← Back
Two stories - detached, small or mid-size
91-48 109 STREET
QUEENS · Richmond Hill · BIN 4195451
💬 Discuss this project
1920Year Built
2Stories
A1Building Class
R6AZoning
1,350 sfGross Floor Area
1Units
0 Open ViolationsFDNY Report ↗
Two stories - detached, small or mid-size · 2,000 sf lot · 0.68 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralElectricalPlumbingGeneral
Roof2p · 1 filing · 11 docs
Floor 21p · 1 filing · 11 docs
Floor 1
Filed — no permit issued8p · 1 filing · 3 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
HOMING NYC LLC203/22/2026
HAMING NYC LLC103/22/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
12/17/2018$621K—HOMING NYC LLC → Private party$460/sf building
05/31/2017$160K—— → —$119/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
TRINITY SOLAR LLC202/18/2026
PARKER AND WEST ENGINEERING, PLLC110/24/2024
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
SUNRUN103/21/2026
ACA ASSOCIATES203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
TRINITY SOLAR LLCGeneral Contractor104/09/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
BITOPI CONSULTANTS LLC7036202/18/2026
PARKER AND WEST ENGINEERI5272110/24/2024
Building Lifecycle
All (16)Filed (3)Permit Issued (1)Signed Off (1)Violation (7)Special Inspection (4)
02/25/2026
Signed off — Alteration
Installation of solar system on the roof as per plan. No change in use, egress or occupancy
Q01215494-I1
02/18/2026
Filed — Alteration
Installation of solar system on the roof as per plan. No change in use, egress or occupancy
Q01215494-P1
02/18/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
KAMRUL AHSAN
02/18/2026
Special inspection requirement — Energy Code Compliance Inspections
Ayracon Almaraz
02/18/2026
Special inspection requirement — Final
Ayracon Almaraz
02/18/2026
Special inspection requirement — Air barrier - visual inspection
Ayracon Almaraz
05/12/2025
Permit issued — Solar
Q01215494-I1-SL
04/28/2025
Filed — Alteration
Installation of solar system on the roof as per plan. No change in use, egress or occupancy
Q01215494-I1
10/24/2024
Filed — Alteration
FILING HEREWITH TAX ABATEMENT APPLICATION FOR INSTALLATION OF ROOF MOUNTED SOLAR PANELS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
Q01123296-I1
03/17/2018
Violation issued (ECB, closed)
Construction
03/07/2018
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
01/31/2018
Violation issued (ECB, closed)
Construction
12/05/2017
Violation issued (ECB, closed)
Construction
01/30/2013
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
10/29/2012
Violation issued (ECB, closed)
Construction
10/29/2012
Violation issued (ECB, closed)
Construction
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarSigned-offTRINITY SOLAR LLC05/12/2025
2 projects · most recent 07/10/2025
FiledStatusContractorScope
07/10/2025CompleteREDLINE ELECTRIC INC1 meters
10/24/2024Permit IssuedSUNRUN SOLAR ELECTL CORP—
1 project · most recent 10/24/2024
FiledStatusContractorScope
10/24/2024——16 panels, 6.56 kw, 338.1 roof_area_sqft
▾Special Inspection Requirements (DOB NOW) — 4
DateRequirementInspectorRole
02/18/2026Fire-Resistant Penetrations and JointsKAMRUL AHSANspecial
02/18/2026Energy Code Compliance InspectionsAyracon Almarazprogress
02/18/2026FinalAyracon Almarazprogress
02/18/2026Air barrier - visual inspectionAyracon Almarazenergy_progress
▾Documents — 14 on file (BIS + DOB NOW)
▸Plans & Drawings3
▸DOB NOWPlans/Sketch3
08/21/2026Q01123296-I1Request digital key ↗
08/17/2026Q01215494-I1Request digital key ↗
08/17/2026Q01215494-P1Request digital key ↗
▸Seals & Professional Certifications7
▸DOB NOWDPL-1: Design Professional Seal & Signature3
08/17/2026Q01215494-I1Open ↗
08/17/2026Q01215494-P1Open ↗
08/13/2026Q01123296-I1Open ↗
▸DOB NOWProgress Inspector Seal & Signature3
08/23/2026Q01215494-P1Open ↗
08/23/2026Q01215494-P1Open ↗
08/23/2026Q01215494-P1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature1
08/23/2026Q01215494-P1Open ↗
▸Environmental & Asbestos3
▸DOB NOWDEP ACP-5: Asbestos Assessment Report3
08/17/2026Q01215494-P1Open ↗
08/17/2026Q01215494-I1Open ↗
08/13/2026Q01123296-I1Open ↗
▸Approvals, Objections & Sign-offs1
▸DOB NOWUtility Company Final Acceptance Letter1