| Owner | Filings | Most Recent |
|---|---|---|
| SAFELINE GROUP | 6 | 07/08/2026 |
| METRO CONTRACTING NY | 9 | 03/22/2026 |
| HP BUILDING MANAGEMENT IN | 9 | 03/22/2026 |
| B 4 S SUCCESS GROUP | 1 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| BRICOLAGE DESIGNS | 12 | 06/19/2024 |
| MJE PROFESSIONAL SERVICES | 2 | 07/13/2023 |
| ENTHINK ENGINEERS LLC | 3 | 06/07/2023 |
| BGM ENGINEERING | 1 | 03/25/2022 |
| Representative | Filings | Most Recent |
|---|---|---|
| BRICOLAGE DESIGNS | 13 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| HP BUILDING MANAGEMENT IN | General Contractor | 15 | 07/08/2026 |
| METRO CONTRACTING NY, INC. | General Contractor | 2 | 03/21/2026 |
| RRP PLUMBING CORP | Fire Protection | 1 | 07/08/2026 |
| SAFELINE GROUP INC | General Contractor | 1 | 07/08/2026 |
| RRP PLUMBING CORP | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| SJS INSPECTIONS AND CONSU | 8286 | 6 | 06/19/2024 |
| CENTURY TESTING & CONSULT | 4081 | 7 | 01/04/2024 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Permit Issued | ANGELINE PENA-LEVI | 02/07/2024 |
| DOB NOW | Mechanical Systems | Signed-off | ANGELINE PENA-LEVI | 01/12/2024 |
| DOB NOW | Construction Fence | Signed-off | ANGELINE PENA-LEVI | 07/06/2023 |
| DOB NOW | Supported Scaffold | Signed-off | SAFELINE GROUP INC | 06/19/2023 |
| DOB NOW | Sprinklers | Signed-off | RALPH W. LANDOLFI JR. | 06/17/2023 |
| DOB NOW | Plumbing | Signed-off | RRP PLUMBING CORP | 02/09/2023 |
| DOB NOW | Sidewalk Shed | Signed-off | METRO CONTRACTING NY, INC. | 02/06/2023 |
| DOB NOW | Structural | Permit Issued | ANGELINE PENA-LEVI | 01/23/2023 |
| DOB NOW | Support of Excavation | Signed-off | ANGELINE PENA-LEVI | 08/18/2022 |
| DOB NOW | General Construction | Permit Issued | ANGELINE PENA-LEVI | 07/21/2022 |
| DOB NOW | Construction Fence | Signed-off | ANGELINE PENA-LEVI | 07/08/2022 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 06/19/2024 | Permit Issued | HP BUILDING MANAGEMENT IN | Heating Systems |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/03/2024 | Complete | APPROVED ELECTRIC CORP. | General Wiring |
| 12/30/2023 | Complete | KENNETH FISK ELECTRIC COR | General Wiring |
| 02/04/2023 | Complete | RICHARD NEU | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/19/2024 | Permit Issued | HP BUILDING MANAGEMENT IN | Steel, Concrete, Masonry |
| Date | Type | Result | Report |
|---|---|---|---|
| 06/03/2024 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 05/15/2024 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 03/27/2024 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 03/07/2024 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 01/26/2024 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 01/26/2024 | Pass-Final PL - Underground | Pass | View ↗ |
| 01/26/2024 | Pass-Final PL - Up to 9 Requested Floors | Pass | View ↗ |
| 01/02/2024 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 12/19/2023 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 09/08/2023 | Pass-Final PL - Up to 9 Requested Floors | Pass | View ↗ |
| 02/16/2023 | Pass-Final PL - Underground | Pass | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 07/12/2024 | HVAC-R and service water heating equipment | SERGEY BOLOTOV | energy_progress |
| 07/12/2024 | Fenestration air leakage | SERGEY BOLOTOV | energy_progress |
| 07/12/2024 | Maintenance information | SERGEY BOLOTOV | energy_progress |
| 07/12/2024 | Fenestration areas | SERGEY BOLOTOV | energy_progress |
| 07/12/2024 | Permanent certificate | SERGEY BOLOTOV | energy_progress |
| 07/12/2024 | Lighting in dwelling units | SERGEY BOLOTOV | energy_progress |
| 07/12/2024 | Air barrier - visual inspection | SERGEY BOLOTOV | energy_progress |
| 07/12/2024 | HVAC-R and service water heating system controls | SERGEY BOLOTOV | energy_progress |
| 07/12/2024 | Interior lighting power | SERGEY BOLOTOV | energy_progress |
| 07/12/2024 | Exterior lighting power | SERGEY BOLOTOV | energy_progress |
| 07/12/2024 | Insulation placement and R values | SERGEY BOLOTOV | energy_progress |
| 07/12/2024 | Lighting controls | SERGEY BOLOTOV | energy_progress |
| 07/12/2024 | Final | SERGEY BOLOTOV | progress |
| 07/12/2024 | Footing and Foundation | SERGEY BOLOTOV | progress |
| 07/12/2024 | Energy Code Compliance Inspections | SERGEY BOLOTOV | progress |
| 07/12/2024 | Fire-Resistance Rated Construction | SERGEY BOLOTOV | progress |
| 07/12/2024 | Heating Systems | SERGEY BOLOTOV | special |
| 07/12/2024 | Subgrade Inspections | SERGEY BOLOTOV | special |
| 07/12/2024 | Concrete - Cast-In-Place | SERGEY BOLOTOV | special |
| 07/12/2024 | Masonry | SERGEY BOLOTOV | special |
| 07/12/2024 | Mechanical Systems | SERGEY BOLOTOV | special |
| 07/12/2024 | Structural Cold-Formed Steel | SERGEY BOLOTOV | special |
| 07/12/2024 | Structural Steel - Details | SERGEY BOLOTOV | special |
| 07/12/2024 | Structural Steel - High Strength Bolting | SERGEY BOLOTOV | special |
| 07/12/2024 | Fire-Resistant Penetrations and Joints | SERGEY BOLOTOV | special |