← Back
Two stories - detached, small or mid-size
90-22 196 STREET
QUEENS · BIN 4222316
💬 Discuss this project
1925Year Built
2.5Stories
A1Building Class
R4Zoning
1,935 sfGross Floor Area
1Units
4 Open Violations 3 unresolved · 1 paperwork only ▸FDNY Report ↗
Two stories - detached, small or mid-size · Owner of record: NAHRED REALTY LLC · 6,882 sf lot · 0.28 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralFire Protection
Roof7p · 1 filing · 20 docs
Floor 24p · 1 filing · 20 docs
Floor 14p · 1 filing · 20 docs
Cellar5p · 1 filing · 20 docs
Basement4p · 1 filing · 20 docs
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
01/10/2025$999K—— → —$516/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
D&E BUILD EVERGREEN INC.408/12/2025
PETER CHO ARCHITECTS, PLLC103/28/2025
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
METRO DESIGN CONSULTANTS INC1003/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
J&J DESIGNS INCGeneral Contractor607/08/2026
JOSEPH WEINSTEIN ELECTRICElectrical103/22/2026
RISHON HOMES CORPGeneral Contractor103/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
D&E BUILD EVERGREEN I9342208/12/2025
TRIANGLE INSPECTION & TES7495108/12/2025
NKM ENGINEERING PLLC6244107/01/2025
Building Lifecycle
All (67)Filed (5)Permit Issued (4)Signed Off (1)Violation (5)Objection (22)Special Inspection (30)
07/21/2026
Violation issued (ECB, open)
Construction
06/14/2026
Violation issued (ECB, open)
Construction
06/14/2026
Violation issued (ECB, open)
Construction
04/06/2026
Violation issued (ECB, open)
Unknown
12/20/2025
Permit issued — Foundation
Q01221901-I1-GC-CX
12/20/2025
Permit issued — Structural
Q01221901-I1-FO-EA
12/05/2025
Objection resolved — Addressed
12/03/2025
Objection resolved — Addressed
11/28/2025
Objection resolved — Addressed
11/28/2025
Objection resolved — Addressed
10/20/2025
Signed off — Full Demolition
Handheld Full demolition of an existing two & half story one-family frame building
Q01167223-I1
10/17/2025
Objection resolved — Addressed
09/12/2025
Permit issued — Full Demolition
Q01167223-I1-FD
09/12/2025
Permit issued — Construction Fence
Q01202295-I1-FN
09/12/2025
Objection raised — Plumbing
08/12/2025
Filed — New Building
PROPOSED NEW THREE (3) STORY, THREE (3) FAMILY BUILDING WITH CELLAR. OBTAIN A CERTIFICATE OF OCCUPANCY. ALL WORK AS PER PLANS.
Q01221901-S1
08/12/2025
Objection resolved — Addressed
08/12/2025
Objection resolved — Addressed
08/12/2025
Objection resolved — Addressed
08/12/2025
Objection resolved — Addressed
08/12/2025
Objection resolved — Addressed
07/30/2025
Objection raised — Zoning
07/30/2025
Objection raised — Zoning
07/30/2025
Objection raised — Zoning
07/30/2025
Objection raised — Admin
07/30/2025
Objection raised — Plumbing
07/30/2025
Objection raised — Structural
07/30/2025
Objection raised — Structural
07/29/2025
Objection raised — Scope
07/16/2025
Objection raised — Scope
07/01/2025
Filed — New Building
PROPOSED NEW THREE (3) STORY, THREE (3) FAMILY BUILDING WITH CELLAR. OBTAIN A CERTIFICATE OF OCCUPANCY. ALL WORK AS PER PLANS.
Q01221901-S2
07/01/2025
Filed — New Building
PROPOSED NEW THREE (3) STORY, THREE (3) FAMILY BUILDING WITH CELLAR. OBTAIN A CERTIFICATE OF OCCUPANCY. ALL WORK AS PER PLANS.
Q01221901-I1
05/07/2025
Special inspection requirement — Mechanical Systems
Danny Chen
05/07/2025
Special inspection requirement — Concrete - Cast-In-Place
Danny Chen
05/07/2025
Special inspection requirement — Excavations - Sheeting, Shoring, and Bracing
Danny Chen
05/07/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Danny Chen
05/07/2025
Special inspection requirement — Heating Systems
Danny Chen
05/07/2025
Special inspection requirement — Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation
Danny Chen
05/07/2025
Special inspection requirement — Structural Steel - High Strength Bolting
Danny Chen
05/07/2025
Special inspection requirement — Subgrade Inspections
Danny Chen
05/07/2025
Special inspection requirement — Subsurface Investigations (Borings/Test Pits)
Rajasekhar Sakhamuri
05/07/2025
Special inspection requirement — Masonry
Danny Chen
05/07/2025
Special inspection requirement — Structural Steel - Details
Danny Chen
05/07/2025
Special inspection requirement — Wood – Seismic Resistance
NARESH MAHANGU
05/07/2025
Special inspection requirement — Final
PETER CHO
05/07/2025
Special inspection requirement — Footing and Foundation
Danny Chen
05/07/2025
Special inspection requirement — Energy Code Compliance Inspections
Danny Chen
05/07/2025
Special inspection requirement — Fire-Resistance Rated Construction
Danny Chen
05/07/2025
Special inspection requirement — Structural Wood Frame
Danny Chen
05/07/2025
Special inspection requirement — Air barrier — testing
Danny Chen
05/07/2025
Special inspection requirement — Electric vehicle service equipment requirements
Danny Chen
05/07/2025
Special inspection requirement — Air barrier - visual inspection
Danny Chen
05/07/2025
Special inspection requirement — Fenestration air leakage
Danny Chen
05/07/2025
Special inspection requirement — Fenestration areas
Danny Chen
05/07/2025
Special inspection requirement — Interior lighting power
Danny Chen
05/07/2025
Special inspection requirement — Fenestration and door U-factor and product ratings
Danny Chen
05/07/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
Danny Chen
05/07/2025
Special inspection requirement — Insulation placement and R values
Danny Chen
05/07/2025
Special inspection requirement — HVAC-R and service water heating equipment
Danny Chen
05/07/2025
Special inspection requirement — Maintenance information
Danny Chen
Latest 60 of 67 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWFoundationPermit IssuedJ&J DESIGNS INC12/20/2025
DOB NOWStructuralPermit IssuedJ&J DESIGNS INC12/20/2025
DOB NOWFull DemolitionSigned-offJ&J DESIGNS INC09/12/2025
DOB NOWConstruction FencePermit IssuedJ&J DESIGNS INC09/12/2025
DOB NOWFull DemolitionSigned-offRISHON HOMES CORP—
1 project · most recent 08/12/2025
Air Conditioning Systems Heating Systems Ventilation Systems
FiledStatusContractorScopeMake / Model / Capacity
08/12/2025Permit IssuedJ&J DESIGNS INCAir Conditioning Systems, Heating Systems, Ventilation Systems
Cooling
Cooper & Hunter CH-N48LCU-230VO 48,000 BTU · Condensing Unit ×2
CH-N60LCU-230VO 60,000 BTU · Condensing Unit ×1
Heating
Cooper & Hunter CH-48AHU 48,000 BTU · Ahu ×2
CH-60AHU 60,000 BTU · Ahu ×1
Ventilation
Hampton Bay 7114-01 50 CFM · Exhaust Fan ×6
Janska RHW-3652 150 CFM · Exhaust Fan ×3
1 project · most recent 08/12/2025
Sprinkler System
FiledStatusContractorScope
08/12/2025——Sprinkler System
1 project · most recent 08/12/2025
Plumbing-Sprinkler Storm Water/Sanitary
FiledStatusContractorScope
08/12/2025——Plumbing-Sprinkler, Storm, Water/Sanitary
1 project · most recent 02/04/2025
FiledStatusContractorScope
02/04/2025Permit IssuedJOSEPH WEINSTEIN ELECTRIC1 meters
1 project · most recent 08/12/2025
Steel Masonry Wood
FiledStatusContractorScope
08/12/2025Permit IssuedJ&J DESIGNS INCSteel, Masonry, Wood
1 project · most recent 03/28/2025
Fence
FiledStatusContractorScope
03/28/2025Permit IssuedJ&J DESIGNS INCFence
1 project · most recent 08/12/2025
Earthwork
FiledStatusContractorScope
08/12/2025Permit IssuedJ&J DESIGNS INCEarthwork
▾Special Inspection Requirements (DOB NOW) — 34
DateRequirementInspectorRole
05/07/2025Mechanical SystemsDanny Chenspecial
05/07/2025Concrete - Cast-In-PlaceDanny Chenspecial
05/07/2025Excavations - Sheeting, Shoring, and BracingDanny Chenspecial
05/07/2025Fire-Resistant Penetrations and JointsDanny Chenspecial
05/07/2025Heating SystemsDanny Chenspecial
05/07/2025Private On-Site Storm Water Disposal Systems-, and Detention Facilities, InstallationDanny Chenspecial
05/07/2025Structural Steel - High Strength BoltingDanny Chenspecial
05/07/2025Subgrade InspectionsDanny Chenspecial
05/07/2025Subsurface Investigations (Borings/Test Pits)Rajasekhar Sakhamurispecial
05/07/2025MasonryDanny Chenspecial
05/07/2025Structural Steel - DetailsDanny Chenspecial
05/07/2025Wood – Seismic ResistanceNARESH MAHANGUspecial
05/07/2025FinalPETER CHOprogress
05/07/2025Footing and FoundationDanny Chenprogress
05/07/2025Energy Code Compliance InspectionsDanny Chenprogress
05/07/2025Fire-Resistance Rated ConstructionDanny Chenprogress
05/07/2025Structural Wood FrameDanny Chenprogress
05/07/2025Air barrier — testing Danny Chenenergy_progress
05/07/2025Electric vehicle service equipment requirementsDanny Chenenergy_progress
05/07/2025Air barrier - visual inspectionDanny Chenenergy_progress
05/07/2025Fenestration air leakageDanny Chenenergy_progress
05/07/2025Fenestration areasDanny Chenenergy_progress
05/07/2025Interior lighting powerDanny Chenenergy_progress
05/07/2025Fenestration and door U-factor and product ratingsDanny Chenenergy_progress
05/07/2025HVAC-R and service water piping design and insulationDanny Chenenergy_progress
Latest 25 of 34.
▾Documents — 72 on file (BIS + DOB NOW)
▸Plans & Drawings6
▸DOB NOWPlans/Sketch6
08/20/2026Q01167223-I1Request digital key ↗
08/20/2026Q01202295-I1Request digital key ↗
08/19/2026Q01221901-S1Request digital key ↗
Showing 3 of 6 on file for this type
▸Applications & Permits5
▸BISPLAN / WORK APPROVAL APPLICATION2
08/20/2025440823272Open ↗
05/15/2025421842741Open ↗
▸BISBPP-5 - Authorization to the Department of Transportation2
12/15/2025440823272Open ↗
08/20/2025440823272Open ↗
▸BISPLAN - WORK & PERMITS - SUPPPORTING DOCUMENTATION1
10/24/2025421842741Open ↗
▸Zoning, Tax Lot & Property Records7
▸DOB NOWZD1: DOB Zoning Diagram2
08/19/2026Q01221901-P1Open ↗
08/13/2026Q01221901-I1Open ↗
▸DOB NOWZoning Exhibit form (1-5)2
08/19/2026Q01221901-P1Open ↗
08/13/2026Q01221901-I1Open ↗
▸BISTAX LOT: FINAL LOT NUMBER ISSUED1
12/01/2025421842741Open ↗
▸BISTAX LOT: TENTATIVE LOT NUMBER ISSUED1
08/20/2025440823272Open ↗
▸DOB NOWHouse Number Verification: TOPO Stamp1
08/13/2026Q01221901-I1Open ↗
▸Seals & Professional Certifications14
▸DOB NOWDPL-1: Design Professional Seal & Signature6
08/19/2026Q01221901-S2Open ↗
08/19/2026Q01221901-S1Open ↗
08/19/2026Q01221901-I1Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature3
08/25/2026Q01221901-I1Open ↗
08/25/2026Q01221901-I1Open ↗
08/25/2026Q01221901-I1Open ↗
▸DOB NOWProgress Inspector Seal & Signature3
08/25/2026Q01221901-I1Open ↗
08/25/2026Q01221901-I1Open ↗
08/25/2026Q01221901-I1Open ↗
▸BISAPPLICANT OWNER SIGNATURE1
08/20/2025440823272Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY1
08/20/2025440823272Open ↗
▸Trade Schedules & Equipment4
▸DOB NOWElectric Cut-Off1
08/13/2026Q01167223-I1Open ↗
▸DOB NOWWater Cut-Off1
08/13/2026Q01167223-I1Open ↗
▸DOB NOWSewer Cut-Off1
08/13/2026Q01167223-I1Open ↗
▸DOB NOWGas Cut-Off1
08/13/2026Q01167223-I1Open ↗
▸Safety & Tenant Protection6
▸BISSTREET TREE CHECKLIST2
12/02/2025440823272Open ↗
08/20/2025440823272Open ↗
▸DOB NOWStreet Tree Checklist2
08/19/2026Q01221901-P1Open ↗
08/13/2026Q01221901-I1Open ↗
▸BISBPP: STREET TREES SITE PLAN1
12/02/2025440823272Open ↗
▸DOB NOWParks Department Acknowledgment Letter for Street Trees Plan1
08/13/2026Q01221901-I1Open ↗
▸Environmental & Asbestos2
▸DOB NOWRodent Control1
08/13/2026Q01167223-I1Open ↗
▸DOB NOWDEP ACP-5: Asbestos Assessment Report1
08/13/2026Q01167223-I1Open ↗
▸Inspections & Test Reports3
▸DOB NOWSOIL REPORT2
08/19/2026Q01221901-P1Open ↗
08/13/2026Q01221901-I1Open ↗
▸DOB NOWTR4 Test Report and Plot Diagram1
08/13/2026Q01221901-I1Open ↗
▸Approvals, Objections & Sign-offs3
▸BISLETTERS - SUPPORTING DOCUMENTATION3
10/24/2025421842741Open ↗
10/24/2025421842741Open ↗
10/24/2025421842741Open ↗
▸Filing & Intake Forms6
▸BISADDITIONAL INFORMATION2
12/15/2025440823272Open ↗
10/24/2025421842741Open ↗
▸BISEFILING COVER SHEET2
10/24/2025421842741Open ↗
05/19/2025421842741Open ↗
▸BISEFILING JOB APPLICATION COVER SHEET1
08/20/2025440823272Open ↗
▸BISBOROUGH INTAKE FORM1
05/15/2025421842741Open ↗
▸Other Documents16
▸DOB NOWProperty Ownership Certification3
08/19/2026Q01221901-I1Open ↗
08/19/2026Q01221901-P1Open ↗
08/13/2026Q01167223-I1Open ↗
▸DOB NOWSite Survey: Initial2
08/19/2026Q01221901-P1Open ↗
08/13/2026Q01221901-I1Open ↗
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone2
08/19/2026Q01221901-P1Open ↗
08/13/2026Q01221901-I1Open ↗
▸BISRECORDS MGMT FEE PAYMENT RECEIPT1
08/20/2025440823272Open ↗
▸BISPLOT DIAGRAM1
10/24/2025421842741Open ↗
▸BISBPP - SUPPORTING DOCUMENTATION1
08/20/2025440823272Open ↗
▸BISCURB CUT: PROVIDE EXISTING NUMBER1
12/02/2025440823272Open ↗
▸BISBPP: PHOTOS-SIGNED/SEALED BY APPLICANT1
12/02/2025440823272Open ↗
▸DOB NOWAdjoining Owners Notification1
08/13/2026Q01221901-I1Open ↗
▸DOB NOWStructure Photographs1
08/13/2026Q01167223-I1Open ↗
▸DOB NOWFull Demo: 10-Day Notice1
08/13/2026Q01167223-I1Open ↗
▸DOB NOWCommunity Board Notification1
08/13/2026Q01167223-I1Open ↗