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
On file for this project
2 documents · 12 drawing sheets
Work includes per filed plans remove/replace cracked stone coping, repair stone panels/copings, sealant joint restoration, replace damaged veneer anchors, repair stucco wall finish, brick replacement, brick stitching repair, brick corner reconstruction.
On file for this project
3 documents · 3 drawing sheets
INSTALLATION OF PYLWOOD FENCE AS PER PLANS. PLYWOOD FENCE SHALL COMPLY WITH CHAPTER #33 OF THE 2022 CODE NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
On file for this project
2 documents · 4 drawing sheets
Latest 3 of 7 filings on this floor.
Filed — no permit issued71p · 16 filings · 20 docs
ArchitectureCivilDMFire ProtectionGeneralMechanicalPlumbingStructuralOther
PLUMBING MODIFICATIONS TAKING PLACE ON CELLAR AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
3 documents · 4 drawing sheets
SPRINKLER MODIFICATIONS TAKING PLACE ON CELLAR AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
4 documents · 8 drawing sheets
GENERAL CONSTRUCTION TAKING PLACE ON CELLAR AS PER PLANS FILED HREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
4 documents
Latest 3 of 16 filings on this floor.