← Back
Two family frame
90-12 201 STREET
QUEENS · Hollis · BIN 4222956
💬 Discuss this project
1920Year Built
2.5Stories
B2Building Class
R4Zoning
1,695 sfGross Floor Area
2Units
2 Open Violations ▸FDNY Report ↗
Two family frame · 3,000 sf lot · 0.57 FAR built · Flood zone X
Locations of Work
Electrical
Roof1p · 1 filing · 9 docs
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
PARKER AND WEST ENGINEERING, PLLC105/24/2024
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
SUNRUN103/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
SUNRUN INSTALLATION SVCGeneral Contractor107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
PARKER AND WEST ENGINEERI5272105/24/2024
Building Lifecycle
All (10)Filed (1)Permit Issued (1)Signed Off (1)Violation (2)Special Inspection (5)
02/27/2025
Signed off — Alteration
Q01052462-I1
05/31/2024
Permit issued — Solar
Q01052462-I1-SL
05/24/2024
Filed — Alteration
Q01052462-I1
05/16/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
Walid Abdulla
05/16/2024
Special inspection requirement — Structural Stability – Alterations of existing buildings
Walid Abdulla
05/16/2024
Special inspection requirement — Energy Code Compliance Inspections
Walid Abdulla
05/16/2024
Special inspection requirement — Final
Walid Abdulla
05/16/2024
Special inspection requirement — Air barrier - visual inspection
Walid Abdulla
06/21/2006
Violation issued (HPD, open)
B
06/21/2006
Violation issued (HPD, open)
B
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarSigned-offSUNRUN INSTALLATION SVC05/31/2024
1 project · most recent 05/24/2024
FiledStatusContractorScope
05/24/2024CompleteSUNRUN SOLAR ELECTL CORP—
▾Special Inspection Requirements (DOB NOW) — 5
DateRequirementInspectorRole
05/16/2024Fire-Resistant Penetrations and JointsWalid Abdullaspecial
05/16/2024Structural Stability – Alterations of existing buildingsWalid Abdullaspecial
05/16/2024Energy Code Compliance InspectionsWalid Abdullaprogress
05/16/2024FinalWalid Abdullaprogress
05/16/2024Air barrier - visual inspectionWalid Abdullaenergy_progress
▾Documents — 9 on file (BIS + DOB NOW)
▸Plans & Drawings1
▸DOB NOWPlans/Sketch1
08/22/2026Q01052462-I1Request digital key ↗
▸Seals & Professional Certifications6
▸DOB NOWProgress Inspector Seal & Signature3
08/28/2026Q01052462-I1Open ↗
08/28/2026Q01052462-I1Open ↗
08/28/2026Q01052462-I1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature2
08/28/2026Q01052462-I1Open ↗
08/28/2026Q01052462-I1Open ↗
▸DOB NOWDPL-1: Design Professional Seal & Signature1
08/13/2026Q01052462-I1Open ↗
▸Environmental & Asbestos1
▸DOB NOWDEP ACP-5: Asbestos Assessment Report1
08/13/2026Q01052462-I1Open ↗
▸Approvals, Objections & Sign-offs1
▸DOB NOWUtility Company Final Acceptance Letter1
08/13/2026Q01052462-I1Open ↗