← Back
BuildNYC
BROOKLYN
The 125 Metropolitan Condominium
90 NORTH 3RD STREET · BIN 3425618
💬 Discuss this project
—Year Built
—Stories
—Building Class
—Zoning
—Gross Floor Area
—Units
0 Active ViolationsFDNY Report ↗
Flood zone X
Locations of Work
ArchitectureStructuralMechanicalPlumbingFire ProtectionGeneralOther
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
RoofBoulevard Together Developer LLC20p · 5 filings · 20 docs
BulkheadBoulevard Together Developer LLC2p · 1 filing · 12 docs
Floor 5Cadman Associates LLC2p · 1 filing · 2 docs
Floor 4Cadman Associates LLC2p · 1 filing · 2 docs
Floor 3Cadman Associates LLC2p · 1 filing · 2 docs
Floor 2Cadman Associates LLC2p · 1 filing · 2 docs
Floor 1Removery72p · 17 filings · 20 docs
MezzanineCadman Associates LLC10p · 1 filing · 8 docs
Site & exteriorRemovery2p · 2 filings · 7 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
Cadman Associates4507/08/2026
Boulevard Together Developer2907/08/2026
125 Metropolitan Owner1603/21/2026
84 North Street Realty803/21/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
10/07/2015$10.0M—— → —— not available
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
Leon Skvirsky PE202/14/2023
EP Engineering211/03/2022
Acertus Consulting Group410/26/2022
Epoch Design Group108/18/2022
Concept Design Group303/23/2022
JDJ Engineering403/07/2022
Lawler + Co. Architects1002/15/2022
Jose L. Pena, P.E107/01/2020
Niego Associates104/22/2019
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
JM Zoning2003/21/2026
Louis Striar203/21/2026
New York Sign Consultants203/21/2026
Building Brothers403/21/2026
Milrose Consultants503/21/2026
Municipal Building Consultants203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
Alchemy DevelopmentGeneral Contractor603/21/2026
Windecker ConstructionGeneral Contractor603/21/2026
Select Commercial Construction*General Contractor507/08/2026
Paul SignsSign hanger207/08/2026
Bedrock Plumbing & HeatingPlumbing207/08/2026
Active SignsSign hanger107/08/2026
Mauceri Sign CoSign hanger107/08/2026
Bruche Mechanical NYFire Protection107/08/2026
Dependable MechanicalFire Protection107/08/2026
EH Plumbing & HeatingPlumbing107/08/2026
Tavella PLG HeatingFire Protection107/08/2026
Empire State ElectlElectrical103/21/2026
Village P & H NYPlumbing107/08/2026
Pags Electrical ContngElectrical103/22/2026
Fresh Aire Mechanicalspecialty_contractor107/08/2026
KSK Construction GroupGeneral Contractor103/22/2026
Capitol Fire SprinklerPlumbing103/22/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
EP Inspections and Commis7079211/03/2022
Catalpa Special Inspectio2004310/26/2022
CDG Architects LLC /Dba1327303/23/2022
JDJ Engineering6780403/07/2022
Integrity Consulting Service666502/02/2022
Building Lifecycle
All (187)Filed (28)Permit Issued (17)Signed Off (18)Violation (39)Inspection (9)Objection (46)Special Inspection (30)
01/05/2026
Violation issued (ECB, closed)
Elevators
08/05/2024
Violation issued (HPD, closed)
A
10/22/2023
Violation issued (HPD, closed)
A
10/22/2023
Violation issued (HPD, closed)
B
10/22/2023
Violation issued (HPD, closed)
B
10/22/2023
Violation issued (HPD, closed)
B
10/22/2023
Violation issued (HPD, closed)
A
04/20/2023
Signed off — Alteration
NEW SPACE WITH INSTALLATION OF NEW PLUMBING FIXTURES, SANITARY/VENT PIPING FROM FIXTURES, DOMESTIC WATER PIPING TO FIXTURES, AND ELECTRIC WATER HEATER/ RECIRCULATION. no change in use, egress or occupancy under this application.
B00787138-I1
04/20/2023
Signed off — Alteration
modification to existing HVAC system as per plans filed herewith. no change in use, egress or occupancy under this application.
B00787097-I1
03/20/2023
Signed off — Alteration
removal and installation of non bearing partition as per plans filed herewith. no change in use, egress or occupancy under this application.
B00786178-I1
03/09/2023
Signed off — Alteration
INSTALL INTERIOR ILLUMINATED WINDOW SIGN ( REMOVERY)
B00819553-I1
02/15/2023
Permit issued — Sign
B00819553-I1-SG
02/14/2023
Filed — Alteration
INSTALL INTERIOR ILLUMINATED WINDOW SIGN ( REMOVERY)
B00819553-I1
01/30/2023
Signed off — Alteration
INSTALL EXTERIOR NON-ILLUMINATED BLADE SIGN (UNIKWAX)
B08031712-I1
01/26/2023
Special inspection requirement — Final
LEON SKVIRSKY
01/04/2023
Signed off — Alteration
Installation of mechanical units as per plans filed herewith. No change to use, egress or occupancy.
B08004762-I1
12/09/2022
Permit issued — Sign
B08031712-I1-SG
12/09/2022
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
12/07/2022
Filed — Alteration
INSTALL EXTERIOR NON-ILLUMINATED BLADE SIGN (UNIKWAX)
B08031712-I1
11/15/2022
Violation issued (HPD, closed)
I
11/15/2022
Special inspection requirement — Interior lighting power
ERIC BERLENT
11/15/2022
Special inspection requirement — Final
ERIC BERLENT
11/15/2022
Special inspection requirement — Duct leakage testing, insulation and design
ERIC BERLENT
11/15/2022
Special inspection requirement — Lighting controls
ERIC BERLENT
11/15/2022
Special inspection requirement — Mechanical Systems
ERIC BERLENT
11/15/2022
Special inspection requirement — Ventilation and air distribution system
ERIC BERLENT
11/15/2022
Special inspection requirement — Energy Code Compliance Inspections
ERIC BERLENT
11/14/2022
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
11/04/2022
Special inspection requirement — Fire-Resistant Penetrations and Joints
Christopher Burgess
11/04/2022
Special inspection requirement — Mechanical Systems
Christopher Burgess
11/04/2022
Special inspection requirement — Maintenance information
Christopher Burgess
11/04/2022
Special inspection requirement — HVAC-R and service water heating equipment
Christopher Burgess
11/04/2022
Special inspection requirement — Duct leakage testing, insulation and design
Christopher Burgess
11/04/2022
Special inspection requirement — Post-installed Anchors
Christopher Burgess
11/04/2022
Special inspection requirement — HVAC-R and service water heating system controls
Christopher Burgess
11/04/2022
Special inspection requirement — Energy Code Compliance Inspections
Christopher Burgess
11/04/2022
Special inspection requirement — HVAC-R and service water piping design and insulation
Christopher Burgess
11/04/2022
Special inspection requirement — Final
Christopher Burgess
11/03/2022
Filed — Alteration
Installation of mechanical units as per plans filed herewith. No change to use, egress or occupancy.
B08004762-P1
11/03/2022
Objection resolved — Addressed
11/01/2022
Objection raised — Other
11/01/2022
Special inspection requirement — Final
LEON SKVIRSKY
10/26/2022
Filed — Alteration
NEW SPACE WITH INSTALLATION OF NEW PLUMBING FIXTURES, SANITARY/VENT PIPING FROM FIXTURES, DOMESTIC WATER PIPING TO FIXTURES, AND ELECTRIC WATER HEATER/ RECIRCULATION. no change in use, egress or occupancy under this application.
B00787138-P1
10/26/2022
Filed — Alteration
modification to existing HVAC system as per plans filed herewith. no change in use, egress or occupancy under this application.
B00787097-P1
10/25/2022
Special inspection requirement — Interior lighting power
ERIC BERLENT
10/25/2022
Special inspection requirement — Mechanical Systems
ERIC BERLENT
10/25/2022
Special inspection requirement — Duct leakage testing, insulation and design
ERIC BERLENT
10/25/2022
Special inspection requirement — Energy Code Compliance Inspections
ERIC BERLENT
10/25/2022
Special inspection requirement — Final
ERIC BERLENT
10/25/2022
Special inspection requirement — Lighting controls
ERIC BERLENT
10/25/2022
Special inspection requirement — Ventilation and air distribution system
ERIC BERLENT
10/20/2022
Special inspection requirement — Maintenance information
Christopher Burgess
10/20/2022
Special inspection requirement — HVAC-R and service water heating equipment
Christopher Burgess
10/20/2022
Special inspection requirement — HVAC-R and service water piping design and insulation
Christopher Burgess
10/20/2022
Special inspection requirement — HVAC-R and service water heating system controls
Christopher Burgess
10/12/2022
Permit issued — Mechanical Systems
B08004762-I1-MS
10/11/2022
Permit issued — Mechanical Systems
B00787097-I1-MS
10/03/2022
Filed — Alteration
Installation of mechanical units as per plans filed herewith. No change to use, egress or occupancy.
B08004762-I1
09/29/2022
Permit issued — Plumbing
B00787138-I1-PL
08/19/2022
Filed — Alteration
NEW SPACE WITH INSTALLATION OF NEW PLUMBING FIXTURES, SANITARY/VENT PIPING FROM FIXTURES, DOMESTIC WATER PIPING TO FIXTURES, AND ELECTRIC WATER HEATER/ RECIRCULATION. no change in use, egress or occupancy under this application.
B00787138-I1
Latest 60 of 187 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSignSigned-offPaul Signs02/15/2023
DOB NOWSignSigned-offPaul Signs12/09/2022
DOB NOWMechanical SystemsPermit IssuedSelect Commercial Construction*10/12/2022
DOB NOWMechanical SystemsSigned-offWindecker Construction10/11/2022
DOB NOWPlumbingSigned-offBedrock Plumbing & Heating09/29/2022
DOB NOWMechanical SystemsSigned-offAlchemy Development06/09/2022
DOB NOWSprinklersSigned-offDependable Mechanical12/07/2021
DOB NOWPlumbingSigned-offEH Plumbing & Heating10/07/2021
DOB NOWGeneral ConstructionSigned-offAlchemy Development10/04/2021
DOB NOWSprinklersSigned-offTavella PLG Heating02/25/2021
DOB NOWMechanical SystemsSigned-offFresh Aire Mechanical12/02/2020
DOB NOWSignSigned-offActive Signs07/30/2020
DOB NOWMechanical SystemsSigned-offSelect Commercial Construction*06/10/2020
DOB NOWMechanical SystemsSigned-offSelect Commercial Construction*03/24/2020
DOB NOWPlumbingSigned-offVillage P & H NY03/23/2020
DOB NOWSprinklersSigned-offBruche Mechanical NY10/10/2019
DOB NOWSignSigned-offMauceri Sign Co04/22/2019
BISOTISSUEDKimba Industries03/19/2020
BISOTISSUEDSelect Commercial Construction*03/13/2020
BISOTISSUEDTsang Construction10/30/2019
BISPLISSUEDSo Plumbing & Heating06/10/2019
BISPLISSUEDVillage P & H NY06/05/2019
BISOTISSUEDBroadway Builders05/13/2019
BISMHISSUEDSelect Commercial Construction*04/04/2019
BISOTISSUEDSelect Commercial Construction*04/04/2019
BISMHISSUEDMujko Renovation01/14/2019
BISOTISSUEDMujko Renovation10/30/2018
BISPLISSUEDCrown Plumbing10/10/2018
BISOTISSUEDMujko Renovation10/03/2018
BISOTISSUEDKSK Construction Group08/28/2018
BISSPISSUEDCopper Services02/12/2018
BISPLISSUEDCopper Services01/24/2018
BISCCISSUEDKSK Construction Group11/16/2017
BIS—RE-ISSUEDKSK Construction Group10/16/2017
BIS—ISSUEDKSK Construction Group10/16/2017
BISEQISSUEDColgate Enterprise09/01/2017
BISEQISSUEDKSK Construction Group05/15/2017
BISSPISSUEDCopper Services02/13/2017
BISPLISSUEDCopper Services01/05/2017
BIS—ISSUEDKSK Construction Group10/18/2016
+ 17 more permits on file
9 projects · most recent 02/20/2023
General Wiring Lighting
FiledStatusContractorScope
02/20/2023CompleteEmpire State Electl—
10/12/2022CompleteM & M Control WiringGeneral Wiring
06/03/2022CompleteDelta Power ElectricalGeneral Wiring
08/19/2020CompletePags Electrical ContngGeneral Wiring
03/27/2020CompleteCorporate Electric GroupGeneral Wiring
09/18/2019CompleteW 8 ElectricGeneral Wiring
06/10/2019CompleteL.J.F. & Sons Electrical ContsGeneral Wiring
05/20/2019CompleteBDS ElectricGeneral Wiring, Lighting
09/12/2018CompleteKwong Ming ElectricGeneral Wiring
▾Field Inspections (DOB CAP) — 9
DateTypeResultReport
12/09/2022Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
11/14/2022Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
04/20/2022Certified Medical Gas - MG - PL - RoughingCertifiedView ↗
04/20/2022Certified Medical Gas - MG - PL - TestCertifiedView ↗
04/19/2022Fail-Final PL - Up to 3 Requested FloorsFailView ↗
04/08/2022Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
03/08/2022Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
01/28/2022Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
12/10/2021Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 67
DateRequirementInspectorRole
01/26/2023FinalLEON SKVIRSKYprogress
11/15/2022Mechanical SystemsERIC BERLENTspecial
11/15/2022FinalERIC BERLENTprogress
11/15/2022Energy Code Compliance InspectionsERIC BERLENTprogress
11/15/2022Interior lighting powerERIC BERLENTenergy_progress
11/15/2022Lighting controlsERIC BERLENTenergy_progress
11/15/2022Duct leakage testing, insulation and designERIC BERLENTenergy_progress
11/15/2022Ventilation and air distribution systemERIC BERLENTenergy_progress
11/04/2022HVAC-R and service water heating equipmentChristopher Burgessenergy_progress
11/04/2022Maintenance informationChristopher Burgessenergy_progress
11/04/2022HVAC-R and service water piping design and insulationChristopher Burgessenergy_progress
11/04/2022HVAC-R and service water heating system controlsChristopher Burgessenergy_progress
11/04/2022Post-installed AnchorsChristopher Burgessspecial
11/04/2022Fire-Resistant Penetrations and JointsChristopher Burgessspecial
11/04/2022Mechanical SystemsChristopher Burgessspecial
11/04/2022FinalChristopher Burgessprogress
11/04/2022Energy Code Compliance InspectionsChristopher Burgessprogress
11/04/2022Duct leakage testing, insulation and designChristopher Burgessenergy_progress
11/01/2022FinalLEON SKVIRSKYprogress
10/25/2022Mechanical SystemsERIC BERLENTspecial
10/25/2022Lighting controlsERIC BERLENTenergy_progress
10/25/2022Ventilation and air distribution systemERIC BERLENTenergy_progress
10/25/2022Interior lighting powerERIC BERLENTenergy_progress
10/25/2022Duct leakage testing, insulation and designERIC BERLENTenergy_progress
10/25/2022FinalERIC BERLENTprogress
Latest 25 of 67.
▾Tenants in the building
TenantSpaceFloorsRenovation projects
RemoveryPersonal servicesFloor 1
Project B00819553 Alteration · LOC Issued · 02/14/2023
Project B00787097 Alteration · LOC Issued · 08/19/2022
Project B00787138 Alteration · LOC Issued · 08/19/2022
Project B00786178 Alteration · LOC Issued · 08/18/2022
Names are taken automatically from the text of each project’s filed documents (title blocks and cover sheets) and screened to exclude owners, landlords and designers. They may be incomplete or wrong; check the filing.
▾Documents — 635 on file (BIS + DOB NOW)
▸Plans & Drawings26
▸DOB NOWPlans/Sketch15
09/01/2026B00587341-I1Request digital key ↗
08/31/2026B00635143-I1Request digital key ↗
08/31/2026B00635143-P2Request digital key ↗
Showing 3 of 15 on file for this type
▸DOB NOWPlans/Sketch - Mechanical Systems5
09/02/2026B00255121-I1Request digital key ↗
09/02/2026B00289594-I1Request digital key ↗
09/02/2026B00422061-P1Request digital key ↗
Showing 3 of 5 on file for this type
▸DOB NOWPlans/Sketch - Sprinkler3
09/02/2026B00204033-I1Request digital key ↗
09/02/2026B00425911-P1Request digital key ↗
09/02/2026B00425911-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Sign2
09/02/2026B00153371-I1Request digital key ↗
09/02/2026B00324946-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Plumbing1
09/02/2026B00301759-I1Request digital key ↗
▸Applications & Permits103
▸BISPLAN / WORK APPROVAL APPLICATION52
08/05/2024320626765Open ↗
08/05/2024320626765Open ↗
08/09/2021340457400Open ↗
Showing 3 of 52 on file for this type
▸BISWORK PERMIT APPLICATION41
03/21/2020322031387Open ↗
03/18/2020322030967Open ↗
10/31/2019321945115Open ↗
Showing 3 of 41 on file for this type
▸BISPLAN - WORK & PERMITS - SUPPPORTING DOCUMENTATION7
01/12/2021322039012Open ↗
10/21/2019321945115Open ↗
10/21/2019321945115Open ↗
Showing 3 of 7 on file for this type
▸BISBPP-5 - Authorization to the Department of Transportation3
07/11/2018340211256Open ↗
Showing 1 of 3 on file for this type
▸Zoning, Tax Lot & Property Records5
▸BISZONING RESOLUTION DETERMINATION3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸BISADDRESS - NEW HOUSE NUMBER APPROVED1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISZONING EXHIBIT III:DESC. & OWNRSHP.STMNT1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Seals & Professional Certifications123
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION40
03/21/2020322031387Open ↗
03/17/2020321939426Open ↗
03/17/2020321939426Open ↗
Showing 3 of 40 on file for this type
▸DOB NOWProgress Inspector Seal & Signature30
09/01/2026B08004762-P1Open ↗
09/01/2026B08004762-P1Open ↗
08/30/2026B00422061-P1Open ↗
Showing 3 of 30 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature26
09/02/2026B00153371-I1Open ↗
09/02/2026B00422061-P1Open ↗
09/02/2026B00422061-I1Open ↗
Showing 3 of 26 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature11
09/01/2026B08004762-P1Open ↗
08/30/2026B00422061-P1Open ↗
08/29/2026B00255121-P1Open ↗
Showing 3 of 11 on file for this type
▸BISAPPLICANT OWNER SIGNATURE5
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 5 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT5
04/02/2019321939426Open ↗
04/02/2019321939426Open ↗
Showing 2 of 5 on file for this type
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸Trade Schedules & Equipment32
▸BISSCHEDULE B - PLUMBING12
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 12 on file for this type
▸BISEQUIPMENT USE PERMITS4
03/17/2020321939426Open ↗
03/17/2020321939426Open ↗
03/17/2020321939426Open ↗
Showing 3 of 4 on file for this type
▸BISFA - FDNY APPROVAL : FD-FAA3
11/25/2019321939408Open ↗
Showing 1 of 3 on file for this type
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE3
04/29/2019321945115Open ↗
07/27/2018321738474Open ↗
Showing 2 of 3 on file for this type
▸BISEQUIPMENT USE APPLICATION/PERMIT3
03/17/2020321939426Open ↗
Showing 1 of 3 on file for this type
▸BISSEWER/HOUSE CON SIGNOFF: DEP HC 0212
08/22/2018320626765Open ↗
08/22/2018320626765Open ↗
▸BISDETECTOR:SMOKE-CERT. OF INSTALLATION2
04/18/2024320626765Open ↗
Showing 1 of 2 on file for this type
▸BISSEWER CUT-OFF1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISDEP SANITARY SEWER CERTIFICATION (HCP/SCP)1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISSCHEDULE C - HEATING & COMBUSTION EQUIPMENT1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Safety & Tenant Protection31
▸DOB NOWTenant Protection Plan9
09/02/2026B00422061-I1Open ↗
09/02/2026B00422061-P1Open ↗
09/02/2026B00425911-I1Open ↗
Showing 3 of 9 on file for this type
▸BISSTREET TREES: RECEIPT OF STREET TREES SITE PLAN6
09/16/2019320626765Open ↗
09/16/2019320626765Open ↗
09/05/2019320626765Open ↗
Showing 3 of 6 on file for this type
▸BISSTREET TREE CHECKLIST5
02/22/2020322039012Open ↗
09/16/2019320626765Open ↗
04/03/2019340211256Open ↗
Showing 3 of 5 on file for this type
▸BISTenant Protection Plan and Notes4
02/14/2020322031387Open ↗
01/23/2020322030967Open ↗
04/29/2019321945115Open ↗
Showing 3 of 4 on file for this type
▸BISSTREET TREE SUPPORTING DOCUMENT3
09/16/2019320626765Open ↗
09/05/2019320626765Open ↗
Showing 2 of 3 on file for this type
▸BISEXCAVATION OR DEMOLITION: 5-DAY NOTICE2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISANTI-HARASSMENT CHECKLIST1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸DOB NOWHPD-1: Anti-Harassment Area Checklist1
08/13/2026B00819553-I1Open ↗
▸Environmental & Asbestos10
▸BISENVIRONMENTAL RESTRICTIONS - OER NOTICE TO PROCEED5
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 5 on file for this type
▸BISENVIRONMENTAL RESTRICTIONS - OER NOTICE OF SATISFACTION2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸DOB NOWDEP ACP-5: Asbestos Assessment Report2
08/28/2026B08004762-I1Open ↗
08/13/2026B08004762-P1Open ↗
▸BISRODENT CONTROL1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Energy Compliance30
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS13
03/21/2020322031387Open ↗
03/18/2020322030967Open ↗
03/17/2020321939426Open ↗
Showing 3 of 13 on file for this type
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY8
08/12/2021322031387Open ↗
07/30/2021322031387Open ↗
01/20/2021322030967Open ↗
Showing 3 of 8 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS4
01/20/2021322030967Open ↗
03/17/2020321939426Open ↗
02/01/2019321738474Open ↗
Showing 3 of 4 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS (EN2)2
08/12/2021322031387Open ↗
10/14/2020321945115Open ↗
▸DOB NOWEN2: As Built Energy Analysis.2
08/15/2026B00574812-I1Open ↗
08/13/2026B00787097-I1Open ↗
▸BISELECTRICAL APPLICATION FOR SIDEWALK SHED LIGHTING1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Inspections & Test Reports27
▸BISTECHNICAL REPORT: RESPONSIBILITY17
08/12/2021322031387Open ↗
07/30/2021322031387Open ↗
01/20/2021322030967Open ↗
Showing 3 of 17 on file for this type
▸BISTECHNICAL REPORT: CONCRETE DESIGN MIX4
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 4 on file for this type
▸BISTECHNICAL REPORT: CONCRETE/TEST CYLINDER4
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 4 on file for this type
▸BISHYDRAULIC FLOW CALCULATIONS1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISTR2: CONCRETE TEST CYLINDERS TECHNICAL REPORT1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Approvals, Objections & Sign-offs82
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST44
08/13/2021322031387Open ↗
08/10/2021340457400Open ↗
02/08/2021320626765Open ↗
Showing 3 of 44 on file for this type
▸BISLETTERS - SUPPORTING DOCUMENTATION22
06/11/2019320626765Open ↗
02/01/2019321738474Open ↗
11/27/2018340429165Open ↗
Showing 3 of 22 on file for this type
▸BISSCHEDULE A - OCCUPANCY / USE8
08/06/2024320626765Open ↗
08/05/2024320626765Open ↗
02/22/2020322039012Open ↗
Showing 3 of 8 on file for this type
▸BISSUPERSEDING LETTER3
10/30/2019321945115Open ↗
Showing 1 of 3 on file for this type
▸BISADMINISTRATIVE OBJECTIONS2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISCONSTRUCTION CODE DETERMINATION2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISHPD: INCLUSIONARY HOUSING LETTER1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Cost, Insurance & Ownership27
▸BISCOST AFFIDAVIT17
10/14/2020321945115Open ↗
04/02/2020321939408Open ↗
03/17/2020321939426Open ↗
Showing 3 of 17 on file for this type
▸BISPROJECT-SPECIFIC GL INSURANCE5
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 5 on file for this type
▸BISAcord 25 (Acord Certificate of Liability Insurance)3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸BISCOST AFFIDAVIT (FINAL): PW32
08/12/2021322031387Open ↗
01/21/2021322030967Open ↗
▸Filing & Intake Forms100
▸BISBOROUGH INTAKE FORM38
04/02/2020321939408Open ↗
03/28/2020320626765Open ↗
03/17/2020321939426Open ↗
Showing 3 of 38 on file for this type
▸BISADDITIONAL INFORMATION37
08/05/2021322031387Open ↗
07/22/2021322031387Open ↗
11/12/2019321945115Open ↗
Showing 3 of 37 on file for this type
▸BISEFILING COVER SHEET17
02/22/2020322039012Open ↗
01/27/2020322031387Open ↗
01/23/2020322030967Open ↗
Showing 3 of 17 on file for this type
▸BISEFILING JOB APPLICATION COVER SHEET8
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 8 on file for this type
▸Other Documents11
▸BISPLOT DIAGRAM5
02/20/2020322039012Open ↗
07/02/2019320626765Open ↗
Showing 2 of 5 on file for this type
▸BISEXTERNAL FORMS - SUPPORTING DOCUMENTATION4
07/30/2021322031387Open ↗
Showing 1 of 4 on file for this type
▸BISENVIRONMENTAL "E" DEP NOTICE OF SATISFACTION1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISCOMMUNITY BOARD NOTIFICATION1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type