One story - permanent living quarter
91 ARTHUR AVENUE
STATEN ISLAND · Grasmere-Arrochar-South Beach-Dongan Hills · BIN 5045723
💬 Discuss this project
1910Year Built
1.5Stories
A2Building Class
R3-1Zoning
1,100 sfGross Floor Area
1Units
4 Open Violations 3 unresolved · 1 paperwork only ▸FDNY Report ↗
One story - permanent living quarter · Owner of record: 360BUILDERSNYC LLC · 3,100 sf lot · 0.35 FAR built · Flood zone X
Locations of Work
ArchitectureMechanicalCivilGeneralOther
Filed — no permit issued7p · 2 filings · 10 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
360 BUILDERS NYC LLC903/22/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
AVID DESIGNS, INC205/11/2021
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
AVID DESIGNS, INC.453104/23/2021
Building Lifecycle
All (41)Filed (2)Violation (11)Objection (12)Special Inspection (16)
09/20/2022
Special inspection requirement — Lowest Floor Elevation
01/14/2022
Objection raised — Zoning
01/14/2022
Objection resolved — Resolved
01/14/2022
Objection raised — Zoning
01/14/2022
Objection resolved — Resolved
01/14/2022
Objection raised — Zoning
01/14/2022
Objection resolved — Addressed
01/14/2022
Objection raised — Zoning
01/14/2022
Objection resolved — Resolved
01/14/2022
Objection raised — Zoning
01/14/2022
Objection raised — Fire_Protection
01/14/2022
Objection resolved — Resolved
09/03/2021
Violation issued (ECB, closed)
Construction
06/23/2021
Violation issued (ECB, open)
Construction
05/11/2021
Filed — Alteration
S00505501-I1
05/10/2021
Objection raised — Scope
04/26/2021
Violation issued (ECB, closed)
Construction
04/23/2021
Filed — Alteration CO
S00502778-I1
04/16/2021
Special inspection requirement — Concrete - Cast-In-Place
Jeffrey Geary
04/16/2021
Special inspection requirement — Excavations - Sheeting, Shoring, and Bracing
Jeffrey Geary
04/16/2021
Special inspection requirement — Fire-Resistant Penetrations and Joints
Jeffrey Geary
04/16/2021
Special inspection requirement — Subgrade Inspections
Jeffrey Geary
04/16/2021
Special inspection requirement — Final
04/16/2021
Special inspection requirement — Footing and Foundation
04/16/2021
Special inspection requirement — Fenestration areas
Jeffrey Geary
04/16/2021
Special inspection requirement — Air barrier — testing
Jeffrey Geary
04/16/2021
Special inspection requirement — Insulation placement and R values
Jeffrey Geary
04/16/2021
Special inspection requirement — HVAC-R and service water piping design and insulation
Jeffrey Geary
04/16/2021
Special inspection requirement — Air barrier - visual inspection
Jeffrey Geary
04/16/2021
Special inspection requirement — Fenestration air leakage
Jeffrey Geary
04/16/2021
Special inspection requirement — Interior lighting power
Jeffrey Geary
04/16/2021
Special inspection requirement — Structural Stability – Alterations of existing buildings
04/16/2021
Special inspection requirement — Fenestration and door U-factor and product ratings
Jeffrey Geary
02/23/2021
Violation issued (ECB, closed)
Construction
02/23/2021
Violation issued (ECB, closed)
Construction
01/08/2021
Violation issued (ECB, closed)
Construction
01/06/2021
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
01/06/2021
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
12/29/2020
Violation issued (ECB, closed)
Construction
10/10/2020
Violation issued (ECB, open)
Construction
10/10/2020
Violation issued (ECB, open)
Construction
Nothing on file for this building.
1 project · most recent 04/23/2021
FiledStatusContractorScope
04/23/2021——1 scope_items
▾Special Inspection Requirements (DOB NOW) — 16
DateRequirementInspectorRole
09/20/2022Lowest Floor Elevation—progress
04/16/2021Concrete - Cast-In-PlaceJeffrey Gearyspecial
04/16/2021Excavations - Sheeting, Shoring, and BracingJeffrey Gearyspecial
04/16/2021Fire-Resistant Penetrations and JointsJeffrey Gearyspecial
04/16/2021Subgrade InspectionsJeffrey Gearyspecial
04/16/2021Final—progress
04/16/2021Footing and Foundation—progress
04/16/2021Fenestration areasJeffrey Gearyenergy_progress
04/16/2021Air barrier — testing Jeffrey Gearyenergy_progress
04/16/2021Insulation placement and R valuesJeffrey Gearyenergy_progress
04/16/2021HVAC-R and service water piping design and insulationJeffrey Gearyenergy_progress
04/16/2021Air barrier - visual inspectionJeffrey Gearyenergy_progress
04/16/2021Fenestration air leakageJeffrey Gearyenergy_progress
04/16/2021Interior lighting powerJeffrey Gearyenergy_progress
04/16/2021Structural Stability – Alterations of existing buildings—special
04/16/2021Fenestration and door U-factor and product ratingsJeffrey Gearyenergy_progress
▾Documents — 18 on file (BIS + DOB NOW)
▸Plans & Drawings1
▸DOB NOWPlans/Sketch1
08/25/2026S00505501-I1Request digital key ↗
▸Applications & Permits2
▸BISPLAN / WORK APPROVAL APPLICATION1
02/03/2023540244573Open ↗
▸BISBPP-5 - Authorization to the Department of Transportation1
02/09/2023540244573Open ↗
▸Zoning, Tax Lot & Property Records2
▸DOB NOWZD1: DOB Zoning Diagram1
08/13/2026S00502778-I1Open ↗
▸DOB NOWZoning Exhibit form (1-5)1
08/13/2026S00502778-I1Open ↗
▸Seals & Professional Certifications3
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY1
02/03/2023540244573Open ↗
▸BISAPPLICANT OWNER SIGNATURE1
02/03/2023540244573Open ↗
▸DOB NOWDPL-1: Design Professional Seal & Signature1
08/25/2026S00505501-I1Open ↗
▸Safety & Tenant Protection1
▸DOB NOWStreet Tree Checklist1
08/13/2026S00502778-I1Open ↗
▸Inspections & Test Reports2
▸BISBPP-9 - Request for Builders Pavement Field Inspection1
02/03/2023540244573Open ↗
▸BISTECHNICAL REPORT: RESPONSIBILITY1
02/03/2023540244573Open ↗
▸Approvals, Objections & Sign-offs1
▸BISBPP-8 - Request Items for Builders Pavement Plan Signoff1
02/09/2023540244573Open ↗
▸Filing & Intake Forms1
▸BISEFILING JOB APPLICATION COVER SHEET1
02/03/2023540244573Open ↗
▸Other Documents5
▸BISBPP - SUPPORTING DOCUMENTATION2
02/09/2023540244573Open ↗
02/03/2023540244573Open ↗
▸BISBPP: PHOTOS-SIGNED/SEALED BY APPLICANT1
02/09/2023540244573Open ↗
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone1
08/13/2026S00502778-I1Open ↗
▸DOB NOWPlot Diagram1
08/13/2026S00502778-I1Open ↗