← Back
General warehouse
900 SHEPHERD AVENUE
BROOKLYN · BIN 3097865
💬 Discuss this project
1964Year Built
1Stories
E1Building Class
M1-1Zoning
13,700 sfGross Floor Area
1Units
General warehouse · Owner of record: 900 SHEPHERD LLC · 16,000 sf lot · 0.86 FAR built · Flood zone X500
Locations of Work
MechanicalPlumbingGeneral
Roof2p · 1 filing · 9 docs
Floor 14p · 1 filing · 9 docs
Mezzanine3p · 1 filing · 9 docs
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
11/29/2022$5.7M—— → —$415/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
BAZINI ENGINEERING, P.C.205/07/2024
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
HI-TECH HEATING CORPGeneral Contractor203/21/2026
CROSSFIELD PLBG.&HTGPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
BAZINI ENGINEERING, P.C.1808205/07/2024
Building Lifecycle
All (11)Filed (2)Permit Issued (2)Signed Off (2)Inspection (2)Special Inspection (3)
02/21/2025
Signed off — Alteration
EXISTING GAS PIPING TO EXISTING GAS FIXTURES TO BE REPAIRED, AS REQUIRED, IN ORDER TO RESTORE GAS SERVICE. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
B01036579-I1
06/27/2024
Signed off — Alteration
EXISTING GAS PIPING TO EXISTING GAS FIXTURES TO BE REPAIRED, AS REQUIRED, IN ORDER TO RESTORE GAS SERVICE. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
B01036579-S1
05/14/2024
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
05/14/2024
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
05/08/2024
Permit issued — Plumbing
B01036579-S1-PL
05/08/2024
Permit issued — Mechanical Systems
B01036579-I1-MS
05/07/2024
Filed — Alteration
EXISTING GAS PIPING TO EXISTING GAS FIXTURES TO BE REPAIRED, AS REQUIRED, IN ORDER TO RESTORE GAS SERVICE. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
B01036579-S1
05/06/2024
Filed — Alteration
EXISTING GAS PIPING TO EXISTING GAS FIXTURES TO BE REPAIRED, AS REQUIRED, IN ORDER TO RESTORE GAS SERVICE. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
B01036579-I1
05/06/2024
Special inspection requirement — HVAC-R and service water heating equipment
Joseph Bazini
04/16/2024
Special inspection requirement — Mechanical Systems
Joseph Bazini
04/16/2024
Special inspection requirement — Final
Joseph Bazini
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingSigned-offCROSSFIELD PLBG.&HTG05/08/2024
DOB NOWMechanical SystemsSigned-offHI-TECH HEATING CORP05/08/2024
BIS—ISSUEDPRO CONCRETE CONTRACTORS CORP.08/01/1996
BIS—ISSUEDPRO CONCRETE CONTRACTORS CORP.03/22/1995
BIS—ISSUEDPRO CONCRETE CONTRACTORS CORP.09/14/1993
BIS—ISSUEDPRO CONCRETE CONTRACTORS10/20/1992
Nothing on file for this building.
▾Field Inspections (DOB CAP) — 2
DateTypeResultReport
05/14/2024Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
05/14/2024Pass-Final PL - Up to 3 Requested FloorsPassView ↗
▾Special Inspection Requirements (DOB NOW) — 3
DateRequirementInspectorRole
05/06/2024HVAC-R and service water heating equipmentJoseph Bazinienergy_progress
04/16/2024Mechanical SystemsJoseph Bazinispecial
04/16/2024FinalJoseph Baziniprogress
▾Documents — 9 on file (BIS + DOB NOW)
▸Plans & Drawings2
▸DOB NOWPlans/Sketch2
08/25/2026B01036579-S1Request digital key ↗
08/25/2026B01036579-I1Request digital key ↗
▸Seals & Professional Certifications5
▸DOB NOWDPL-1: Design Professional Seal & Signature2
08/13/2026B01036579-I1Open ↗
08/13/2026B01036579-S1Open ↗
▸DOB NOWProgress Inspector Seal & Signature2
08/23/2026B01036579-I1Open ↗
08/23/2026B01036579-I1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature1
08/23/2026B01036579-I1Open ↗
▸Environmental & Asbestos1
▸DOB NOWDEP ACP-5: Asbestos Assessment Report1
08/13/2026B01036579-S1Open ↗
▸Energy Compliance1
▸DOB NOWPreliminary Commissioning Report Certification1
08/13/2026B01036579-I1Open ↗