| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 06/04/2024 | $867K | — | Private party → Private party | $510/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| MIB CONSULTING | 3 | 02/24/2023 |
| Representative | Filings | Most Recent |
|---|---|---|
| KING DAVID ARCHITECTURE | 6 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| EAST ENDERS NYC INC | General Contractor | 3 | 03/21/2026 |
| MORELL BUILDERS INC | General Contractor | 3 | 03/21/2026 |
| SAMUEL & SONS P & H INC | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| MARKANICS CORP | 4600 | 3 | 02/24/2023 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Signed-off | EAST ENDERS NYC INC | 06/23/2022 |
| DOB NOW | Plumbing | Signed-off | SAMUEL & SONS P & H INC | 05/05/2022 |
| Date | Type | Result | Report |
|---|---|---|---|
| 03/09/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 12/07/2022 | Pass-Final General Construction Non-Directive 14 | Pass | View ↗ |
| 11/28/2022 | Fail-Final General Construction Non-Directive 14 | Fail | View ↗ |
| 11/15/2022 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 07/13/2022 | Fail-Final General Construction Non-Directive 14 | Fail | View ↗ |
| 05/10/2022 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 05/10/2022 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 05/10/2022 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 03/07/2023 | HVAC-R and service water heating equipment | Malcolm Barkan | energy_progress |
| 03/07/2023 | HVAC-R and service water heating system controls | Malcolm Barkan | energy_progress |
| 03/07/2023 | Permanent certificate | Malcolm Barkan | energy_progress |
| 03/07/2023 | HVAC-R and service water piping design and insulation | Malcolm Barkan | energy_progress |
| 03/07/2023 | Fire-Resistant Penetrations and Joints | Malcolm Barkan | special |
| 03/07/2023 | Energy Code Compliance Inspections | Malcolm Barkan | progress |
| 03/07/2023 | Maintenance information | Malcolm Barkan | energy_progress |
| 02/20/2023 | Maintenance information | Malcolm Barkan | energy_progress |
| 02/20/2023 | HVAC-R and service water piping design and insulation | Malcolm Barkan | energy_progress |
| 02/20/2023 | HVAC-R and service water heating system controls | Malcolm Barkan | energy_progress |
| 02/20/2023 | Permanent certificate | Malcolm Barkan | energy_progress |
| 02/20/2023 | HVAC-R and service water heating equipment | Malcolm Barkan | energy_progress |
| 02/20/2023 | Fire-Resistant Penetrations and Joints | Malcolm Barkan | special |
| 02/20/2023 | Energy Code Compliance Inspections | Malcolm Barkan | progress |
| 04/20/2022 | Fenestration air leakage | Malcolm Barkan | energy_progress |
| 04/20/2022 | Interior lighting power | Malcolm Barkan | energy_progress |
| 04/20/2022 | Fenestration areas | Malcolm Barkan | energy_progress |
| 04/20/2022 | Fire-Resistant Penetrations and Joints | Malcolm Barkan | special |